Software Engineering: Analysis and Design (CSE3308) Lecture 9b: Project Management in Industry CSE3308/CSC3080/DMS/2000/24
Lecture 9b: Project Management in Industry • Goal • To cover some of the key topics in Project Management, in a practical way, using actual industry examples. • Focus • Focus on (software) product development projects. • Topics • Project Management Overview • Scope Management • Estimation • Risk Management • People Management Introduction
Education B.Sc (Physics/Mathematics) Deakin 1980 Dip.Eng (Digital Control) FIT 1985 M.App.Sc Monash 1993“The Intelligent Interpretation of Line Drawings and Text using Pattern Recognition Analysis”. Career Olex Cables 1980-1983Software Engineer ACI Computer Services 1983 - 1987System Manager, Systems Engineer. Varian Australia 1987-1995Software Engineer, Software Marketing Manager, Project Manager, Software Quality Manager Hewlett-Packard 1985-1996Consultant (PSO) Siemens Research 1996-1997Project Manager (SIEPLAN / Capacity Integrator Project) Open Software Associates1998 - currentProject Manager Trevor Holmes Introduction
SpectrAA-600/800Atomic Absorption spectrometer system. consists of: Microprocessor controlled instrument (near real-time control). PC Workstation for system control and data management. Accessories Graphite Tube Atomizer (GTA) Sample Preparation System (SPS) product price $40K to $80K effort: max team 15 50+ engineering years >500K lines code on the web: http://www.varianinc.com/osi Varian OSI Products Introduction
Sieplan/Capacity IntegratorNetwork planning and design tool for Telecommunications Transmission(SDH & PDH) Networks. consists of: 5 to 200 GUI Clients (Windows) Unix based server (HPUX) Versant OODBMS with databases up to 20GB. product price $500K to $10M effort: max team 60 100+ engineering years development budget > $20M 500K lines code on the web http://www.sr.com.au Siemens Research Products Introduction
OpenUIcross-GUI client/server UIMS consists of: cross GUI runtime engine GUI Builder integrated client / server messaging compiler and virtual machine interpreter effort 65 engineering years 550K lines code on the web http://www.osa.com.au NetDeployInternet application deployment and version management system consists of: Packer identifies component files of application generates catalogue file installs application files on Web Server Launcher checks client machine against catalogue downloads necessary files via HTTP effort to date: 27 engineering years 250K lines code OSA Products Introduction
Project Management • What is a project ? • What is a successful project ? • What drives project management ? • How are projects organized ? • How is progress measured ? • How is progress monitored ? • Additional Resources Project Management
What is a Project ? • A project is a related and interdependent set of activities that: • are related together to meet a set of objectives • have a number of defined starts and finishes over an extended period of time • are implemented by a team • Project work is the opposite of process work • Projects change the status quo Project Management
What is a successful project ? • A project is successful when: • the project has a satisfied client group • the project has met it’s deliverable and quality objectives • the product or system is delivered “on time, on budget” • the project team has a sense of professional satisfaction and accomplishment Project Management
What drives project management ? • Each project is different. • Many factors influence how a project is conducted, and often these factors interact. • Product functional requirements • Scope/Size, • Availability of domain expertise • Maturity of technology, development tools, and methodologies • New ?, Well understood ?, Vendor support ? • Time to Market, • Team size and experience, • Relationship with client • Product Sale vs. Contract, Joint Development ... • Prototypes, Product Trials, Acceptance arrangements ... Project Management
How are projects organized ? • In software development: ... designers have patterns, ... programmers have templates, … and Project Managers have Lifecycle Models. • Mature project managers and development organizations design Lifecycles to best fit the constraints and circumstances of their projects. • Lifecycle Model types are: • Waterfall, Incremental, Iterative, Spiral ... • RAD, Component Assembly ... • Lifecycle Model Resources: • EVO (Hewlett-Packard) http://www.hp.com/hpj/aug96/augart4.htm • MeNtOR SEP (OOPL) http://www.oopl.com.au • Rational Unified Process http://www.rational.com/products/rup Project Management
How is progress measured ? • Indicators of progress are: • the attainment of sub-goals • the completion of tasks • the completion of deliverables • Milestones • ‘Milestones’ are markers, used in a project plan to track progress. • A project is said to be “running to schedule” if all of the planned milestones have been passed on time • Schedule ‘slippage’ is quantified by the projected delay in passing milestones. • Project Reviews are conducted when key project milestones are passed. Project Management
