1 / 9

GLAST LAT Tracker Tower 11, 12, 13 Pre-Ship Review

GLAST LAT Tracker Tower 11, 12, 13 Pre-Ship Review. Luca.latronico@pi.infn.it INFN-Pisa. Tower 11, 12, 13 finalization + tower 15 assembly made the clean room VERY crowded this week!. Towers Assembly and test flowchart highlights. July 29 - August 16, 2005 (INFN-Pisa) :

Download Presentation

GLAST LAT Tracker Tower 11, 12, 13 Pre-Ship Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GLAST LAT Tracker Tower 11, 12, 13 Pre-Ship Review Luca.latronico@pi.infn.it INFN-Pisa

  2. Tower 11, 12, 13 finalization + tower 15 assembly made the clean room VERY crowded this week! Towers Assembly and test flowchart highlights • July 29 - August 16, 2005 (INFN-Pisa) : • assembly of complete tray stack • incomplete cable set • tower 11: non-flight C1,C2 • tower 12: missing C5 • tower 13: missing C2, C5 • Functional and performance tests • Sidewalls, alignment • September 1-14, 2005 (Alenia-Roma) • X-Y-Z vibrations • Thermal-Vacuum cycles • September 16-21, 2005 (INFN-Pisa) : • Missing cables installation and replacements • Solithane, EMI taping • Alignment verification, final CPT • Full EIDP details (soon) at: • http://glast.pi.infn.it

  3. Towers – Delivery configurations

  4. Towers – Delivery configurations Tower PN: LAT-DS-00722 (rev3) Tower SN: 11, 12, 13 Environmental test performed with following configuration variations: Tower 11: C1-001 non-flight installed in place of C1-P-004 C2-008 non-flight installed in place of C2-018 Tower 12: C5 missing Tower 13: C2 missing C5 missing Note: 16 cables over 24 came from Pioneer

  5. Towers configuration and mechanical verifications Configuration: • Kapton tape and foam applied on the flex cables as per LAT-DS-00722 • 4 layers of Poron foam 0.037 THK used on Bottom and Top Tray (–X) side (in place of 5 layers) • Base Plate assembly: • Torque of nuts 5.4 Nm, spec is (5.08 +0.56/-0 Nm) Alignment, Mass, COG: • All towers well aligned and inside stayclear • Masses and CG near estimated values (when used real masses) • Full data available from EIDP and INFN-PISA web site

  6. Towers 11, 12, 13 – Open NCRs • Environmental test in non-flight configuration • INFN/PI-NCRs: 568 (twr11), 575 (twr12), 569(twr13) • environmental test runs were performed with missing or non-flight cables, as agreed by an MRB • the NCR can be closed • Hot/cold power off/on not performed • INFN/PI-NCRs: 578 (twr12), 574 (twr13) • The problem is due to a known and documented issue with resetting MCM (NCR 417) with missing cables • To avoid the many and unknown number of power cycle needed to re-establish a good configuration with as many readable layers as possible, hot/cold switch on and off were not performed • SLAC has requested waiver LAT-XR-07340 on this issue relative to towers 7,9,10,12,13 • the NCR can be closed • Vacuum level out of specification • INFN/PI-NCRs: 581 (twr11), 583 (twr12), 582 (twr13) • The situation is similar to earlier TVAC tests and the proposal is to accept the test as for previous MRBs • the NCR can be closed • INFN/PI-573(twr11): some screws out of torque on sidewall +X • ~20% of the +X sidewall screws found out of torque after Z-axis vibration • All screws were re-torqued to spec, X-Y axis vibrations were performed, all screws torque were checked and no change was found • the NCR can be closed

  7. TVAC – vacuum level out of spec Same behaviour as previous tests – the proposal is to accept the test: • Vacuum slightly higher than spec (~> 10-4 vs 5x10-5 Torr) only during hot soaks • Vacuum level improving with time

  8. Efficiency – bad channels correlation spec Towers Efficiency

  9. Conclusions The clean room is sadly empty and people are looking for things to do (maybe) but 3 excellent towers are on their way to the LAT GRID at SLAC

More Related