An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERT 422/4 Piping and instrumentation diagram (P&id) MISS. RAHIMAH BINTI OTHMAN (Email: rahimah@unimap.edu.my)

  2. QUIZ1 QUESTION 1: • Which of the following statements are true? • Feedback and feedforward control both require measured variable. • The process variable to be controlled is measured in feedback control. • Feedforward control can be perfect in the theoretical sense that the controller can take action via the manipulated even while the controlled variable remains equal to its desired value. • Feedforward control can provide perfect control; that is, the output can be kept at its desired value, even with an imperfect process model. • Feedback control will always take action regardless of the accuracy of any process model that was used to design it and the source of a disturbance. False/True False/True False/True False/True False/True

  3. QUIZ1 QUESTION 2: Ethanol-water mixture is feed to a batch distillation column. This distillation process will produce ethanol vapour at the top product which then condensate to produce liquid ethanol which will be collected into a distillate product tank. The liquid ethanol and an acetic acid liquid from the acid feed tank are then feed to a reactor. An exothermic reaction process will be occurred to produce ethyl acetate (a type of ester). Draw BFD for this process.

  4. BOILER PIPING AND INSTRUMENTATION DIAGRAM (P&ID) QUESTION 3: • Figure below shows the boiler system that used to supply hot steam to a turbine. This system need to supply 100 psi hot steam to the turbine where the PCV-100 will be opened when the pressure reached that desired pressure. With using pressure control through temperature measurement in the boiler, draw a feedforward loop control system. Hot steam Water PCV-100 Process variable need to be controlled = Pressure

  5. QUIZ1 QUESTION 1: • Which of the following statements are true? • Feedback and feedforward control both require measured variable. • The process variable to be controlled is measured in feedback control. • Feedforward control can be perfect in the theoretical sense that the controller can take action via the manipulated even while the controlled variable remains equal to its desired value. • Feedforward control can provide perfect control; that is, the output can be kept at its desired value, even with an imperfect process model. • Feedback control will always take action regardless of the accuracy of any process model that was used to design it and the source of a disturbance. False/True False/True False/True False/True False/True

  6. The Block Flow Diagram (BFD) Answer 1: Hot water out Condenser Ethanol liq. Reactor Ethyl acetate Batch distillation Distillate product tank Cold water in Ethanol-water mixture Acid feed tank

  7. BOILER TIC TT PI PIPING AND INSTRUMENTATION DIAGRAM (P&ID) Answer 1 • Figure below shows the boiler system that used to supply hot steam to a turbine. This system need to supply 100 psi hot steam to the turbine where the PCV-100 will be opened when the pressure reached that desired pressure. With using pressure control through temperature measurement in the boiler, draw a feedforward loop control system. Y Hot steam Water Process variable need to be controlled = Pressure

More Related