Learning Objectives • Be Able To Apply Concepts Listed In Learning Goals • Be Able To Use Formulas Listed In The Equation Summary of Chapter
MRP • Computer Based System • Explodes Master Production Schedule (MPS) Into Required Amounts of Raw Materials & Subassemblies to Support MPS • Nets Against Current Orders & Inventories to Develop Production & Purchased Material Ordering Schedules
Objectives of MRP • Improve Customer Service • Reduce Inventory Investment • Improve Plant Operating Efficiency
Elements of MRP Inputs Outputs Service-Parts Orders and Forecasts Inventory Transaction Data Order Changes Order Inventory Status File Planned Order Schedule MRP System Master Production Schedule Planning Report Performance Bill of Materials File Action Notices
MRP Computer Program • Begins With Number of End Items Needed • Add Service Parts Not Included in MPS • Explode MPS Into Gross Requirements by Consulting Bill of Materials File • Modify Gross Requirements to Get Net Requirements: • Net Requirements = Gross Requirements + Allocated Inventory + Safety Stock - Inventory On Hand • Offset Orders to Allow for Lead Time
Engineering and process designs Bills of materials Material Requirements Plan Inputs
Authorized master production schedule Other sources of demand Engineering and process designs Bills of materials Material Requirements Plan Inputs
Authorized master production schedule Other sources of demand Engineering and process designs Inventory transactions Inventory records Bills of materials Material Requirements Plan Inputs
Authorized master production schedule Other sources of demand Engineering and process designs Inventory transactions Inventory records MRP explosion Bills of materials Material Requirements Plan Explosion
Authorized master production schedule Other sources of demand Engineering and process designs Inventory transactions Inventory records MRP explosion Bills of materials Material requirements plan Material Requirements Plan Output
Bill of Materials Back slats Seat cushion Leg supports Seat-frame boards Back legs Front legs A Ladder-back chair
A Ladder-back chair Back slats Seat cushion B (1) Ladder-back subassembly C (1) Seat subassembly D (2) Front legs E (4) Leg supports Leg supports Seat-frame boards F (2) Back legs G (4) Back slats H (1) Seat frame I (1) Seat cushion Back legs Front legs A Ladder-back chair J (4) Seat-frame boards Bill of Materials Level Code 0 1 2 3
Master Production Schedule April May 1 2 3 4 5 6 7 8 Ladder-back chair 150 150 Kitchen chair 120 120 Desk chair 200 200 200 200 Aggregate production plan 670 670 for chair family
Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 Planned receipts Planned order releases Inventory Record
Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 Planned receipts Explanation: Gross requirements are the total demand for the two chairs. Projected on-hand inventory in week 1 is 37 + 230 – 150 Planned order releases Inventory Record
Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 117 Planned receipts Explanation: Gross requirements are the total demand for the two chairs. Projected on-hand inventory in week 1 is 37 + 230 – 150 = 117 units. Planned order releases Inventory Record
Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 117 Planned receipts Scheduled or planned receipts in week t Projected on-hand inventory balance at end of week t Inventory on hand at end of week t - 1 Gross requirements in week t = + – Planned order releases Inventory Record
Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 117 117 117 – 3 – 3 –153 –273 –273 Planned receipts Scheduled or planned receipts in week t Projected on-hand inventory balance at end of week t Inventory on hand at end of week t - 1 Gross requirements in week t = + – Planned order releases Inventory Record
Explanation: Without a new order in week 4, there will be a shortage of three units: 117 + 0 + 0 – 120 = – 3 units. Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 117 117 117 –3 – 3 –153 – 273 – 273 Planned receipts Planned order releases Planned Orders
Explanation: Adding the planned receipt brings the balance to 117 + 0 + 230 – 120 = 227 units. Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 117 117 117 227 Planned receipts 230 Planned order releases Planned Orders
Explanation: Adding the planned receipt brings the balance to 117 + 0 + 230 – 120 = 227 units. Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 117 117 117 227 Planned receipts 230 Planned order releases Planned Orders