Milestone Tracking Chart (45º Chart) milestone-3 1/1/99 1/2/99 1/3/99 1/4/99 1/5/99 milestone-2 Milestone Date milestone-1 1/1/99 1/2/99 1/3/99 1/4/99 1/5/99 Date Charted
How is progress monitored ? • Project Reviews • Periodic: Weekly / Monthly Progress Reviews • Milestone: End of Phase or Stage Reviews • The purpose of a review is to check that a project is on track, and agree actions to keep, or put, it on track. • If a project is not on track, then steps must be taken to get it back on track. For example: • change deadlines • change specifications • overtly degrade quality • partition product and add resources • use faster / better technology • work harder - in the short term. • If a project is on track, there will still be issues and risks that need to be identified, and appropriate action plans established. Project Management
Additional Resources • Pressman: Software Engineering - A Practitioner’s Approach • Thomsett: The Busy Person’s Project Management Book • http://www.ozemail.com.au/~thomsett/book/busy_book.htm • Jarvis & Crandall: Inroads to Software Quality,Prentice Hall, ISBN 0-13-238403-5 Project Management
Scope Management • How to define the scope of a project • Project Scoping • Scoping in contracted projects • Scoping Example Scope Management
How to define the scope of a project • Project scope is defined by the activities, responsibilities, and deliverables required to complete the project. • In a product development project, the scope is determined by the product ‘features’ that are declared to be “in”, “out”, and “undecided”. • A project should proceed only when the “in” and “out” scoping is agreed, and a process for finalizing the “undecided” is agreed. • Even minor scope changes can have a major impact on a project • may need to replan after every scope change Scope Management
Roles Product Specification/Project Scope developed at the intersection of the Sales & Marketing and Product Engineering cycles. Sales & Marketing gather, filter, and interpret market requirements. Product Engineering maintains the specification, and proposes technologies and solutions. Processes Often adhoc. Can be driven by individual biases, QFD: Quality Function Deployment (the House of Quality) used by HP, Varian OSI http://mijuno.larc.nasa.gov/dfc/qfd.html Sales andMarketing ProductEngineering ProductSpecification Project Scoping Scope Management
Scoping in contracted projects • Contract Scoping • More emphasis on a negotiated specification, delivery schedule, acceptance criteria, and other contract details. • Client representative propose a Feature List and provide Domain Expertise. • Project Team maintains the specification, and proposes technologies and solutions. Scope Management
Scoping Example • Initial Brief (Enhancement Project) • A major enhancement for a large client-server product is proposed to be released in 8 months. • The existing product specification details 54 significant “features”. • A new specification is to be developed in workshops with the client, and detailed using Use Cases. • The workshops will address three distinct business areas within the overall application domain. • Project Planning • The Project Manager develops a plan & schedule for the “Use Case workshops”, and a series of “scoping workshops”. • The scoping workshops will be conducted through an “Expert Group” drawn from (customer) domain experts, and senior project staff. Scope Management
Sep Oct Nov Dec 1/9 8/9 15/9 22/9 29/9 6/10 13/10 20/10 27/10 3/11 10/11 17/11 24/11 1/12 8/12 15/12 22/12 16/9 30/9 2/10 30/9 7/10 9/10 13/10 13/10 21/10 23/10 Scoping Example - project plan extract Use Case Sets Business Sub-Domain A Final U/C Workshop Draft Feature Assessment Scoping Workshop Œ Finalize Use Cases Business Sub-Domain B Final U/C Workshop Draft Feature Assessment Scoping Workshop Finalize Use Cases Presentation to U/C Workshop participants Business Sub-Domain C + Sub-Domain D Final U/C Workshop Draft Feature Assessment Scoping Workshop Finalize Use Cases Scope Management
Use Case drafts Set 1: + 27 Features ProductFeature List 54 Features Use Case (set 1.) Use Case (set 1.) Feature List (scoped) Scoping Example - process Feature List & Use Case Finalisation Process Use Case Sets 1 - 3 • Feature Assessment 1. Complete Use Case drafts. 2. Identify “new” Features and Issues in Use Cases. 3. Assess Use Case Features/Issues 4. Prepare submission to Expert Group with indicative estimates. • Scope Verification(by Expert Group) Meetings: Œ 2/10, 9/10, 23/10 5. Resolve Issues / Clarify Requirements 6. Consolidate and Rank Features 7. Adjust list order & Identify minimum feature set for a “deployable system”. 8. Management Review. consolidate & rank Ranked Features feature 1 feature 2 ... deployable system ... feature N development budget … feature M Scope Management
Scoping Example • Workshop Results • The Use Case and Scoping workshops identified and detailed: • Business Sub-Domain A: 16 Use Cases, 27 New Features • Business Sub-Domain B: 15 Use Cases, 9 New Features • Business Sub-Domain C: 25 Use Cases, No New Features Scope Management
