An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Dubna modules assemblystatus (October 14 2013) • Straw manufacture: • current serial numberis # 6527 • for CH2 M2 X-Y900 straws are glued • for CH4 M1U-V 900 straws are ready • for CH4 M2X-Y 776 straws are manufactured • CH2 M1 U-Vstatus • CH2 M2 X-Ystatus • CH4 M1 U-Vstatus • CH2 M1 U-Vdelivery to CERN • Presented by S.Movchan 4-Nov-14 S.Movchan Straw manufacturing and QC 1

  2. Straws • 900 straws for CH2 M2 X-Y(2-nd Dubna module) are glued: • # (2990-3567) ~ 400 pc • # (3568-4394) - 50 pc • # (4395-4842) ~ 450pc • 900 straws for CH4 M1 U-V(3-d Dubna module) are ready: • # (4843-5750) • 776straws for CH4 M2 X-Y(4-th Dubna module) are manufactured: • # (5751-6527) 4-Nov-14 S.Movchan Straw manufacturing and QC 2

  3. CH2 M1 U-Vstatus 4-Nov-14 S.Movchan Straw manufacturing and QC 3

  4. Dubna assembly site (LHEP, bld.217) CH2 M1 U-V Start – 28/09/2012 finish of straw gluing (07/02/2013) Quality control by laser Module vacuum test: Leak ~ 500 mbar*cm3/min 4-Nov-14 4

  5. Module removed from assembly tooling (June 2013) 4-Nov-14 S.Movchan Straw manufacturing and QC 5

  6. CH2 M1 U-V: U-coordinate gas leak test Leak: 15 mBar/3 days at P=1.4 Bar 4-Nov-14 S.Movchan Straw manufacturing and QC 6

  7. CH2 M2 X-Ystatus 4-Nov-14 S.Movchan Straw manufacturing and QC 7

  8. CH2 M2 X-Y installed for assembly (July 16 2013) 4-Nov-14 Microworld physics, Gomel, 2013 8

  9. CH2 M2 X-Y status: all straws glued (October 14 2013) 8layers glued 4-Nov-14 S.Movchan Straw manufacturing and QC 9

  10. CH2 M2 X-Y: straw pre-tension check Example: Y, layer 1 F=(1.75-1.95) kG sensor 4-Nov-14 Microworld physics, Gomel, 2013 10

  11. CH2 M2 X-Y: straw position check top Example: Y, layer 1 middle bottom 4-Nov-14 Microworld physics, Gomel, 2013 11 +/- 100 m

  12. CH4 M1 U-V: vacuum test in progress 4-Nov-14 S.Movchan Straw manufacturing and QC 12

  13. Preparation for module delivery to CERN: 4 pc Shocklog device and dumping pads 4-Nov-14 S.Movchan Straw manufacturing and QC 13

  14. CH2 M1 U-V delivery to CERN 4 safety bolts: frame max shift is limited dL = 10 mm 4-Nov-14 S.Movchan Straw manufacturing and QC 14

  15. Shocklog 2 shocklog with 2 different thresholds will be used 4-Nov-14 S.Movchan Straw manufacturing and QC 15

  16. Conclusion • Straw manufacture: • 900 straws are glued in the CH2 M2 X-Y • 900 straws areready for CH4 M1 U-V • 776 straws are manufactured for CH4 M2 X-Y • CH2 M1 U-V: • straw gluing and wiring – done • final assembly – done • tests (HV, gas leak) – in progress • delivery to CERN – October 2013 • CH2 M2 X-Y: • straw gluing – done • wiring – October 2013 • final assembly – November 2013 • tests (HV, gas leak) – December 2013 • delivery to CERN – January 2014 • “Straw 2” installation – Feb-March 2014 4-Nov-14 S.Movchan Straw manufacturing and QC