Explanation: Offsetting for a two-week lead time puts the corresponding planned order release back to week 2. Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 117 117 117 227 Planned receipts 230 Planned order releases 230 Planned Orders
Explanation: Offsetting for a two-week lead time puts the corresponding planned order release back to week 2. Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 117 117 117 227 Planned receipts 230 Planned order releases 230 Planned Orders
Explanation: The first planned order lasts until week 7, when projected inventory would drop to – 43. Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory –43 37 117 117 117 77 227 227 Planned receipts 230 Planned order releases 230 Planned Orders
Explanation: Adding the second planned receipt brings the balance to 77 + 0 + 230 – 120 = 187. Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 117 117 117 77 227 227 Planned receipts 230 230 Planned order releases 230 Planned Orders
Explanation: Adding the second planned receipt brings the balance to 77 + 0 + 230 – 120 = 187. Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 37 117 117 117 77 227 227 Planned receipts 230 230 Planned order releases 230 Planned Orders 187
Explanation: The corresponding planned order release is for week 5. Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 187 37 117 117 117 77 227 227 Planned receipts 230 230 Planned order releases 230 230 Planned Orders
Item: C Description: Seat subassembly Lot Size: 230 units Lead Time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 150 0 0 120 0 150 120 0 Scheduled receipts 230 0 0 0 0 0 0 0 Projected on-hand inventory 187 37 187 117 117 117 77 227 227 Planned receipts 230 230 Planned order releases 230 230 Planned Orders
Lot-Sizing Rule Comparison • The FOQ rule generates high average inventory because it creates remnants. • The POQ rule reduces average on-hand inventory because it does a better job of matching order quantity to requirements. • The L4L rule minimizes inventory investment but maximizes the number of orders placed.
MRP explosion MRP Outputs
MRP explosion Material requirements plan • Action notices • Releasing new orders • Adjusting due dates • Priority reports • Dispatch lists • Supplier schedules • Capacity reports • Capacity requirements planning • Finite capacity scheduling • Input-output control MRP Outputs
MRP explosion Material requirements plan • Action notices • Releasing new orders • Adjusting due dates • Priority reports • Dispatch lists • Supplier schedules • Capacity reports • Capacity requirements planning • Finite capacity scheduling • Input-output control Routings and time standards MRP Outputs
MRP explosion Material requirements plan • Action notices • Releasing new orders • Adjusting due dates • Priority reports • Dispatch lists • Supplier schedules • Capacity reports • Capacity requirements planning • Finite capacity scheduling • Input-output control Routings and time standards Manufacturing resources plan Performance reports MRP Outputs
MRP explosion Material requirements plan • Action notices • Releasing new orders • Adjusting due dates • Priority reports • Dispatch lists • Supplier schedules • Capacity reports • Capacity requirements planning • Finite capacity scheduling • Input-output control Routings and time standards Manufacturing resources plan Cost and price data Performance reports MRP Outputs
Item: Seat subassembly Lot size: 230 units Lead time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 0 0 0 0 150 120 150 120 Scheduled receipts 0 0 0 0 0 0 0 230 Projected on-hand inventory 37 117 117 227 227 77 187 187 117 Planned receipts 230 230 Planned order releases 230 230 MRP Explosion
Item: Seat subassembly Lot size: 230 units Lead time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 0 0 0 0 150 120 150 120 Planned receipts 230 230 Planned order releases 230 230 MRP Explosion
Item: Seat subassembly Lot size: 230 units Lead time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 0 0 0 0 150 120 150 120 Planned receipts 230 230 Planned order releases 230 230 Item: Seat frames Lot size: 300 units Lead time: 1 week Item: Seat cushion Lot size: L4L Lead time: 1 week Week Week 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Gross requirements Gross requirements Scheduled receipts Scheduled receipts 300 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Projected on-hand inventory Projected on-hand inventory 40 0 Planned receipts Planned receipts Planned order releases Planned order releases MRP Explosion
