190 likes | 279 Views
FRA-70-3.41 VE Workshop. Why are we here? What is the process ? What is the timeframe ? What to expect? What is the end result? Will we get out early ?. Introductions & Set-up. Why are we here?
E N D
Why are we here? • What is the process? • What is the timeframe? • What to expect? • What is the end result? • Will we get out early? Introductions & Set-up
Why are we here? • Federal law requires a VE analysis on projects meeting a $50 million dollar threshold, or stand alone bridge projects greater than $40 million. • Benefits – return of 100:1 on VE workshops Introductions & Set-up
What’s the Process? • Identify projects meeting thresholds • Hold VE workshop at optimum time in development • Create report based on VE workshop • Hold Implementation Board meeting • Incorporate results into project Introductions & Set-up
What’s the timeframe? • Hold workshop • Draft report following VE workshop – 2 weeks • Final report including comments from VE team – 2 weeks • Implementation board meeting – 45 days • Add to plans Introductions & Set-up
What to expect? • Information Phase • Function Analysis • Creative Phase • Evaluation Phase • Development Phase • Report Out Introductions & Set-up
Project Briefing • Project background • Review existing project documentation • Review cost estimate • Design constraints • Project challenges • Project timeline – design and construction • Current project status Information Phase
What is the Purpose and Need? • What is the core function? • Key design elements? Function Analysis
Noun – Verb Association • Assign functions of major project components • Cost Model – 80% of cost in 20% of items Function Analysis
All ideas are good, until the evaluation phase • Adding value can be: • Saving money • Improving safety • Speeding construction • Making construction easier • Using better materials • Improving operations • Simplifying maintenance • Reducing environmental impacts • Reducing right-of way impacts. Creative Phase
What’s off limits? • Pavement type. • Can we close Interstate 70? • ? Creative Phase
Common VECP Ideas • Subgrade stabilization • Sheeting / Retaining wall design • Steel beams vs. concrete • Revise profile to balance earthwork • Lime stabilization to geotextile • Use MSE walls • Use precast floor beams • New storm water layout • Cutting existing bridge deck into smaller single span beams • Revised bridge design from multiple span to single span on MSE walls Creative Phase
Rate generated ideas to select those that will be further developed. Evaluation Phase
Time to work • Develop selected ideas to determine feasibility, prepare cost estimates and compare to original design • Cost estimate Development Phase