4th phase: 3 TeV luminosity upgrade 3 TeV nominal parameters

CLIC Parameters and upgrade scenario http://cdsweb.cern.ch/record/1132079/files/CERN-OPEN-2008-021.pdf. 4th phase: 3 TeV luminosity upgrade 3 TeV nominal parameters. 2nd phase: 500 GeV luminosity upgrade 500 GeV nominal parameters. 3rd phase: 0.5 to 3 TeV energy upgrade

jpadgett
Download Presentation

4th phase: 3 TeV luminosity upgrade 3 TeV nominal parameters

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CLIC Parameters and upgrade scenariohttp://cdsweb.cern.ch/record/1132079/files/CERN-OPEN-2008-021.pdf 4th phase: 3 TeV luminosity upgrade 3 TeV nominal parameters 2nd phase: 500 GeV luminosity upgrade 500 GeV nominal parameters 3rd phase: 0.5 to 3 TeV energy upgrade 3 TeV conservative parameters 1rst phase: Initial operation 500 GeV conservative parameters

  2. Beam emittances at Damping Rings

  3. Beam sizes at Collisions

  4. LC 500 GeV Main parameters @ CLIC08http://clic-meeting.web.cern.ch/clic-meeting/ComparisonTable.html

  5. CLIC main parameters @ CLIC08http://cdsweb.cern.ch/record/1132079?ln=frhttp://clic-meeting.web.cern.ch/clic-meeting/clictable2007.html

  6. CLIC main parameters (proposed)http://cdsweb.cern.ch/record/1132079?ln=frhttp://clic-meeting.web.cern.ch/clic-meeting/clictable2007.html

  7. Beam sizes at Collisions

  8. CLIC Luminosity versus Energy

  9. Power flow @ 500 GeV 129.4 MW Wall Plug Modulator auxiliaries 63.4 MW 61.5 MW hREL = .93 Main beam injection, magnets, services, infrastructure and detector aux = 0.97 hM = .90 Power supplies klystrons hK = .70 1 GHz RF power: 36.1 MW 66 MW hS = .95 Drive beam acceleration hA = .977 hplug/RF = 38.8 % Drive Beam power: 33.5 MW 3.4 MW hRF/main = 39.6 % F(s)= .97  .96 hD = .84 Drive beam power extr. Dumps 26.2 MW hTRS = .98 PETS htot = 7.5 % hT = .96 12 GHz RF power: 24.6 MW (2 x 25 kJ x 50 Hz) hRF = .396 Main linac 9.75 MW Main beam

  10. Power flow @ 3 TeV 415 MW Wall Plug Modulator auxiliaries 260.4 MW AC power 252.6 MW hREL = .93 aux = 0.97 Main beam injection, magnets, services, infrastructure and detector hM = .90 Power supplies klystrons hK = .70 148.0 MW 1 GHz RF power 154.6 MW hS = .95 Drive beam acceleration hA = .977 hplug/RF = 38.8 % 137.4 MW Drive Beam Power 13.7 MW hRF/main = 27.7 % F(s)= .97  .96 hD = .84 Drive beam power extr. Dumps 107.4 MW hTRS = .98 PETS htot = 6.8 % hT = .96 101.1 MW 12 GHz RF power (2 x 101 kJ x 50 Hz) hRF = .277 Main linac 28 MW Main beam

  11. CLIC Plug Power requirements Courtesy: H.Braun

  12. Courtesy: R.Tomas Garcia

  13. 326 klystrons 33 MW, 139 ms combiner rings Circumferences delay loop 80.3 m CR1 160.6 m CR2 481.8 m drive beam accelerator 2.37 GeV, 1.0 GHz CR1 CR1 1 km delay loop CR2 326 klystrons 33 MW, 139 ms drive beam accelerator 2.37 GeV, 1.0 GHz 1 km delay loop Drive Beam Generation Complex CR2 decelerator, 24 sectors of 868 m BDS 2.75 km BDS 2.75 km BC2 BC2 245m 245m IP1 e- main linac , 12 GHz, 100 MV/m, 21.04 km e+ main linac TA R=120m TA R=120m 48.3 km CLIC overall layout 3 TeV booster linac, 9 GeV, 2 GHz Main Beam Generation Complex BC1 e- injector 2.4 GeV e+ injector, 2.4 GeV e+ DR 365m e- DR 365m Main & Drive Beam generation complexes not to scale

  14. 326 klystrons 33 MW, 29 ms combiner rings Circumferences delay loop 80.3 m CR1 160.6 m CR2 481.8 m drive beam accelerator 2.47 GeV, 1.0 GHz CR1 CR1 1 km delay loop CR2 326 klystrons 33 MW, 29 ms drive beam accelerator 2.47 GeV, 1.0 GHz 1 km delay loop Drive Beam Generation Complex CR2 decelerator, 5 sectors of 868 m BDS 1.87 km BDS 1.87 km BC2 BC2 245m 245m IP1 e- main linac , 12 GHz, 80 MV/m, 4.39 km e+ main linac TA R=120m TA R=120m 13.0 km CLIC overall layout 0.5 TeV booster linac, 9 GeV, 2 GHz Main Beam Generation Complex BC1 e- injector 2.4 GeV e+ injector, 2.4 GeV e+ DR 365m e- DR 365m

  15. Longitudinal section of a laser straight Linear Collider on CERN site– Courtesy: J.Osborne IP under CERN Prevessin site Phase 1: 0.5 TeV extension 13 km Phase 2: 3 TeV extension 48.5 km CERN site Prevessin Detectors and Interaction Point 0.5TeV = 13 Km 3 TeV = 48.5 Km

  16. Upgrade strategy from 500 GeV to 3 TeV • 500 GeV phase 500 GeV sectors with CLIC 502 structure at 80 MV/m (50 GeV/sect) with return loop and dumps positions at the optimum position for 3TeV Extra sector installed in space of BDS future extension at 3 TeV • Two upgrade alternatives from 500 GeV to 3 TeV: • CLIC G structures at 100 MV/m all along linac • Remove last sector to provide space for BDS and reuse components to build one of the additional sector • Adapt quadrupole focusing of the last 4 sectors from low to high En and change accelerating structures from 502 to G on the last 4 sectors • Install 20 additional sectors in each linac with G structures at 100 MV/m (62.5 MeV/sector) • CLIC G at 100 MV/m except for last 4 sectors with 502 at 80 MV/m • Remove last sector to provide space for BDS and reuse components to build one of the additional sector • Adapt quadrupole focusing of the last 4 sectors from low to high En but maintain 502 accelerating structures at 80 MV/m (50 MeV/sect) • Install 21 additional sectors in each linac (4*50MeV+21*61.9MeV) • 1 additional sector and total tunnel length increased by 868 m