A_RD_03 R/D for the High Power Couplers for ILC

A_RD_03 R/D for the High Power Couplers for ILC. Walid KAABI (LAL-Orsay, France) Eiji KAKO (KEK, Japan). 1. Acknowledgements. LAL-Orsay Team; Alessandro VARIOLA, Mickael LACROIX, Alice THIEBAULT KEK-STF Team; Hitoshi HAYANO, Toshio SHISHDO,

jparish
Download Presentation

A_RD_03 R/D for the High Power Couplers for ILC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. A_RD_03R/D for the High Power Couplersfor ILC Walid KAABI (LAL-Orsay, France) Eiji KAKO (KEK, Japan) FJPPL'2012 @ Clermont 1

  2. Acknowledgements • LAL-Orsay Team; • Alessandro VARIOLA, • Mickael LACROIX, • Alice THIEBAULT • KEK-STF Team; • Hitoshi HAYANO, • Toshio SHISHDO, • Ken WATANABE, • Yasuchika YAMAMOTO FJPPL'2012 @ Clermont 2

  3. Outline • Introduction • Activities of Input Couplers at LAL • Activities of Input Couplers at KEK • Plan of Coupler R & D in 2012’ • Summary FJPPL'2012 @ Clermont 3

  4. Introduction • Activities of Input Couplers at LAL • Activities of Input Couplers at KEK • Plan of Coupler R & D in 2012’ • Summary E. KAKO (KEK) 2012' May 28 FJPPL'2012 @ Clermont

  5. Introduction (1) KEK/ STF-1 Zo = 50 W Warm window Cold window f62 f62 Zo = 50 W Zo = 50 W LAL/ TTF-V FJPPL'2012 @ Clermont 5

  6. Introduction (2) LAL TTF-V couplers conditioned at KEK. FJPPL'2012 @ Clermont 6

  7. Introduction • Activities of Input Couplers at LAL • Activities of Input Couplers at KEK • Plan of Coupler R & D in 2012’ • Summary E. KAKO (KEK) 2012' May 28 FJPPL'2012 @ Clermont

  8. Coupler Activities at LAL (1) TTF-3 coupler • Working on TTF3 conditioning procedure improvement: • Decreasing time duration (handling, assembly and in-situ baking improvement) • Conditioning 2 coupler pairs in series • Delivering conditioned couplers for Flash machine-DESY. • Performing XFEL couplers Industrialisation phase. FJPPL'2012 @ Clermont 8

  9. Coupler Activities at LAL (2) Automation of coupler cleaning procedure: design of washing machine Ultrasonic cleaning: 1h • Reduce time procedure & work in hidden time • Improve procedure repeatability • Suppress pollution risk between the steps Drying cycle and cleaning quality test: 48h In situ backing: 75h FJPPL'2012 @ Clermont 9

  10. Coupler Activities at LAL (3) • The main coupler activity at LAL in the last two year: Contribution to the XFEL project by assuming the following tasks: • Industrial monitoring and coupler fabrication control at production sites. • RF conditioning of the 800 produced couplers at LAL. FJPPL'2012 @ Clermont 10

  11. Coupler Activities at LAL (4) • All process steps will take place in an ISO5 clean room (70 m2): • Leak test at reception, • Couplers in-situ baking (75h), • RGA connection and gas analysis (24h), • Antenna tuning, • RF conditioning (24 to 30h), • Pumping system removal and couplers disassembly, • Packaging in boxes and shipping. A 6-7 days process 8 couplers treated simultaneously. FJPPL'2012 @ Clermont 11

  12. Coupler Activities at LAL (5) Installation of an RF station delivering 5MW allowing 4 coupler pairs conditioning in the same time: FJPPL'2012 @ Clermont 12

  13. Introduction • Activities of Input Couplers at LAL • Activities of Input Couplers at KEK • Plan of Coupler R & D in 2012’ • Summary E. KAKO (KEK) 2012' May 28 FJPPL'2012 @ Clermont

  14. Coupler Activities at KEK (1) KEK-STF activities on cryomodule tests • STF - 0.5 : (2007) • 1 nine-cell cavity, 1 STF-1 coupler • STF - 1.0 : (2008) • 4 nine-cell cavities, 4 STF-1 couplers • S-1 Global : (2010) • 4 nine-cell cavities, 4 TTF-3 couplers, • + 4 nine-cell cavities, 4 STF-2 couplers • Quantum-Beam : (2012) • 2 nine-cell cavities, 2 STF-2 couplers • STF - 2 : (2014) • + 8 nine-cell cavities, 8 STF2 couplers FJPPL'2012 @ Clermont 14

  15. Coupler Activities at KEK (2) Two STF-2 couplers for S1-G (variable coupling) Four STF-1 couplers (fixed coupling) Eight STF-2 couplers for STF-2 #1 Six CW couplers for cERL FJPPL'2012 @ Clermont 15

  16. Coupler Activities at KEK (3) Assembly of capture cryomodule for QB accelerator (Oct. 2011) (Dec. 2011) E. KAKO (KEK) 2012' May 28 FJPPL'2012 @ Clermont

  17. Coupler Activities at KEK (4) KEK-STF Quantum-Beam Accelerator High-flux X-ray by Inverse-Compton scattering 10mA electron beam (40MeV, 1ms, 5Hz) Photo-cathode RF-gun Capture cryomodule ( two 9-cell cavities ) Collision point (Laser, electron beam) 2011, Dec : Cryomodule completed. 2012, Feb : Cool-down started, Mar : High power tests, Apr : First beam acceleration. FJPPL'2012 @ Clermont 17

  18. Coupler Activities at KEK (5) Comparison of cavity performance between V.T and C.T VT Results of MHI-12 and MHI-13 for Capture Cryomodule Vertical Test Cryomodule Test Operational Gradient E. KAKO (KEK) 2012' May 28 FJPPL'2012 @ Clermont

  19. Coupler Activities at KEK (6) STF-2 Project at KEK Capture Cryomodule (two 9-cell cavities) 2012’, Feb. Cool-down STF-2 #1 Cryomodule (eight 9-cell cavities) 2014’, Jan. Cool-down FJPPL'2012 @ Clermont 19

  20. Coupler Activities at KEK (7) High Pressure Gas Tests V.T results of 11 cavities for STF-2 Project 35 MV/m Capture Cryomodule STF-2 #1 Cryomodule STF-2 #2 Cryomodule Eight STF-2 couplers FJPPL'2012 @ Clermont 20

  21. Coupler Activities at KEK (8) Conditioning up to 200 kW (2 ms, 5 Hz), and 40 kW (CW) CW Input Couplers for cERL Injector Cryomodule (Apr. 2012) E. KAKO (KEK) 2012' May 28 FJPPL'2012 @ Clermont

  22. Introduction • Activities of Input Couplers at LAL • Activities of Input Couplers at KEK • Plan of Coupler R & D in 2012’ • Summary

  23. Plan of Coupler R/D in 2012’ • LAL : • Conditioning of XFEL couplers. • Automatic coupler cleaning machine. • Plasma cleaning of couplers. • KEK : • Beam operation of QB cryomodule. • Conditioning of 8 couplers for STF-2 #1. • Conditioning of cERL CW couplers at RT. • High power tests of cERL Injector module. FJPPL'2012 @ Clermont 23

  24. SUMMARY • Activities on coupler developments in • both LAL and KEK have been continued, • vigorously. • Collaborative work on coupler conditioning • was successfully carried out. • Discussion on the conditioning results • between LAL and KEK was very fruitful. FJPPL'2012 @ Clermont 24

  25. Thank you for your attention... FJPPL'2012 @ Clermont 25