DDG 51 Program. Presented to: Surface Navy Association. 15-17 January 2013. Presented by: CAPT Mark Vandroff , USN Program Manager, DDG 51 Shipbuilding Program mark.vandroff@navy.mil (202)781-2177. Agenda. DDG 51 Shipbuilding Profile DDG 113-116 Status

jonah-duke
Download Presentation

15-17 January 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DDG 51 Program Presented to: Surface Navy Association 15-17 January 2013 Presented by: CAPT Mark Vandroff, USN Program Manager, DDG 51 Shipbuilding Program mark.vandroff@navy.mil (202)781-2177

  2. Agenda DDG 51 Shipbuilding Profile DDG 113-116 Status Baseline (BL) 9 New Construction (NC) IAMD Shipyard Initiatives FY13-17 Multi-Year Procurement (MYP) Flight III Update Primary Configuration Baseline Changes Design/Cost/Capabilities Trade-offs Service Life Allowance Comparison Summary

  3. DDG 51 Class Shipbuilding Profile MS IV 10/93 MS IIIA 10/86 MS II 12/83 MS I 6/81 MS 0 2/80 ACAT ID ACAT ID ACAT IC ACAT IC FY # of Ships 62 Delivered to Fleet Flight I Flight II Flight IIA 4 Under Contract Flight III 21 Flight I Ships 7 Flight II Ships 44 Flight IIA Ships 3 Flight III Ships FUTURE AWARD FY98-01 MYP FY02-05 MYP UNDER DELIVERED CONTRACT TOTAL BIW 34 2 36 Ingalls 28 2 30

  4. DDG 113-116 Status • DDG 113 (HII) Start Fab completed 03 Sep 12 (2.55% complete through Nov 2012) • DDG 114 (HII) Start Fab scheduled for 3 Jun 13 DDG 113 DDG 114 DDG 115 DDG 116 • DDG 115 (BIW) Start Fab completed 22 Feb 12 (11.44% complete through Nov 2012) • DDG 116 (BIW) 1ST 100 tons scheduled for 13 Jan 13

  5. DDG 51 Program StatusBaseline (BL) 9 New Construction (NC) IAMD • BL 9 NC IAMD DDG computer program for DDGs 113-116 • Developed from AEGIS Common Source Library (CSL) • Supports all Baselines associated with IAMD • Being developed from AEGIS Modernization, BL 9 IAMD DDG • BL 9 IAMD DDG certification date is Jun 2014 • Small delta in software to address configuration differences between AMOD & NC destroyers • Approximately 95% of BL 9 NC IAMD DDG PoR software development completed • BL 9 NC IAMD DDG certification scheduled for FY17 • DDG 113 AEGIS Weapon System currently undergoing testing at Production Test Center (PTC) in Moorestown, NJ

  6. Shipyard Initiatives • Electrical Mockups: Allows later loadout of Electronic Equipment, which decreases likelihood of damage and improves accessibility • Support Tower: Provides access and craft offices, tool/rod rooms, and restrooms in vicinity of ship during erection • Machinery Packaging: Outfitting in shop vice on ship • Planning System Integration: Shift from Craft-centric to System-centric build plan for selected systems • Dimensional Management System: Improved Accuracy Control procedures and fixtures • Ultra Hall: Maximize Outfitting Indoors and support downstream critical path • Safer • More Efficient • Cost Effective • Goal: Move as Much Work Upstream as Possible 6

  7. FY13-FY17 Multi-YearProcurement (MYP) • FY 13-17 MYP RFP Issued 1 May 12 • Shipbuilder Bids Received 9 Jul 12 • Current Continuing Resolution (CR) Expires 27 Mar 13 • FY 2013 National Defense Authorization Act (NDAA) Enacted 2 Jan 13 • FY 2013 Defense Appropriations Act Enacted TBD • USD(AT&L) submits 30 Day Notification letter to Congress TBD • Award MYP Contract TBD

  8. Flight III Update • Completed 2nd year of Flight III Study on 17 Sep 12 • Preliminary Design development started May 2012; completion planned for Nov 2013 • Gate 2 completed 24 Jul 12 • Gate 3 completed 26 Oct 12 • CDD and CONOPS Joint staffing underway • Preliminary Design Review (PDR) planned for 1stQtr FY14 • An Engineering Change Proposal (ECP) will be developed to reflect Flight III modifications • ECP notionally planned for initial implementation on 2nd FY16 Ship 8

