An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HARPS ... North • OG organization and Schedule HARPS-N PDR Harvard CfA, 06/07-12-2007

  2. Project schedule OG • 2008: Procurement of components • 04/2008 - 04/2009: Manufacturing of mechanical parts for vacuum and optics • 01/2009: Start assembly • 03/2009: Delivery of FA, DU and Control HW and SW by CfA to OG • 04/2009 - 07/2009: Integration and tests OG

  3. OG manpower Phases A-D • WP-11 Science Support: Lovis, Pepe • WP-14 Interface Engineering: Fleury, Hughes • WP-21 Fiber run procurement: Pepe + Szentgyorgyi • WP-25 Optics procurement: Pepe + Szentgyorgyi • WP-26 Vacuum System: Fleury, Hughes, Pichard • WP-27 Detector Dewar: Hughes, Fleury, Pepe • WP-28 Spectrograph Mechanics: Hughes, Fleury, Pichard, 2 mechanics, 1 electronics • WP-51 DRS: Lovis • TBD: WP 50 OPS and WP-52 Data archiving

  4. Item Responsible Delivery To whom Echelle, collimator CfA December 2008 OG Prism OG August 2008 CfA Grism CfA December 2008 OG Objective OG December 2008 OG Opto-mechanics OG December 2008 OG Optical bench OG December 2008 OG Detector dewar OG July 2008 CfA Science camera CfA March 2009 OG Vacuum system OG December 2008 OG Fiber run OG December 2008 OG Sp. electronics OG August 2008 CfA Procurement scheme

  5. Item Responsible Delivery To whom Adapter Unit CfA March 2009 OG HW & SW CfA March 2009 OG Control SW CfA March OG Trigger & DRS OG March 2009 OG Obs. Prep. SW TBD March 2009 OG Spectrograph room CfA July 2009 WHT Spectrograph OG August 2009 WHT Archiving SW TBD August 2009 WHT Procurement scheme

  6. Procurement funding • Objective, Vacuum System: Ordered and paid by OG • Collimator, echelle: Ordered and paid by CfA • Detector dewar: Procured by OG, funding transfer CfA -> OG • Optical supports: Manufactured by OG • Other opto-mechanics: Scheme? • Spectrograph electronics: Scheme?

  7. All the best, HARPS-N !