140 likes | 598 Views
AMRP PROJECT. FORESHORE OF NAGARJUNA SAGAR RESERVOIR (PUTTAMGANDI). UDAYA SAMUDRAM BALANCING RESERVOIR. AKKAMPALLY BALANCING RESERVOIR . (1.5 TMC). TUNNEL. CISTERN. (1.5 TMC). Aiti Pamula Reservoir. MAIN CANAL. 136.150 KM. Musi Reservoir. D41. 1.47 KM. Km. 0.00. 3 KM. Km. 23.20.
E N D
AMRP PROJECT FORESHORE OF NAGARJUNA SAGAR RESERVOIR (PUTTAMGANDI) UDAYA SAMUDRAM BALANCING RESERVOIR AKKAMPALLY BALANCING RESERVOIR (1.5 TMC) TUNNEL CISTERN (1.5 TMC) Aiti Pamula Reservoir MAIN CANAL 136.150 KM Musi Reservoir D41 1.47 KM Km. 0.00 3 KM Km. 23.20 APPROACH CHANNEL PUMP HOUSE , PUMPS & PREASUE MAINS LINK CANAL D19 D22 D25 D37 D39 D40 D55 D41 TO D55 EPC PACKAGE NO. 80 • The main canal works completed. • All 4 Pumps installed and water was let out into canals. • No. of pumps : 4 Nos. of 18MW each. • Lift height : 100M • Power required : 153 Millions Units • The distributaries & field channels are under progress • The project will be completed in all respects by 3/2008 • Reservoir: Akkampally & Udayasamudram • Utilisation : 30.00TMC (2.50TMC for drinking water to 516 villages) • Ayacut : 2.70 Lakh Acs. • Length of canal : 136.150 Kms – 3000 c/s. • .With the completion of Distributaries and field channels in packages 77 to 81 and low level canal with lift an IP of 2.70 Lakh acres will be created by 3/2008. PACKAGE 77 PACKAGE 78 PACKAGE 79 DISTRIBUTORIES (D19, D22, D25, D37, D39, D40 TO D55) CONSTRUCTION OF WHOLE DISTRIBUTORY SYSTEM, CM & CD WORKS AND MICRO NETWORK (FIELD CHANNELS)
AMRP PROJECT • High Level Canal • Lift Height : 100 M • No. of Pumps : 4 No.s • Pump Capacity (each) : 18 MW • Power Required : 72 MW PRESENT STATUS : • High Level canal including Head works : Completed • Two Balancing Reservoirs (2 Nos.) : Completed • Distributary system for 36,000 Acres : Completed • Distributary system for 1,90,000 Acres : Under progress • Low Level Canal • Lift Height : 27.50 M • No. of Pumps : 3 Nos. • Pump Capacity(each) : 4 MW • Power required : 12MW PRESENT STATUS : • Low Level Canal (Km. 0.00 to Km. 13.00) : Completed • Low Level Canal (Km. 13.00 to Km. 63.00) : Under Progress • Lifts and low level canal beyond 63Kms : Tenders under finalisation
AMRP PROJECT Package No. 77/Cat-II : Execution of distributaries of D-19, D-22&D-25, lining of upstream and downstream canal portions at structures and Micro Network (Field Channels ) Name of the Contractor : M/s Siddhartha Constructions (P) Ltd.,& Swapna Constructions (JV) Agreement Amount : Rs. 33.44 Crores Agreement Date : 19-3-2005 Period of Completion : 36 Months (10milestones) Date of completion : 18-03-2008 • Investigation (HPs) : Completed (Total length of 167 Kms) • Designs (Structures) : Approval for 40 Kms length against 167Km structure. • Execution (Distributary) : Progress in 10Km against total length of 167Km. • Qty. of earth work done : 3,30,000Cum • Land Acquisition : Required 1194 Acres, Requisitioned – 988 Acres; Acquired 24 Acres • Expenditure : Rs. 6.482 Crs.(Inc. Mob. Adv. Rs. 3.342 Crs) against Rs.33.44 Crores.
