60 likes | 142 Views
Using MsProject for Earned Value Calculations. Advanced MsProject Course Dr. Leigh Geiger. Set Up Process. Create Project Plan Baseline the Plan Track progress/actuals & update the plan Set the Status Date Select the Earned Value method Use MsProject EV Views & Reports. Set Up Process.
E N D
Using MsProject for Earned Value Calculations Advanced MsProject Course Dr. Leigh Geiger
Set Up Process • Create Project Plan • Baseline the Plan • Track progress/actuals & update the plan • Set the Status Date • Select the Earned Value method • Use MsProject EV Views & Reports
Set Up Process • Create Project Plan • Baseline the Plan • Track progress/actuals & update the plan • Set the Status Date • Select the Earned Value method • Use MsProject EV Views & Reports
Earned Value Methods • % Complete • Calculated for each task: [Act Dur/Dur]*100 • If you enter it directly -Project calculates Act. & Rem. Duration • Use if actual work is entered • Physical % Complete • Not calculated, must be entered directly • Use if Actuals aren’t accurate Possible to use up 90% of total task duration and still be only 10% Physical Complete, e.g., when most work is planned for the last minute.
EV Views & Reports • Table Views • Earned Value • Earned Value Cost Indicators • Earned Value Schedule Indicators • Cost Reports • Earned Value • Visual Reports • EV Over Time