1 / 20

Instrument Overview and System Engineering

This document provides an overview of the Alice instrument, including its requirements, system engineering, and risk management. It compares Rosetta Alice with New Horizons Alice and discusses the preliminary design review topics.

jerald
Download Presentation

Instrument Overview and System Engineering

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Instrument Overview and System Engineering John Scherrer Jscherrer@swri.edu (210) 522-3363 July 24, 2002 Alice Preliminary Design Review

  2. Topics • Requirements • Instrument overview • S/C interface • Rosetta Alice vs. New Horizons Alice • Resources • System Engineering • Risk Management Alice Preliminary Design Review

  3. Top Level Requirement • The ALICE sensor shall obtain ultraviolet spectral maps over a 520 Å -1870 Å bandpass. The spectral resolution shall be 1.7 Å per spectral element. The FOV shall be 6° x 0.1º and the spatial resolution shall be 5 mrad/pixel. ALICE shall accommodate a solar occultation channel. * From section 3.3 of Mission Science Definition document Alice Preliminary Design Review

  4. Flowdown of Requirements Alice Preliminary Design Review

  5. General Description Alice is an integrated UV spectrograph composed of the following major elements: • A 41 x 65 mm off-axis paraboloidal primary telescope mirror. • A 50 x 50 mm toroidal holographic diffraction grating. • A 2-D imaging photon-counting microchannel plate (MCP) detector assembly with vacuum cover/window assembly. • Two entrance apertures: Airglow and Solar Occultation • Electronics that include: • Microcontroller and C&DH electronics • Double Delay line detector electronics • Driver circuitry for actuators / heaters / switches, etc. • Redundant high voltage power supplies • Redundant low voltage power converters These elements are all packaged in a highly-baffled aluminum housing. Alice Preliminary Design Review

  6. Mechanical Layout Slit Assembly Detector Zero Order Trap Grating OAP Mirror Baffles SOC Pick-off Mirror Aperture Opening Solar Occultation Channel Aperture Door (Shown Open) Alice Preliminary Design Review

  7. Simplified Block Diagram Alice Preliminary Design Review

  8. Optical Path Detector Zero Order Trap Grating Failsafe Door (Shown Closed) Aperture Opening OAP Mirror Slit Assembly Solar Occultation Channel (SOC) Aperture Door (Shown Open) SOC Pick-off Mirror Baffles Alice Preliminary Design Review

  9. Rosetta Alice Alice Preliminary Design Review

  10. Modes of Operation • Histogram – builds up 1024 x 32 (spectral vs. spatial) array 16 bits deep. Primarily used for Airglow observations. • Pixel List – Photon counting mode where the location of each photon event on the detector array (i.e. spectral and spatial location) is stored and transmitted. Time hacks are inserted to provide temporal resolution. This is primary mode of operation for Solar Occultation. Alice Preliminary Design Review

  11. Interface Summary (1 of 2) • Mechanical: • Hard mounted to S/C (or S/C bracket) • FOV is “aligned” with other optical instruments. • Alignment: • Alice SOC shall be aligned to HGA (REX) within 0.23º (knowledge to 0.02º). Will use in-flight calibration to re-verify alignment. • Thermal: • Desire to be at S/C temperature and coupled to S/C as much as possible (to minimize heater requirements). • Blankets cover most of exposed surfaces of Alice. (FOV’s are clear). Alice Preliminary Design Review

  12. Interface Summary (2 of 2) • Electrical: • Alice uses standard High Speed (LVDS) and Low Speed (UART) instrument interfaces. • Max telemetry rate is 480 kbits/sec (includes margin) which will occur during Solar Occultation (30 ksamples/sec). • Alice is equipped with SA 3865 microcontroller which allows for instrument flexibility and simplifies S/C interface. • Microcontroller minimizes number of needed commands. • Alice releases all doors via S/C telecommand • Alice has internal autonomous safing functions (that can be disabled). • Other: • Alice (as with all UV instruments) is contamination sensitive and will impose requirements on the spacecraft and other instruments. • GN2 (Grade C or 99.999%) purge through launch is required. Alice Preliminary Design Review

  13. New Horizons Alice vs. Rosetta Alice(1 of 2) • Environments: • NH is slightly wider temperature range. • NH is higher radiation environment. • Currently, NH loads are higher than as tested for on Rosetta. • Duration of the NH mission is longer though ON time is less. • Optical: • Identical optics and detector • Slightly different bandpass required moving detector • Electrical: • NH requires ping-pong memory. • For increased reliability, NH Alice has redundant LVPS and HVPS. • LVPS is custom design rather than hybrid. • Instrument controls actuators rather than spacecraft. • Different spacecraft interface. Alice Preliminary Design Review

  14. New Horizons Alice vs. Rosetta Alice(2 of 2) • Mechanical: • On NH, pyro’s are not allowed. Switched to wax pellet and shape memory alloy actuators. • Added Solar Occultation Channel aperture and pick off mirror. • Pump out tube length reduced. • Thermal: • Very similar thermal design. • Software: • NH is simpler spacecraft interface. • Simpler operations (reduced modes of operation and simpler requirements). • Testing: • Very similar plan and series of tests. Alice Preliminary Design Review

  15. Resources • Mass: • Current Best Estimate = 3.86 kg • Mature value (with uncertainty 12.6%) = 4.35 kg • Values are known and approved by project. • Power (data acquisition mode): • Current Best Estimate = 4.74 watts • Mature value (with uncertainty 15%) = 5.45 kg • Assumes 65% efficiency of LVPS • Current allocation is 5.64 watts • TM Rate • Maximum expected rate is 480 kbps • This rate is based on highest expected count rate during Solar Occultation plus margin. • S/C capability on TM interface is 16 Mbps. Alice Preliminary Design Review

  16. System Engineering • Main responsibilities: • Verification of technical requirements • DOORS, Verification Plan, Test Procedures • Management of technical resources • Monthly reports • Oversight and control of system interfaces • ICD’s, specs, Div. 15 Change Control process • John Stone is lead of System Engineering • Dave Slater (Proj. Scientist), as well as PM and subsystem leads support SE activities. Alice Preliminary Design Review

  17. Risk Management: Process • We are transitioning to use of Web-based Risk Management Tracking System from more traditional spreadsheet system. • Similar to NAIMS (New Horizons Action Item Management System) • Automatically emails responsible person for updating of status of risk item and mitigation plans. • Risks ranked by Consequence and Likelihood. • Mitigation Plans with trigger dates included. • Team is polled weekly for their “worries”. • Risks are statused monthly. Alice Preliminary Design Review

  18. Top 5 Current Risks Alice Preliminary Design Review

  19. Reynolds 600 HV Connector Discussion Alice Preliminary Design Review

  20. Backup Material • Alice Instrument Performance Specification (Draft) • Mechanical Interface Control Drawing (Draft) • Thermal Interface Control Drawing (Draft) • Fault Tree • Project Schedule • Contamination Control Plan • Verification Test Plan • Radiometric Calibration Plan • Software Development Plan • Software Requirements Document (Draft) • Preliminary Structural Analysis • Preliminary Thermal Analysis Alice Preliminary Design Review

More Related