TG3c Closing Report January 2008 Taipei

This report provides a summary of the TG3c meeting held in January 2008 in Taipei, including attendance, meeting accomplishments, upcoming schedule, and the timeline for the project.

Download Presentation

TG3c Closing Report January 2008 Taipei

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project: IEEE P802.15 Working Group for Wireless Personal Area Networks (WPANs) Submission Title: [TG3c Closing Report January 2008 Taipei] Date Submitted: [17 January 2008] Source: [Reed Fisher] Company [Oki Electric Industry Co., Ltd.] Address [2514 E. Maddox Rd., Buford, GA 30519 USA.] Voice:[1-770-271-0529] E-Mail:[reedfisher@juno.com] Re : [] Abstract:[Description of TG3c January 2008 meeting reports ] Purpose:[Report to 802.15 Closing Interim Meeting, 17 January 2008] Notice :This document has been prepared to assist the IEEE P802.15. It is offered as a basis for discussion and is not binding on the contributing individual(s) or organization(s). The material in this document is subject to change in form and content after further study. The contributor(s) reserve(s) the right to add, amend or withdraw material contained herein. Release:The contributor acknowledges and accepts that this contribution becomes the property of IEEE and may be made publicly available by P802.15. R. Fisher, Oki Electric Industry co. Ltd

  2. TG3c 17th Meeting, Taipei TaiwanClosing Report 17 January, 2008

  3. 13:30Monday, January 14. Call to order. • TG3c Leadership: Chair: R. Fisher. vice Chair: S. Kato Secretary : H. Ikeda , T. Baykas, C.S. Sum • Technical Editor: J. Gilb • Sub Editors: A. Astrin, S. Skafidas, I. Lakkis, C. Ngo, T. Baykas, C.S. Sum, • A. Kasher, B. Gaffney • 3. Attendance • Approx. 80 attendees in each slot. • 4. Eleven 2-hour time slots are allocated、and nine slots were used. • 5. 12:00January 17 Meeting adjourned

  4. Meeting Accomplishments R. Fisher, Oki Electric Industry co. Ltd

  5. Record of Motion Ballot Motion: (Time: Jan. 17, 2008, AM1) • To accept changes provided in documents 08/0056r1, 08/0066r1. • These changes shall be included in the draft document version DF1 Motion by J. Gilb Second by S. Kato Ballot result: Yes: 49, No: 0, Abstain: 0 Motion carried R. Fisher, Oki Electric Industry co. Ltd

  6. Upcoming schedule/calls • DF1 posted by February 15 AOE. • Conference call #1 • 20 February, 2008, 9 am KST/JST, 1.5 hours duration. • Hosted by NICT • Conference call #2 • 4 March, 2008, 6 am PST, 1.5 hours duration • Hosted by Intel. R. Fisher, Oki Electric Industry co. Ltd

  7. List of Contributions R. Fisher, Oki Electric Industry co. Ltd

  8. Plan to Get to Baseline Document 08/076r0 • January 2008: Draft baseline document was presented. Future plan: • February and March 2008: Conference calls • March 2008: Resolve open issues, and approve draft for WG letter ballot • March-May 2008: WG letter ballot R. Fisher, Oki Electric Industry co. Ltd

  9. Ballot plan 08/076r0 • May 2008 – First letter ballot completed, start comment resolution • September 2008 – Resolution of comments completed, begin re-circulation ballot • November 2008 – re-circulation ballot completed, comment resolution, and Start Sponsor ballot • January 2009 – 802 Sponsor Ballot completed, comment resolution, start recirculation ballot • March 2009 – 802 Sponsor Ballot re-circulation completed and, submit to RevCom for final approval • May 2009 – Approval by RevCom R. Fisher, Oki Electric Industry co. Ltd

  10. TG3c Timeline Project timeline based on 08/0076r0 R. Fisher, Oki Electric Industry co. Ltd