Schedule for UB production & quality requirements L.P.C.C. COLLEGE DE FRANCE Stephane COLONGES September 2001
Schedule for UB production & quality requirements - LPCC CDF - Sept. 2001 • Schedule for UB pre-production & production. • Quality requirements for Unified Board pre-production & production.
Schedule for production - LPCC CDF - September 2001 • Since August 24th, 2001 : public tender is published (European restricted procedure). • November 2001 : after the 1st candidates selection, the specification document will be sent. AT THIS TIME THE DESIGN HAS TO BE FINISHED!!!
Schedule for production - LPCC CDF - September 2001 • January 2002 : selection of the better offer, taking in consideration the production schedule, costs and quality insurance. • Before March 2002, we want test our first prototype « UB » with PMT Bases, a complete FE, Led flasher, and all other parts. • We can not start the industrial production without this tests!
Schedule for production - LPCC CDF - September 2001 1st Industrials prototypes : *03/02 : 2 prototypes *04/02 : 8 prototypes Pre-production of 120 UB units Public tender published 1st UB Tests with all parts 20 UB units sent to labs & 100 UB units in Argentina for integration / installation in the Pampa 1st UB prototype conception We must define all UB`s specifications, as well for all other parts Industrials prototypes tests in laboratory & Malargue L.A.L. Test Bench Specifications document sent to candidates Offer selection 09/01 10/01 11/01 12/01 01/02 02/02 03/02 04/02 05/02 06/02 07/02 08/02 09/02 10/02
Schedule for production - LPCC CDF - September 2001 Production of 900 UB Production of 800 UB Installation of 600 UB in Pampa Pre-production evaluation (final tests) Integration / Installation of 900 UB in Pampa Production evaluation 11/02 12/02 01/03 02/03 03/03 04/03 05/03 06/03 07/03 08/03 09/03 10/03 11/03 12/03 01/04 02/04 03/04 05/04 06/04
Schedule for production - LPCC CDF - September 2001 This schedule depend on : • Component availability • Budget possibility • Prototypes testing approbation • Factory disponibility • We must define all UB specifications
Quality requirements for Unified Board - LPCC CDF - Sept. 2001 • Quality insurance : In our public tender we have asked for the ISO 9000 quality insurance (or equivalent), technical and man power resources, tests procedures, production logging system and boards backtracking. • The boards reliability is defined by the MIL-HDBK-217F standard (ground fixed conditions) • The MTBF index is determined and must be equal to the Auger life time.
09/01 10/01 11/01 12/01 01/02 02/02 03/02 04/02 05/02 06/02 07/02 08/02 09/02 10/02