Scoping Example • Budgeting • Available Resource • The Project Manager has a budget of 2868 Man Days for the development team (those project staff directly responsible for implementing the system). • Estimates • After analyzing the results of the workshops, the development team estimate that: • 1424 Man Days will be required to re-develop system infrastructure. • 1414 Man Days will be required to implement the 36 new features • The Project Manager estimates that development overheads, finals testing, acceptance and release will require 710 Man Days. • Discretionary Capacity • After subtracting “fixed costs” only 734 Man Days are available to implement the requested features. Scope Management
Use Case drafts Set 1: + 27 Features ProductFeature List 54 Features Use Case (set 1.) Use Case (set 1.) Project Feature List (scoped) N Features costed at < XX man days Scoping Example - process Feature List & Use Case Finalisation Process Use Case Sets 1 - 3 • Confirm Scope 9. Confirm scopeagainst Development Capacity. • Use Case Detailing 10. Use scoped Feature List to complete detailing of Use Cases. 11 Confirm cost estimates for all features in scoped system. consolidate & rank Ranked Features feature 1 feature 2 ... Development Capacity deployable system ... feature N Discretionary Capacity (XX Man days) development budget limit N features = XX man days … feature M Overheads + Release (710 Man days) Discretionary Capacity XX < 734 man days Note: 2868 man day budget must be confirmed. Basic Functionality & System Infrastructure (1454 man days) Scope Management
Scoping Example • Scope Finalization • Project team and Client representatives negotiate on a final set of features that fit the development budget, while meeting the customer’s minimum requirement for a deployable system. • Each feature assessed for its value to the client cf. it’s incremental development cost. • A final Feature List proposed to Client Management. • Conclusion • Negotiations Failed. • Unable to derive a Feature List that met the Client’s minimum requirement. • Never commit to a “fixed price” (in $ or delivery date) before finalizing scope. Scope Management
Estimation • Estimation vs. Guesstimation • Best / Average / Worst • Estimation Example • Productivity • Scheduling • Additional Resources Estimation
Estimation vs. Guesstimation • A guess is a guess … an estimate is an estimate … • Guess: an unsupported prediction. • Guesstimate: a guess based on relevant experience, undocumented information, or history. • Estimate: a prediction based on experience, history or information formally recorded. • When most people say “I estimate that it will take 6 days”, they are guessing or guesstimating. • Estimation requires a formal history, including predicted and actual times for tasks, that document the organization's past projects. • When guesstimating: • get independent guestimates from multiple sources (project team members) • document all assumptions Estimation
Best/Average/Worst • Single figure estimates hide uncertainty • Three figure estimates capture the range of uncertainty • best: assume that things go better than expected. (10% confidence) • average: assume that things go to plan. (50% confidence) • worst: assume that things go worse than expected. (90% confidence) • If there is a wide variation between the best and worst: • allow more time for a more detailed investigation • divide the task into subtasks and estimate individually Estimation
Estimation Example • Based on project history • Effort calibrated against size using a Class Count • Project Outline • Enhancement Project • 3-tier Client-Server system (product) • Size • The new specification details functionality for 110 Business Domain classes. • Productivity • Developer productivity has been measured and recorded for previous releases of this product. • Productivity rates are available for new code development, code modification, and code reuse. Estimation
Estimation Example • Business Domain Model (BDM) • Classes Count: 110 • Data & Presentation Layers • Assume 2.6 DPO classes per Business Domain class • Productivity Rates (Coding): • New: 04 Classes/person month • Modify: 06 Classes/person month • Re-Use: 10 Classes/person month • User Interface (GUI) Layer • Assume 1 GUI class per Business Domain class • Productivity Rates (Coding): • New: 04 Classes/person month • Modify: 06 Classes/person month • Re-Use: 10 Classes/person month Estimation
Estimation Example • Resource Effort / Availability Estimates Estimation
Productivity • Variation between individuals • A number of studies indicate that there is an order of magnitude difference in productivity between the strongest and weakest team members. • Researchers have obtained the following results for defect free, non-commented, 3GL code: • WorstBestCase study 1 4 Barry Boehm 1 10 Capers Jones 1 16 Sackman 1 30 Putnam & Myers • Assumptions about who is to do the work and under what conditions must be made clear when estimating and not lost when developing a team schedule. Estimation
