An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Courtyard by Marriott Danielle Shetler - Structural Option Senior Thesis - Spring 2005

  2. Presentation Outline • Background • Existing Structural Conditions • Proposal • Structural Redesign • LEED Study • Cost Comparison • Conclusions/Recommendations Courtyard by Marriott Lancaster, PA

  3. Background • Project Team • Baker, Ingram & Associates – Structural Engineer • Barton Associates, Inc – Mechanical/Electrical Engineer • High Construction Company – Design-Builder • High Hotels, LTD – Owner • Greenfield Architects, LTD - Architect Courtyard by Marriott Lancaster, PA

  4. Background • Location • Greenfield Corporate Center – Lancaster, PA Project North Courtyard by Marriott Courtyard by Marriott Lancaster, PA

  5. Background • 5 Story Hotel • 133 Guest Rooms • 83,821 Square Feet • Construction Dates • Start Date – July 12, 2004 • Completion Date – June 30, 2005 • Project Delivery Method – Design Build • Total Cost = $9,550,000 Courtyard by Marriott Lancaster, PA

  6. Presentation Outline • Background • Existing Structural Conditions • Proposal • Structural Redesign • LEED Study • Cost Comparison • Conclusions/Recommendations Courtyard by Marriott Lancaster, PA

  7. Existing Structural Conditions • Building Length = 253’-10” • Largest Width = 74’-9” • Building foot print with typical bay – 28’ span Courtyard by Marriott Lancaster, PA

  8. Existing Structural Conditions • Existing Structural System • Foundation • Spread footings (31) – various sizes • 4” & 6” Slab on Grade • Floor System • 8” pre-cast hollow core plank – span east/west direction • Gravity • 8” reinforced masonry shear walls • Lateral • Moment frames Courtyard by Marriott Lancaster, PA

  9. Existing Structural Conditions • 1st Floor – lobby area, conference room, pool, restaurant, kitchen • Exterior Wall: 8” reinforced load bearing ivany block • Interior: Steel columns – do not follow grid • 2nd Floor – guest rooms • Framed with large steel beams • W 36x393, W 36x300, W 36x230, W 27x84 • Moment connections - central • north/south & east/west directions Courtyard by Marriott Lancaster, PA

  10. Existing Structural Conditions • 2 typical bays – 2nd floor Courtyard by Marriott Lancaster, PA

  11. Existing Structural Conditions • 3rd, 4th & 5th Floors – guest rooms • 8” reinforced masonry shear walls • Typical bay – 3rd, 4th & 5th floors Courtyard by Marriott Lancaster, PA

  12. Existing Structural Conditions • Typical shear wall layout Courtyard by Marriott Lancaster, PA

  13. Existing Structural Conditions • Existing Building Section • Total building Height = 52’ • 1st floor height = 12’-8” • 2nd, 3rd & 4th floor heights (each) = 10’ • 5th floor height = 9’-4” Courtyard by Marriott Lancaster, PA

  14. Existing Structural Conditions • Lateral Loads • Wind Loads (N/S Direction) Courtyard by Marriott Lancaster, PA

  15. Existing Structural Conditions • Seismic Loads (N/S & E/W Directions) • R = 3.5 Courtyard by Marriott Lancaster, PA

  16. Existing Structural Conditions • Gravity Loads • Dead Loads • 8” Pre-cast Planks = 65 psf • 8” CMU = 32 psf • Structural Steel = 5 psf • Metal Deck = 2 psf • Roofing Materials = 7 psf • MEP, Misc = 10 psf • Total = 121 psf • Live Loads • Corridor/Guest Rooms = 40 psf • Mechanical Rooms = 150 psf • Stairs = 100 psf • Wall Loads • 8” CMU + E.I.F.S. = 47 psf Courtyard by Marriott Lancaster, PA

  17. Presentation Outline • Background • Existing Structural Conditions • Proposal • Structural Redesign • LEED Study • Cost Comparison • Conclusions/Recommendations Courtyard by Marriott Lancaster, PA

  18. Proposal • Structural System Redesign • Combination of masonry shear walls and steel floor framing to staggered truss system • Change roof from sloped to flat - green roof • Design Criteria • Code requirements for IBC 2003 • Maintain large open area on 1st floor • Maintain low floor-to-floor height • Provide feasible & cost effective design Courtyard by Marriott Lancaster, PA

  19. Proposal • Why staggered truss system? • Provides large column free open space on first floor • Provides an open floor layout for hotel rooms on upper floors • Provide low floor-to-floor height • Highly efficient for resistance to lateral loads caused by wind and earthquake • Fast and easy construction (especially useful during winter construction) • Light system Courtyard by Marriott Lancaster, PA

  20. Presentation Outline • Background • Existing Structural Conditions • Proposal • Structural Redesign • LEED Study • Cost Comparison • Conclusions/Recommendations Courtyard by Marriott Lancaster, PA

