PRESENTATION ON STATUS OF IMPLEMENTATION OF WATERSHED DEVELOPMENT PROGRAMME IN NAGALAND STATE

WORKSHOP ON INTEGRATED WAERSHED MANAGEMENT PROGRAMME – PLANNING FOR 2010-11 ON 20-21 ST MAY 2010. PRESENTATION ON STATUS OF IMPLEMENTATION OF WATERSHED DEVELOPMENT PROGRAMME IN NAGALAND STATE. A. Integrated Watershed Management Programme (IWMP).

josh
Download Presentation

PRESENTATION ON STATUS OF IMPLEMENTATION OF WATERSHED DEVELOPMENT PROGRAMME IN NAGALAND STATE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WORKSHOP ON INTEGRATED WAERSHED MANAGEMENT PROGRAMME – PLANNING FOR 2010-11 ON20-21ST MAY 2010 PRESENTATION ON STATUS OF IMPLEMENTATION OF WATERSHED DEVELOPMENT PROGRAMME IN NAGALAND STATE

  2. A. Integrated Watershed Management Programme (IWMP)

  3. 1. (a). DETAILS OF SANCTION UNDER IWMP DURING 2009-2010

  4. Contd…

  5. 1. (B). STATUS OF IMPLEMENTATION OF IWMP DURING 2009-10 • Status of AAP& DPR preparation : Completed • Total Amount Released : Rs. 29.49 crores i) Central Share: Rs. 28.54 Crores ii) State Share: Rs. 0.95 Crores • Amount Utilized : Rs. 6.95 crores • Unspent Balance : Rs. 22.54 crores (as on 10th May 2010)

  6. Details of Institutional & Administrative Expenditure (i).State Level Nodal Agency (SLNA)

  7. GIS CELL - STATUS • Softwares procured : - Arc GIS Software – ArcInfo Licence 1 No. ArcView Licence – 3 Nos. • Satellite data - LISS MX-IV (5 mtr resolution) • SOI Topo sheet 1: 50,000 scale on digital format • GIS Thematic layers prepared : • Drainage maps • Contours • Soil (1: 2,50,000 scale) • Slope • Aspect • Relief • Land Use Land Cover (under progress) • Delineation of micro-watershed • GPS data (Collection of ground truth data for all sanctioned projects) - Completed

  8. MIS STATUS • Created official Website with a separate domain name www.lrdgon.com • Created Preliminary Database for State, District & Projects • Adobe CS5 software has been indented for developing front-end as well as for server site integration

  9. ii). District Watershed-Cum-Data Cell

  10. Social & Resource Mapping (IWMP Mokokchung - II)

  11. Project Planning Exercise with villagers (IWMP Longleng-1)

  12. Geo-referencing of project area by WDT members and villagers (IWMP Peren-I )

  13. WDT Members burning the midnight lamp to keep up the project timelines (Wokha District)

  14. (iii). Capacity building plan of the state

  15. TrainingforWatershed Community at Chudi Village (IWMP Wokha-I) on 9-02-10

  16. (iv). Details of Entry Point Activity (EPA) undertaken during 2009-10

  17. EPA – Water Reservoir being inaugurated at Kulhopu Village (IWMP Zunheboto-II) by Deputy Commissioner, Zunheboto on 13/05/2010

  18. EPA– CONSTRUCTION OF WATER HARVESTING STRUCTURE IN PROGRESS AT LOWER KHOMI VILLAGE UNDER IWMP PHEK-i

  19. Field prepared for Rubber Plantation during 2010 (Aree New village, IWMP Wokha-I)

  20. Pits dug along contour bunds for Rubber Plantation at Mekokla (IWMP-Wokha-II)

  21. IWMP - PHYSICAL TARGET FOR 2010-11 • Preparation of PPR is in progress.

  22. PRE-IWMP : Integrated Wastelands Development Programme (IWDP)

  23. Integrated Wastelands Development Programme (IWDP) • Status of IWDP : • No. of Projects Sanctioned : 42 • No. of Projects Completed : 41 • No. of incomplete projects : 1 • Action Plan for completion of overdue projects :Project expected to be completed by Sept. 2010. • Completion Report : To be submitted by June 2010 • Status of Post Project Evaluation (PPE) : • PPE completed : 6 • No. of PPE yet to be done : 35 • PPE assigned to 7 institutions • PPE Expected to be completed : October 2010

  24. Total Amount Released : Rs.206.62 crores i) Central Share: Rs. 191.60 Crores ii) State Share : Rs. 15.02 Crores • Amount Utilized : Rs. 206.22 crores • Unspent Balance : Rs. 0.40 crores(as on 30/04/10) • No. of UCs pending : NIL • Completion Report : To be submitted by June 2010 • Status of Updation of QPR & MPR : • Online data entry of QPRs done for all projects where formats/tables have been provided. For projects where tables are not provided, pending QPRs, UCs in hard copies have been furnished.

  25. THANK YOU