BLM for the Injectors project Cabling non-Conformities

LIU-PSB Working Group Meeting ( 15/08/2013). BLM for the Injectors project Cabling non-Conformities . CKB50 : Coaxial cable. Brown polyolefin. SI-CU 23x9x0.16. Diameter in [mm]. 11.5 +/-0.3. High Mu FE. PETP. SI-CU 23x9x0.16. 8.71. PETP. 8.07. AL-PETP-AL. 8.03. PE. 7.98. CU.

johnna
Download Presentation

BLM for the Injectors project Cabling non-Conformities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LIU-PSB Working Group Meeting (15/08/2013) BLM for the Injectors project Cabling non-Conformities Christos Zamantzas (christos.zamantzas@cern.ch)

  2. CKB50: Coaxial cable Brown polyolefin SI-CU 23x9x0.16 Diameter in [mm] 11.5 +/-0.3 High Mu FE PETP SI-CU 23x9x0.16 8.71 PETP 8.07 AL-PETP-AL 8.03 PE 7.98 CU 7.94 7.3 7.25 2.6 Cable: Signal -(1000V)- Screen 1 –(500V)- Screen 2 (Triaxial) 1. Adapter: BNC or SMA Signal - Screen 1 (coaxial) Connector male: (receptacles) -Signal -Isolation (1000V) -Screen 1 -Isolation (500V) -Screen 2 (Triaxial) Connector female: (cable) -Signal -Isolation (1000V) -Screen 1 -Isolation (500V) -Screen 2 (Triaxial) 2. Adapter: BNC / SMA / N-type Signal - Screen 1 & Screen 2(coaxial) 15/08/2013

  3. Cabling Diagram Connector Types: enclosed in cable tray tube ~ 1 m 50 ÷ 200 m ~ 5 m Ionization Chamber HV Power Supply (~1500 V) HV BNC CKB 50 SMA BNC Signal Acquisition Card (BLEDP) Internal Screen 1 BNC External Screen 2 SMA TRIAX • Screen of HV BNC is open on the IC side to assure there is no ground loop. • Internal screen to shield low frequency noise (GND only on electronics side, IC is floating). • External screen to shield high frequency noise. 15/08/2013

  4. CKB50: non-conformity Brown polyolefin SI-CU 23x9x0.16 Diameter in [mm] 11.5 +/-0.3 High Mu FE PETP SI-CU 23x9x0.16 8.71 PETP 8.07 AL-PETP-AL 8.03 PE 7.98 CU 7.94 7.3 7.25 2.6 Cable: Signal -(1000V)- Screen 1 –(500V)- Screen 2 (Triaxial) • Isolation between the two shields not optimal. • Added additional steps for the connector assembly to avoid leaks. • At random positions discovered shorts between the two shields. • Not possible to be used with Triaxial functionality. 15/08/2013

  5. Cabling Non-Conformities Connector Types: enclosed in cable tray tube ~ 1 m 50 ÷ 200 m ~ 5 m Ionization Chamber HV Power Supply (~1500 V) HV BNC CKB 50 SMA BNC Signal Acquisition Card (BLEDP) Internal Screen 1 BNC External Screen 2 SMA TRIAX cablenon-conformities • Internal and External screen are shorted in multiple and random places. • Non-conformity (most probable) due to thin insulator. 15/08/2013

  6. Alternative Cabling Configuration Connector Types: enclosed in cable tray tube ~ 1 m 50 ÷ 200 m ~ 5 m Ionization Chamber HV Power Supply (~1500 V) HV BNC CKB 50 SMA BNC Signal Acquisition Card (BLEDP) Internal Screen 1 BNC External Screen 2 SMA TRIAX cablenon-conformities • Connect both shields together on both sides • Leave the ground on the detector side floating • Configuration will be very similar like in LHC system. 15/08/2013

  7. Meeting with manufacturer • On the first meeting agreed: • Modification of the specifications • Two more PET-foils over the magnetic screen. • No problems mounting the connector. • The electrical properties will not change. • Manufacturer to run a trial until end of September • We will test the sample and release the cable until mid-October • If all ok, manufacture about 6km until end of November • Re-installation to begin mid-January. 15/08/2013

  8. Next steps • Next week, meet with manufacturer on financial matters. • Costs of the new production • Handling of the stock already at CERN • Decide if we continue with the installation or remove all and wait for the new production. • Currently the issue affects 32 detectors • During LS2, 80 additional will need to be installed. 15/08/2013