LST Installation Readiness Review Mechanical Installation Preparation H. James Krebs May 5, 2004 H.J. Krebs
Mechanical Installation Preparation • IR-12 is the location of most mechanical preparation work during 2004 & 2005 • Why IR-12? • IR-12 Hall is very similar to IR-2 Hall • Same floor plan • Identical 50/10 ton crane combination • We need space • IR-12 was empty • IR-2 is presently occupied with BaBar related items H.J. Krebs
IR-2 H.J. Krebs
IR-12 - Before H.J. Krebs
IR-12 Today H.J. Krebs
IR-12 Activities • Pre-installation preparation of brass plates • Radius corners • Drill & tap threaded holes for slide swivel shackles • Camber plates as needed • Stage plates for assembly • BaBar model • Build a fairly crude but full scale mock-up of the forward end of BaBar including: • Barrel assembly simulating corner blocks removed • FWD end doors • FWD PEP pier H.J. Krebs
Full Scale BaBar Model H.J. Krebs
12” Thick (Z) Sextant Prototype H.J. Krebs
Sextant Iron Cable Channel H.J. Krebs
IR-12 Activities • Purpose of Model • Construct elevator platform • Test function • Check for interferences with end doors, beamline and PEP pier • Load test • Modify as necessary for corrections or improvements • Brass installation preparation • Test installation hardware • Practice brass plate installation • Brass push test • LST detector installation preparation • Test installation hardware • Practice LST detector installation • A full length XZ gap (layer 8) model is being constructed for this H.J. Krebs
IR-12 Activities • Steel handling fixtures • Train technical support staff • Check centers of gravity • Determine appropriate rigging • Load test • Function test, if possible • Modify as needed • Perform a field job hazards analysis H.J. Krebs
Elevator Platform • Due to SLAC internal problems, the purchase req for the elevator platform was issued two months later than planned. • Expect upper elevator components beginning of June • Expect lower elevator components mid June • Still enough time to erect, test and modify these platforms • Very little schedule float remains on these items H.J. Krebs
RPC Pulling Clamps H.J. Krebs
Brass Handling Fixtures • Brass positioners • Purpose • Adjusts the orientation of the brass absorber plates to align with openings in the flux return steel. The positioners for the lower sextant are different than those for the upper sextant. • Needed 2004 • Responsible person • Allen Constable • Status • Design and drawings are complete • Fabrication of upper positioners complete • Fabrication of lower positioners in process • Need to function test using BaBar mock up H.J. Krebs
Upper Brass Positioners H.J. Krebs
Upper Brass Positioners H.J. Krebs
Brass Handling Fixtures • Brass plate pushers • Purpose • To push the brass absorber plates into the gaps in the steel flux return. • Needed 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings are complete • Fabrication is nearing completion • Need to function test using full length XZ gap mock up H.J. Krebs
Brass Plate Pushers H.J. Krebs
24” Brass Plate Pusher H.J. Krebs
Brass Pull Test H.J. Krebs
Brass Pull Test (315.3 lb Plate) H.J. Krebs
Steel Handling Fixtures • Side Gap Plate Fixture • Purpose • Remove and reinstall the side gap plates on the FWD and BWD ends to enable removal of RPCs, installation of brass absorber plates and LSTs, and access to RPC electronics • Needed 2004, 2005 • Responsible person • Jim Krebs • Status • Fabrication complete • CG tested in unloaded and loaded conditions (have used many times in the past) H.J. Krebs
Side Gap Plate Fixture H.J. Krebs
Side Gap Plate Fixture H.J. Krebs
Steel Handling Fixtures • Center Gap Plate Fixture • Purpose • Remove and reinstall the upper and lower center gap plates on the FWD end to enable removal of RPCs and installation of brass absorber plates and LSTs • Needed 2004 • Responsible person • Jim Krebs • Status • Fabrication complete • CG tested in unloaded condition • Rigging procedure and job hazards analysis written and reviewed • Load tested to 168% of design load H.J. Krebs
Center Gap Plate Fixture H.J. Krebs
Center Gap Plate Fixture H.J. Krebs
Center Gap Plate Load Test H.J. Krebs
Center Gap Plate Load Test H.J. Krebs
Center Gap Plate Load Test H.J. Krebs
Steel handling Fixtures • Solenoid Support Arm Fixture • Purpose • Remove and reinstall the upper and lower solenoid support arms on the FWD end used to react axial loads. This will enable removal of the upper and lower FWD corner blocks. • Needed • 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings complete • Fabrication complete • CG tested in unloaded condition • Rigging procedure and job hazards analysis written and reviewed • Load tested to 236% of design load H.J. Krebs
Solenoid Support Arm Fixture H.J. Krebs
Solenoid Support Arm Fixture H.J. Krebs
Solenoid Supt Arm Load Test H.J. Krebs
Steel Handling Fixtures • Corner Block Adaptors • Purpose • Moves corner block rigging connection in Z direction to more convenient location. There are two basic adaptors corresponding to the mid & lower corner blocks and right and left hand units to correspond with east and west. • Needed • 2004 (lower), 2005 (mid & lower) • Responsible person • Jim Krebs • Status • Design and drawings complete for lower adaptor • Fabrication complete • Load tested to 139% H.J. Krebs
Lower Corner Block Adaptor H.J. Krebs
Lower Corner Block Adaptor H.J. Krebs
Steel Handling Fixtures • Adaptor Installation Fixture • Purpose • Used to install and remove the adaptors on the mid & lower corner blocks. • Needed • 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings complete • Fabrication complete • CG tested in unloaded and loaded conditions • Rigging procedure and job hazards analysis written and reviewed • Load testing believed to be unnecessary H.J. Krebs
Adaptor Installation Fixture H.J. Krebs
Steel Handling Fixtures • FWD Lower Corner Block Fixture • Purpose • Supports the FWD lower corner block dead load from crane during removal and reinstallation process. • Needed • 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings complete • Fabrication complete • CG tested in unloaded condition • Rigging procedures and job hazards analysis have been written and reviewed • Load tested to 129% of design load H.J. Krebs
FWD Lower Corner Block Fixture H.J. Krebs
FWD Lower Corner Block fixture H.J. Krebs
Lwr Crnr Blk Fixture Load Test H.J. Krebs
Steel handling Fixtures • BWD Lower Corner Block Fixture • Purpose • Supports the BWD lower corner block dead load from crane during removal and reinstallation process. • Needed • 2004, 2005? • Responsible person • Richard Boyce • Status • Design is in process H.J. Krebs
Steel handling Fixtures • FWD Upper Corner Block Fixture • Purpose • Supports the FWD upper corner block dead load from crane during removal and reinstallation process. • Needed • 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings complete • Fabrication complete • CG tested in unloaded condition • Rigging procedures and job hazards analysis have been written and reviewed • Load tested to 132% of design load H.J. Krebs
FWD Upper Corner Block Fixture H.J. Krebs
FWD Upper Corner Block Fixture H.J. Krebs
FWD Upr Crnr Blk Load Test H.J. Krebs
Steel Handling Fixtures • Corner Block Bolt Storage Bins • Purpose • Stores corner block bolts and organizes bolts to reinstall them in their original locations. Six storage bins will be fabricated. • Comments • A written torquing sequence and torquing procedure is in process • Needed • 2004, 2005 • Responsible person • Jim Krebs • Status • Design and drawings complete • Fabrication complete H.J. Krebs
Corner Block Bolt Storage Bins H.J. Krebs