TB summary:. Issues from TB: 2007-10-09. Vacuum infrastructure: Wing Lau to be asked whether he can take on coordination/overview role Target: dust mitigation plan: MICE Note 180: C.Booth: plan endorsed: Diamond-like graphite Propose limited number of pulses (>2M)
E N D
Issues from TB: 2007-10-09 • Vacuum infrastructure: • Wing Lau to be asked whether he can take on coordination/overview role • Target: dust mitigation plan: • MICE Note 180: C.Booth: plan endorsed: • Diamond-like graphite • Propose limited number of pulses (>2M) • Enough for running January to May • Liquid-hydrogen test cryostat: • Jacketing plan proposed by Y.Ivanyushenkov accepted • Focus-coil tender exercise: • Proposed offer/vendor accepted • Agreed that pulse-tube cooler would be specified
Issues from TB: 2007-10-09 • Progress against milestones: • TOF: • Anticipate ToF0&1 will arrive at RAL 15Nov07 • Some uncertainty owing to INFN management • ToF2: • Goal to deliver ToF2 by Jun08 • KL: • KL fully equipped in Roma III – End Nov07 • KL fully tested in Roma III – mid-Dec 07 • Expect to integrate in cosmic test before Xmas • CKov – postponed
Issues from TB: 2007-10-09 • Reviews: • Beam-line review: November/December • Poole (ASTeC, Chair), Petit-Jean (PSI), Gardner (ISIS) • Diffuser review • Lau meeting with Perrin this week at CERN. • DAQ/controls review • ABr/JSG to draft charge/agenda today. • WBS/Schedule review • December • Next meeting: • 16Nov07: 14:30 BST