1 / 35

Transmission Main Leak Detection and Condition Assessment: Brazil Trade Mission 2012

Transmission Main Leak Detection and Condition Assessment: Brazil Trade Mission 2012. Corporate Overview. Formed in 2003. Based in Toronto. Original focus was on correlation based Leak Detection Equipment, specifically for PVC.

jonah
Download Presentation

Transmission Main Leak Detection and Condition Assessment: Brazil Trade Mission 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Transmission Main Leak Detection and Condition Assessment: Brazil Trade Mission 2012

  2. Corporate Overview • Formed in 2003. • Based in Toronto. • Original focus was on correlation based Leak Detection Equipment, specifically for PVC. • Developed Non Destructive pipe condition assessment technology • Changed focus to service offerings: • Leak detection for Large diameter mains • Condition assessment for ferrous and asbestos cement mains

  3. Agenda • Correlation Theory Review • Echologics • Key Advantages • Leak Detection Case Studies • Condition Assessment Background • Condition Assessment Case Studies • Summary

  4. Correlation Theory

  5. Correlation: a Review • Old technology: proven on metallic distribution mains • Manufacturer’s began to work on plastic and other types of pipes: made claims that could not be consistently achieved! • Required a different approach to: • Sensors • Signal Processing • Amplifiers • Echologics achieved some extraordinary success, other manufacturers immediately introduced ‘trunk main correlators’, but have never achieved our level of success • Development continues; now on our 5th generation of hardware

  6. Correlation Theory • Leaks make noise • Time of flight technology • Correlation function: • Leak bracketed with 2 Sensors • Leak noise takes longer to arrive at Sensor 1 than Sensor 2 • Correlator measures time difference to identify exact leak location

  7. Why is Echologics Successful • Advances in sensor design, signal processing, correlation algorithms • Advances in post processing of data • Advances in field techniques • It is as much about the people, as it is about the equipment

  8. Sensor development • We have done extensive R&D into plastic and transmission main sensor requirements, developed both hydrophones and accelerometers for large diameter The People • We have an intense training program and detailed field / data analysis processes • We have a young, passionate team of engineers

  9. Echologics CorrelationAdvantages

  10. Advantage and Disadvantages • Advantages: • Easily implemented with existing fittings • No requirement to close service take offs or laterals • No requirement to alter the flow in the pipe • Can ‘see’ leaks many km away; will find largest leaks first • Will find small leaks (typical results 2 LPM on 1500mm pipe at 3.5 bar, 1100m) • Disadvantages: • Will not find very small leaks (<1LPM) • Accuracy of location needs to be carefully verified

  11. Technology Comparison

  12. Leak Detection Case Studies

  13. Case Study: SABESP • Leak discovered by Smart Ball Pilot • Dry hole had been dug based on Smartball location • Requested by Genival Abdias to try and pinpoint the leak • Echologics correlated the leak to within <1m accuracy 13

  14. Site Location

  15. Leak Location Excavation

  16. Successful Leak Location

  17. Case Study: United Water New Jersey • Echologics performed a transmission main leak detection pilot survey on 8km of UWNJ transmission mains • 24” to 42” diameter • Testing revealed 5 leaks • One major leak discovered on a pipeline section outside of the boundaries of the original test plan • We first saw this leak 3 km from the eventual location

  18. Correlations provided evidence of leakage outside the current test area Out of Bracket Leak Detected

  19. Correlation across the river crossing revealing a prominent peak 40m east of fitting on the main Isolated Leak Under a Stream

  20. UWNJ 42” RCP Repair Pictures

  21. Other Examples: • Thames Water, England • Bristol Water, England • Las Vegas Valley Water Department • Springfield, Massachusetts • Echologics confirmed 2 leaks that was already discovered by expensive in-pipe technologies - 36”(915mm) and 48” (1200mm) main • Sydney, Australia • Barrie, Ontario • New Orleans

  22. Condition Assessment Background

  23. Remaining Pipe Wall Thickness Measurement • Metallic pipes lose thickness from internal and external corrosion • Asbestos cement pipes lose “effective thickness” from aggressive waters leaching calcium out of cement and weakening walls • Physical wall thickness doesn’t change, but the pipe loses structural stiffness and strength

  24. Velocity Measurement Noise Source Measure the sound velocity Wave propagation velocity (v) = D/ΔT, where ΔT is time delay between signals 1 and 2

  25. Minimum1 Average2 Wall Thickness Minimum around the circumference Averaged along the length

  26. Las Vegas, NV: LVVWD Pilot • Two sections of 6” AC pipe tested • .73” remaining structural thickness was measured by Echologics • Results indicated that pipe met requirements of PC200 • Excavated pipe to confirm results • Testing confirmed that our results accurately represented the remaining structural thickness of the pipe

  27. Las Vegas: Velocity Measurement & Results

  28. Las Vegas, NV: Excavated Pipe

  29. Results of 14” lab testing

  30. Pink area represents structurally sound concrete White area has lost structural integrity

  31. Newark, NJ: Pilot on cast iron pipe • Pilot study on cast iron pipe installed in 1910 • Pipe had been chosen for cement mortar lining as a rehabilitation technique • Our study determined that it was highly degraded and required a structural lining • We also found a leak during the study, losing about $20,000 worth of water a year

  32. Newark, New Jersey Fire Hydrant Service Leak at House #195 Average Pipe Wall Thickness of 0.18”, 63.9% loss Pit #1 - Valve Pit #2 Pit #3

  33. Newark, New Jersey This is the remaining structural thickness! Confidential Use pursuant to Company instructions

  34. Other Examples: • Dayton, Ohio • Sweetwater, California • Hamilton, Ontario • Chicago, Illinois • Successfully identified 3000ft section of reinforced concrete cylinder pipe with a significant number of wire breaks • Calgary, Alberta • Maple Ridge, British Columbia • Bloemfontein, South Africa

  35. Summary • Echologics has pioneered the effective use of correlators on large diameter pipe, and continues to develop the technology • In North America, we are now considered a viable alternative to insertion technologies: numerous successful studies have been completed • Claims made by other manufacturers continue to throw the technology into doubt • In several projects we have been directly compared to Sahara and have found the same leaks • Our condition assessment technology can accurately determine the remaining structural wall thickness of pipes • There is return on investment from: • Prioritizing which pipes require rehab or replacement • Performing leak detection simultaneously • Ensuring the correct decision is made with respect to rehab or replacement

More Related