Item: Seat subassembly Lot size: 230 units Lead time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 0 0 0 0 150 120 150 120 Planned receipts 230 230 Planned order releases 230 230 Usage quantity: 1 Usage quantity: 1 Item: Seat frames Lot size: 300 units Lead time: 1 week Item: Seat cushion Lot size: L4L Lead time: 1 week Week Week 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Gross requirements Gross requirements 230 230 0 0 Scheduled receipts Scheduled receipts 300 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Projected on-hand inventory Projected on-hand inventory 40 0 Planned receipts Planned receipts Planned order releases Planned order releases MRP Explosion
Item: Seat subassembly Lot size: 230 units Lead time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 0 0 0 0 150 120 150 120 Planned receipts 230 230 Planned order releases 230 230 Usage quantity: 1 Usage quantity: 1 Item: Seat frames Lot size: 300 units Lead time: 1 week Item: Seat cushion Lot size: L4L Lead time: 1 week Week Week 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Gross requirements Gross requirements 230 0 230 230 0 230 0 0 0 0 Scheduled receipts Scheduled receipts 300 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Projected on-hand inventory Projected on-hand inventory 40 0 Planned receipts Planned receipts Planned order releases Planned order releases MRP Explosion
Item: Seat subassembly Lot size: 230 units Lead time: 2 weeks Week 1 2 3 4 5 6 7 8 Gross requirements 0 0 0 0 150 120 150 120 Planned receipts 230 230 Planned order releases 230 230 Item: Seat frames Lot size: 300 units Lead time: 1 week Item: Seat cushion Lot size: L4L Lead time: 1 week Week Week 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Gross requirements Gross requirements 230 0 230 0 230 0 230 0 0 0 0 0 0 0 0 0 Scheduled receipts Scheduled receipts 300 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Projected on-hand inventory Projected on-hand inventory 40 110 180 180 180 180 0 0 0 0 0 0 40 110 110 0 0 0 Planned receipts Planned receipts 300 230 230 Planned order releases Planned order releases 300 230 230 MRP Explosion
Item: Seat frames Lot size: 300 units Lead time: 1 week Item: Seat cushion Lot size: L4L Lead time: 1 week Week Week 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Gross requirements Gross requirements 230 0 230 0 230 0 230 0 0 0 0 0 0 0 0 0 Planned receipts Planned receipts 300 230 230 Planned order releases Planned order releases 300 230 230 MRP Explosion
Item: Seat frames Lot size: 300 units Lead time: 1 week Item: Seat cushion Lot size: L4L Lead time: 1 week Week Week 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Gross requirements Gross requirements 230 0 230 0 230 0 230 0 0 0 0 0 0 0 0 0 Planned receipts Planned receipts 300 230 230 Planned order releases Planned order releases 300 230 230 Item: Seat-frame boards Lot size: 1500 units Lead time: 1 week Week 1 2 3 4 5 6 7 8 Gross requirements Scheduled receipts 0 0 0 0 0 0 0 0 Projected on-hand inventory 200 Planned receipts Planned order releases MRP Explosion
Item: Seat frames Lot size: 300 units Lead time: 1 week Item: Seat cushion Lot size: L4L Lead time: 1 week Week Week 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Gross requirements Gross requirements 230 0 230 0 230 0 230 0 0 0 0 0 0 0 0 0 Planned receipts Planned receipts 300 230 230 Planned order releases Planned order releases 300 230 230 Usage quantity: 4 Item: Seat-frame boards Lot size: 1500 units Lead time: 1 week Week 1 2 3 4 5 6 7 8 Gross requirements 0 0 0 0 0 1200 0 0 Scheduled receipts 0 0 0 0 0 0 0 0 Projected on-hand inventory 200 Planned receipts Planned order releases MRP Explosion
Item: Seat frames Lot size: 300 units Lead time: 1 week Item: Seat cushion Lot size: L4L Lead time: 1 week Week Week 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 Gross requirements Gross requirements 230 0 230 0 230 0 230 0 0 0 0 0 0 0 0 0 Planned receipts Planned receipts 300 230 230 Planned order releases Planned order releases 300 230 230 Item: Seat-frame boards Lot size: 1500 units Lead time: 1 week Week 1 2 3 4 5 6 7 8 Gross requirements 0 0 0 0 0 1200 0 0 Scheduled receipts 0 0 0 0 0 0 0 0 Projected on-hand inventory 200 500 500 500 500 500 200 200 200 Planned receipts 1500 Planned order releases 1500 MRP Explosion
CRP • Tests MPS for Feasibility • Utilizes Routings to Determine Labor/Machine Loads • If Schedule Feasible, Recommends Freezing • If Schedule Overloads Resources, Points Out Processes That Are Overscheduled
Load Schedules • Compares Actual Labor and Machine Hours Against Available Hours • Offsets Schedules Between Successive Stages of Production by Lead Times • Provides Feasible MPS and Economically Loaded Work Centers • Promotes System Operating Efficiency ... Lowers Costs!