1 / 18

Uncertainty and stakeholder management – a study of two railway projects Hans Petter Krane,

Uncertainty and stakeholder management – a study of two railway projects Hans Petter Krane, PhD student, NTNU. EURAM, Liverpool 14.05.2009. Introduction Background Main results, discussion Conclusions Questions, discussion. Outline of the presentation. Introduction Background

jsharp
Download Presentation

Uncertainty and stakeholder management – a study of two railway projects Hans Petter Krane,

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Uncertainty and stakeholder management – a study of two railway projects Hans Petter Krane, PhD student, NTNU EURAM, Liverpool 14.05.2009

  2. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Outline of the presentation • Introduction • Background • Main results, discussion • Conclusions • Questions, discussion

  3. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion What did we look at? • How the Management of Stakeholders and Risks is Combined in two fairly ”media exposed” projects • How risks to the functionality delivered by the projects are handled • And how both internal and external stakeholders are handled

  4. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion What did we believe? • Projects are not giving priority to functionality delivered • Focus mostly on external stakeholders • Focus mostly on threats • Large projects have most resources; will do it best

  5. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion What did we find? • Large project focused on costs & time – small project on ”getting it right” • Both projects studied were mostly focussed on neighbours • Main focus for both projects: Threats • – And the implications of this ? ……

  6. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion The setting • Look at projects with ”high profile” towards society • -That have much interaction with their environment • -And may easily be critisised • Important risks/uncertainties will be stakeholder-related

  7. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Further issues in focus Approval of projects for further develpment For projects > 500MNOK (60 M€), public sector • Governmental QA-regime • Stakeholder and power relations • The relation: Line organisation   Project

  8. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Research questions • In the paper formulated as: • Explore how risk management worked in the projects • Study influence from internal and external stakeholders • But here also deeper into: • How were risks to ”functionality delivered” handled? • How did power relations around the projects work?

  9. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion The cases • Large project: • New double track line • Commuter area near capital • 450 Mill € • Primo 2001 – Aug. 2005 • Small project: • Station upgrade • Commuter area near capital • 3 Mill € • Autumn 2006 – summer 2007 • Qualitative research, Interview based • 24 persons (sum both projects)

  10. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Some findings, with comments • Here we have just gone deeper into a few (– The rest you must read yourself!)

  11. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Example 1:”The Curve” (in the small project) • Safety requirements => Major alterations to plans • Strong restrictions to establishment of new stations in curves • Several changes in approach / possible outcome as time passed • Expressing different perceived power among stakeholders

  12. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Example 2: ”The Neighbourhood” (in both projects) • Handling of neighbours defined as crucial (possibly stopping project, giving bad esteem) • Hence: A well prepared strategy, projects organised to keep up good relations • Stable situation over long period

  13. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Example 3: ”The Reductions” (in the large project) • “Reduction list” prepared if cost overruns • I.e. prepared for reductions in functionality/ benefits • When used: Internal disputes in railway authority regarding use and effects • Seemingly internally stronger tensions regarding • communication • stakeholder relations • power relations than externally

  14. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Some comments • ”The Curve” • Strong safety authority (SJT) • Multi phase development of relations • ”The Neighbourhood” • Stable situation – taken care of - all OK! • ”The Reductions” • Unclear area • Tensions, unsettled

  15. Risk area Functionality/ Benefits Cost, delivery Positive Opportunities Risk polarity X Negative Risk • Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Possible conclusions • Neighbours – well managed, stable relations • Safety authority (SJT) – unclear power relations • Line organisation  Project – unclear, strong interests • For risk management as a whole:

  16. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Summing up: • This was a fairly loose collection of observations, but most important lessons are: • Found dynamic, new, unexpected relations – if not taken serious, may present major challenges to project success • Challenging interest differences found Line organisation  Project organisation – Problems if not recognised

  17. Introduction • Background • Main results, discussion • Conclusions • Questions, discussion Questions, discussion

  18. Thank you for your attention ! • hans.p.krane@ntnu.no (Tel. +47 975 15 809)

More Related