Scheduling • Many other tasks need to be performed in the working environment. • When developing a schedule, a Project Manager must take into account time and effort expended for: • holidays and sick lease • training • reviewing other people’s work including estimates, design, code, documentation ... • progress tracking & reporting • inter & intra-team interaction, and other team and management communication. • Elapsed time is 2 - 3 times the estimated time Estimation
Additional Resources • Productivity benchmark data • International Software Benchmarking Standards Group (ISBSG) • http://www.isbsg.org.au • OSA • The sustained average coding rate at OSA is 40 lines per engineer per day • Tools • SPR KnowledgePLAN, SPR CHECKPOINT • http://www.spr.com/html/products.htm Estimation
Risk Management • Planning for risk management • Risk Management Example • Additional Resources Risk Management
Planning for risk management • Project Plan • Seek early identification of project risks, and the development of a risk management plan with the project plan. • The table of project risks from the project plan should be regularly updated and reviewed at Project Reviews. • Risk Table • For each identified risk, should include: • the current ranking • the probability of the risk eventuating • the severity of the risk • consequences if the risk eventuates • a mitigation strategy • a contingency plan Risk Management
Risk Management Example Risk Management
Risk Management Example Risk Management
Risk Management Example • Risk Analysis & Planning • 1. Feedback from Widget 1.0 trials is not received in time to be incorporated in the Widget 2.0 product. • Probability: High Severity: High • Consequence: No prior field experience from Widget 1.0 reduces ability to avoid acceptance problems. • Mitigation Strategy: Make results from Incremental Releases available to customers for preview. • 2. Customer doesn’t meet delivery milestones for ‘external dependencies’. • Probability: Medium Severity: High • Consequence: Schedule slippage. • Mitigation Strategy: a) Regular progress reviews in Project Management forums. b) Escalate to customer sponsor. • Contingency: No delivery schedule commitments. Risk Management
Risk Management Example • Risk Analysis & Planning • 3. Key resources are diverted to Widget 1.0 support during Widgets 2.0 development. • 4. Insufficient resources and duration planned for Acceptance Testing • 5. New or immature business practices (eg. Red Widget Design) in Customer lead to change requests in Construction or Acceptance phases. • Probability: Medium Severity: Medium • Consequence: a) Identification of new features after specification sign-off. b) Extra incremental releases delayed final release to Customer acceptance. • Mitigation Strategy: a) Early analysis of potential for process changes. b) Strict observance to Change Management processes. • Contingency: Schedule implementation of change requests after acceptance of baseline Widget 2.0 system. • 6. Support for Widget 1.0 sales diverts resources from new product development. Risk Management
Risk Management Example • Risk Analysis & Planning • 7. Integration risk with technologies new to ACME Widgets being introduced in Widget 2.0 architecture (eg. CORBA). • Probability: High Severity: Low • Consequence: a) Schedule Slippage. b) Non-optimal design decisions.. • Mitigation Strategy: Prototype in Nov - Dec. • Contingency: a) Look at alternate technologies. b) ‘Buy in’ expertise by hire experts in technologies. Risk Management
Risk Management Example • Risk Analysis & Planning (managed) • 1. Too much parallelism in specification and modeling tasks (inefficient and faulty information flow between modeling teams). • 2. Divergence in Wingdings and Widgets specifications. ACME Widgets and Customer teams disagree on requirement specifications. • Probability: Low Severity: High • Consequence: Delay in achieving sign-off for specifications. • Mitigation Strategy: a) Re-focus on project goals. b) Regular Use Case team review of draft specifications. c) Scope resolution through the Expert Group. • Contingency: Escalate to as necessary to the Widgets Expert Group, Widgets Management Group, and Governance Board. • 3. Can’t identify a new (viable) Architecture. • 4. ACME Widgets and Customer disagree on Feature Scope Risk Management
Additional Resources • Project Risk Assessment Form • http://www.ozemail.com.au/~thomsett/form/Default.htm Risk Management
People Management • Manager’s Role • ensure that a team meets its set objectives • ensure that all team members have an opportunity to contribute • help team members to achieve the goals that they set themselves • Remember • Management decisions effect people • Team members are not just resources: • they are individuals with their own ambitions and interests • they MUST be treated with respect. • Above all … have fun ! People Management