Northeast Reliability Interconnect Project As presented to NEPOOL RC on 7/12/04

Northeast Reliability Interconnect Project As presented to NEPOOL RC on 7/12/04 For 15.5/12C/TCA Approval. Presentation Objective. Address the CMP questions Review updated ISO-NE Congestion analysis 12C/15.5/Transmission Cost Allocation (TCA) motion and approval. Preferred Solution.

jin
Download Presentation

Northeast Reliability Interconnect Project As presented to NEPOOL RC on 7/12/04

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Northeast Reliability Interconnect Project As presented to NEPOOL RC on 7/12/04 For 15.5/12C/TCA Approval

  2. Presentation Objective • Address the CMP questions • Review updated ISO-NE Congestion analysis • 12C/15.5/Transmission Cost Allocation (TCA) motion and approval

  3. Preferred Solution • Northeast Reliability Interconnect Project as 345 kV path between Orrington and Pt. Lepreau Project Includes - • A 345kV transmission line between Orrington and Pt. Lepreau • Mechanically Switched Series Compensation on S388 south of Orrington • 115kV Breaker upgrade at Maxcys due to short circuit currents • Shunt capacitor installation at CMP substations Gulf Island and Kimball Rd • SPS upgrades and changes

  4. ISO-NE Congestion analysis presentation

  5. Benefits of Preferred Solution • Strengthens a section of a very weak 345 kV path • Reduces contingencies that separate Maritime Provinces from Eastern Interconnection • Eliminates GCX SPS • Increases Maritimes to Orrington capability from 700 MW to 1000 MW • Increase in resource capacity and energy available to New England (Orrington South flows due to Orrington-Maxcys series compensation) • Parallel path transmission

  6. Benefits of Preferred Solution • Reduces losses between Orrington and New Brunswick • Facilitates opportunities to improve/create other parallel paths and additional transfers • Provides NEPOOL with improved fuel diversity • Increased New England-New Brunswick transfer capability could provide opportunities for locked-in generation in Maine – especially given Maritimes winter peak • Future potential for increased sharing of ancillary services with New Brunswick

  7. ISO-NE Congestion Analysis • Congestion analysis performed by ISO-NE looking at the addition of the NRI and flow opportunities that are a result of it • Values are cumulative 6 year based on own year values • Cumulative NE Generator Production Cost Savings - $31M • Cumulative NE Net LSE Expense - $99M

  8. Closing • The Northeast Reliability Interconnect is the only alternative available to address all the reliability issues described • The NRI also provides a range of economic opportunities • This line is a critical step in strengthening the northern New England transmission system • FERC has indicated that apportioning the reliability benefits of transmission projects is impractical and thus it is appropriate to socialize the cost of projects to ensure they are constructed • FERC has also noted the value of increasing transfer capability between control areas • It is important to seize the opportunity to construct transmission infrastructure as it is becoming increasingly difficult to acquire required permits • This reliability based project merits 100% regional funding support