  9. Primary FY10 and Follow Changes • DER 1 • EOSS • BMD • Topside • EOSS • CBSP • NMT • SSEE Inc F • DER 2/3 • BMD • AFT VLS • VLS Mod • BMD • HVAC Upgrade • Pilot House • AWS Upgrade • CIC Display Upgrades • 03 Level • AWS Upgrade • MMSP / BMD • Radar Room 3 • AWS Upgrade • BMD 5.0 • MK45/Mod4 Gun • AWS Upgrades • GWS Upgrade (Ethernet) • CSMC • AWS Upgrades • NIXIE • SLQ-25 C • FWD VLS • VLS Mod • BMD • HVAC Upgrade • Remove Forward Kingpost • Remove Port Anchor • Next Generation Glide Slope Indicator • CIC • AWS Upgrade • CIC Display Upgrade • GWS Upgrade • BFTT • TTWCS Upgrade • MFTA Winch Room • Space and Wt, installed at PSA • CSER 1 • AWS Upgrades • VLS Mod • GWS Upgrade • TER • TTWCS Upgrade • CSER 3 • AWS Upgrade • VLS Mods • Comm Center • CBSP • SSEE Inc F • ISNS D(V)9 • NMT • CSER 2 • AWS Upgrades • CIC Display Upgrades • MMSP / BMD • Sonar Control • AWS Upgrade • ASW Upgrade • SER 1, 2, 3 • ASW Upgrade

  10. Primary FY12 and Follow Changes • Pilot House • NAVSSI Upgrade • Topside • SSEE Inc F Deck Edge Ants. • Array Room 2 • CANES • SSES • CANES • IC Gyro Rm 2 • NAVSSI Upgrade • CIC • CANES • Comm Center • HF DAG • NAVMACS TR • CANES • IC Gyro Rm 1 • NAVSSI Upgrade • CANES • SNAP II Computer Rm • CANES • CSER 3 • CANES • CSER 2 • CANES • Sonar Control / SER 1 • CANES

  11. Primary FY13 and Follow Changes • Mast • SEWIP Blk 2 • MOBI • Intake / Update • CRES Louvers • Pilot House • MOBI • IPDS-LR • Knudsen 320 Fathometer • CPS Fan Rooms • CBR Filter Kit Elimination • Crew Berthing • Accommodations • Physical Fitness • Boat Davit • All Electric SLAD • AMR 1 • Cross Flooding • SEWIP • AN/SLQ-32 Blk 2 • Radio Trans. Rm • GBS • Hull • Knudsen 320 Fathometer • CIC • Knudsen 320 Fathometer • Sonar • AN/SQQ-89 Upgrade • Knudsen 320 Fathometer • Stave Cable Connectorization

  12. Primary FY14 and Follow Changes • Mast • CEC w/ CAB-S • SRQ-4 Ku-Band • AN/SPQ-9B Radar • Replaces AN/SPS-67 • Radar Room 3 • BMD • Aft VLS • BMD • Fwd VLS • BMD • MFTA • Install In Line • Radio Trans. Rm • Integrated AN/SRQ-4 • CIC • UPX-29 (V) AIMS MK XIIA • SEWIP Blk 2 • Integrated AN/SRQ-4 • CSER 2 • Total Ship Training Capability • Cooler Replacement • Sonar • AN/SQQ-89 Upgrade • AN/SQQ-89 ARR-75 Replacement • Cooler Replacement

  13. FY16 and Follow Changes (Flight III) • Enclosures • Added P/S enclosures and stacked boats for displaced equip & stores • AMDR-S • Replacing AN/SPY-1D(V) • ACB Next / TI Next Upgrade to AWS • Obsolescence and roll-down impact changes as required • AC Plant • 5 x 300 Ton HES/C AC Plants Replacing 5 x 200 Ton AC Plants • Electric Plant • 3 x 4MW, 4160 VAC SSGTGs replacing 3 x 3MW, 450 VAC SSGTGs

  14. Flight III Design/Cost/CapabilitiesTrade-offs * Notional FY # with 75 LT ballast

  15. FY10 Flt IIA – FY16* Flt IIIService Life Allowance Comparison Current Baseline SPQ-9B ∆ AMDR-S ∆ Current Baseline SPQ-9B ∆ AMDR-S ∆ FY14 Flt IIA with SPQ-9B; FY16 Flt III with AMDR-S FY14 Flt IIA with SPQ-9B; FY16 Flt III with AMDR-S Current Baseline 450 VAC 450 VAC 4160 VAC 450 VAC Current Baseline 5x200T ACs 5x200T ACs 5x200T ACs 5x300T ACs FY16 Flt III with change to 5x300T HES-C AC Units FY16 Flt III with change to 3x4MW GTGS & 4160 VAC Notes: 1. - * Second ship in FY16 is designated as the DDG 51 Flight III 2. - FY10 values are calculated, out year values are projections based on Not to Exceed Design Budget Estimates 15

  16. Summary • Four DDG 51 Restart ships under contract and starting fabrication • Shipbuilder proposals in review for FY13-17 MYP • Shipbuilders incentivized to improve production efficiency and reduce cost • Integrated Air and Missile Defense (IAMD) objective being fulfilled through evolutionary configuration baseline changes • Flight III Preliminary Design currently underway; ECP Development to follow 16