All Experimenters’ Meeting. November 11, 2013. Accelerator Operation Summary. From : November 4, 2013 (0000 hours) To: November 11, 2013 (0000 hours). Calendar Week # 45 NuMI Weekly Integrated Intensity 5.84 E18 protons
E N D
All Experimenters’ Meeting November 11, 2013
Accelerator Operation Summary From : November 4, 2013 (0000 hours) To: November 11, 2013 (0000 hours) Calendar Week # 45 NuMI Weekly Integrated Intensity 5.84 E18 protons BNB Weekly Integrated Intensity 5.33 E18 protons NMuonWeekly Integrated Intensity 1.67 E14 protons MTest Weekly Integrated Intensity 1.61 E14 protons Beam Hours To NuMI121.6 hours Beam Hours To BNB124.4hours Beam Hours To NMuon 54.0 hours Beam Hours To MTest 58.5hours
Status /Work Completed/Plans • Proton Source • Tuning and Maintenance • Swapped sources • Main Injector • Access for Recycler restriction • Tuning and Maintenance • Recycler • Beam pipe alignment @ 215 & looked in beampipe at 308/309 • Found alphasorb in 308 location • Recycler RF used to capture beam • Beginning commissioning • BNB • Tuning • Horn off/Beam off target mode • MiniBooNE starts taking beam • NuMI • Tuning
Status /Work Completed/Plans • Switchyard • Tuned extraction and beamline • Foil calibration • Setup slit to NMuon • MTest • Foil Calibration • Tuning • NMuon • Vacuum work and tunnel cleanup complete • Startup sheet, Beam Permit and Running Conditions signed • NMuon startup on Friday • NM1 Box SWIC problem • SWIC partially in the beam • No spare SWIC of this type • SWIC being removed today
Schedules and Links: • Schedule can be accessed from the Operations Home Page • - Schedules -> Operations Schedule • Direct link to schedule • - http://www-ad.fnal.gov/ops/schedule.html