  21. Structural Redesign • Staggered Truss System • Trusses • Transverse direction • Story high trusses • Located in demising walls between guests rooms • Placed on alternating column lines – staggering between floors • Moment frames • Longitudinal direction • 8” pre-cast hollow core plank floor system • Connected to truss chords with weld plates & grouted • Transfers load to trusses • Spread footings • AISC Design Guide 14 • ETABS • Slope roof  Flat roof • 8” pre-cast hollow core plank Courtyard by Marriott Lancaster, PA

  22. Structural Redesign • New Building Layout • 252’ x 74’ • Truss spacing – 28’ • Truss span – 74’ • 1st floor height – 13’ • All other floor-to-floor heights – 10’ Courtyard by Marriott Lancaster, PA

  23. Structural Redesign • Typical section with staggered truss system Odd Story Even Story Courtyard by Marriott Lancaster, PA

  24. Structural Redesign Courtyard by Marriott Lancaster, PA

  25. Structural Redesign • Typical Truss • Vertical & diagonal members – 6” tube sections • Chords – W 10’s • Columns – W 12’s Vierendeel Panel Web Members – HSS shape Chord members – W shape Courtyard by Marriott Lancaster, PA

  26. Structural Redesign • Lateral Loads • Wind Loads (N/S Direction) Courtyard by Marriott Lancaster, PA

  27. Structural Redesign • Seismic Loads (N/S & E/W Directions) • R = 3.0 Courtyard by Marriott Lancaster, PA

  28. Structural Redesign • Gravity Loads • Dead Loads • 8” Pre-cast Planks = 65 psf • Leveling Compound = 5 psf • Structural Steel = 5 psf • Green Roof Material = 25 psf • Partitions = 12 psf • MEP, Misc = 10 psf • Total = 122 psf • Live Loads • Corridor/Guest Rooms = 40 psf • Mechanical Rooms = 150 psf • Stairs = 100 psf • Wall Loads • 23 psf Courtyard by Marriott Lancaster, PA

  29. Structural Redesign • Load Combinations – IBC 2003 • 1.4D • 1.2D + 1.6L • 1.2D + 1.6W + 0.5L • 1.2D + 1.0E + 0.5L • 0.9D + (1.0E or 1.6W) Courtyard by Marriott Lancaster, PA

  30. Structural Redesign • Results of design • 8” pre-cast hollow core plank • Truss web members (vertical & diagonal) • HSS 10 x 6 • Truss chord members • Range W 10 x 33 to W 10 x 112 • Columns • W 12 x 96, W 12 x 106, W 14 x 132 • Foundation • Fewer spread footings (20) – possible size reduction • Possibility of using 2 long strip footings Courtyard by Marriott Lancaster, PA

  31. Presentation Outline • Background • Existing Structural Conditions • Proposal • Structural Redesign • LEED Study • Cost Comparison • Conclusions/Recommendations Courtyard by Marriott Lancaster, PA

  32. LEED Study • Green Roof Implementation • Change roof from slope to flat • Pre-cast planks replace cold formed trusses • Add vegetated roof to 85% of entire roof area (15,850 Square Feet) • LEED credit • 1 point • Criteria – cover at least 50% of entire roof area Courtyard by Marriott Lancaster, PA

  33. LEED Study • Section of green roof material Vegetation/Plants Plant Media Drainage Layer & Filter Waterproof Membrane/Insulation Roof Structure Courtyard by Marriott Lancaster, PA

  34. LEED Study • Advantages • Lengthens roof life by 2 or 3 times • Lowers noise levels • Reduces immediate storm water run-off • Reduces building cooling & heating cost • Absorbs carbon dioxide & creates oxygen • Aesthetically pleasing • LEED credit Courtyard by Marriott Lancaster, PA

  35. Presentation Outline • Background • Existing Structural Conditions • Proposal • Structural Redesign • LEED Study • Cost Comparison • Conclusions/Recommendations Courtyard by Marriott Lancaster, PA

  36. Cost Comparison • Structural System • Existing • $1,423,584 • New System • $1,003,043 Savings:$420,541 (30%) Courtyard by Marriott Lancaster, PA

  37. Presentation Outline • Background • Existing Structural Conditions • Proposal • Structural Redesign • LEED Study • Cost Comparison • Conclusions/Recommendations Courtyard by Marriott Lancaster, PA

  38. Conclusions/Recommendations • Staggered Truss • Very efficient system • Cost effective • Light Weight • Provides needed open space • Marriott Standards • Change in strict architecture • Efficiency of room size – restricted percentage • Small building • Green Roof • Advantageous to building • Cost effective • Feasible for this building Courtyard by Marriott Lancaster, PA

  39. Thank You!! • Kathy Hauser – Baker, Ingram & Associates • Frank McCabe – High Hotels • Jeff Sterner – High Construction • Greenfield Architects • AE Faculty • My Friends & Family Courtyard by Marriott Lancaster, PA

  40. Questions?? Courtyard by Marriott Lancaster, PA

More Related