AMRP PROJECT Package No.78/Cat-II : Excavation of distributaries D-37 and Micro Network (Field Channels), and lining of upstream and downstream canal portions at structures, CM & CD works. Name of the Contractor : M/s ECCI-MRKR (JV) Agreement Amount : Rs. 49.99 Crs. Agreement Date : 24-3-2005 Period of Completion : 36 Months(10 milestones) Date of Completion : 23-03-2008 • Investigation (HPs) : Major & Minor Completed. Sub-Minors are in progress. • Designs (Structures) : Under approval. • Execution (distributary) : Earthwork excavation for 17Km of Major & 15KmMinorsis completed against 219Kms length. • Qty. of earth work done : 5.00 Lakh Cum against 20 Lakh Cum • Expenditure : Rs. 5.29 Crores (including Mob.Adv. of Rs.2.50Crs) against Rs.49.99Crs. • Land Acquisition : Required 1770 Acres, Requisitioned 1223 Acs. Acquired : 95 Acs.
AMRP PROJECT Package No.79/Cat-II : Excavation and formation of embankments and construction of D-39 & D-40 distributary system, CM & CD works, lining the U/s and D/s canal portions at structures with concrete and Micro Network (Field channels) Name of the Contractor : M/s Siddhartha Constructions Pvt. Ltd., - Swapna Constructions (JV) Agreement Amount : Rs. 40.29 Crs. Agreement Date : 19-3-2005 Period of Completion : 36 Months(10 milestones) Date of completion : 18-03-2008 • Investigation : Major & Minors completed (Total length of 193.65Kms) • Designs (Structures) : approved in 36 KM against 193.65 Kms length • Execution(Distributary) : Progress in 13.00 Km of Majors against 193.65 Kms. • Qty. of earth work done : 3,75,000 Cum • Land Acquisition : Required 1836 Acres, Requisitioned 1232 Acres, Acquired 97 acres • Expenditure : Rs. 9.305 Crs. (Inc. Mob.Adv. Rs. 4.025 Crs.) against Rs. 4.029 Crs.
AMRP PROJECT Package No. 80/Cat-II : Execution of distributaries D41 to D55 and Micro Network (Field Channels) and lining of upstream and downstream canal portions at structures. Name of the Contractor : M/s ECCI-MRKR (JV) Agreement Amount : Rs. 44.795 Crs. Agreement Date : 13-5-2005 Period of Completion : 39 Months Date of completion : 12-08-2008 • Investigation : Investigation completed • Designs approval : HPs are approved from D41 to D45, D47,D49,D50,D51 and D53 to D55. • Execution : Progress in 8Kms of Major • Qty. of earth work done: 1,30,000 cum • Expenditure : Rs. 3.60 Crs (including Mob. Advance Rs.2.20Crores) against Rs.44.795Crs. • Land Acquisition : Required 1500 Acres, Requisitioned – 391 acres
AMRP PROJECT Name of the Contractor : M/s AKR – Coastal (JV) Agreement Amount : Rs. 67.124 Crs. Agreement Date : 28-03-2005 Period of Completion : 36 Months(10milestones) Date of completion : 27-03-2008 Package No. 81/Cat-II: Execution of Low level canal from Km.27.00 to Km.63.00 including distributary system and Micro network from Km.0.00 to Km.63.00 • Investigation : Main canal completed Structures on main canal, distributary system in progress. • Execution : Progress in 12Km of Main canal against 36 Kms length • Qty. of earth work done : 7,50,000 Cum • Expenditure : Rs. 15.274 Crs. (inc. Mob. Adv. Rs. 6.694 Crs.) against Rs.16.69Crores LA Paid : Rs. 0.73 Crs. Mob. Adv. Recovered : Rs. 0.99 Crs. • Land Acquisition : Required 2100 Acres, Requisitioned – 690 Acres; DN/DD Published : 200 Acres.
AMRP PROJECT (Tunnel Scheme) Name of the Contractor : M/s. Jaiprakash Associates Ltd. Agreement Amount : Rs. 1925 Crs. Agreement Date : 25-08-2005 Period of Completion : 60 Months(20milestones) Date of completion : 24-08-2010 Tunnel: Execution of Tunnels 1 & 2 of SLBC including Construction of Head Regulator. • Investigation : Investigation, design, planning and procurement of TBM for tunnel is in progress • Expenditure : Rs.96.25 Crores (Mob. Advance) • Execution : Starts from 9/2006 (Investigation, design, bore hole, exploration etc to be completed by 8/06 – 12 months period)