90 likes | 250 Views
eFEX PDR. Scope Actions Schedule. Introduction. eFEX PDR was held 12 Feb Reviewers Stefano (chair), Sam (Tile Cal), Wade (Hub module), Uli (L1Topo + jFEX), Richard (Test module), Jim+DavidS (physics), Maurice (ROD), Stefan Hass (CTP + CERN electronics group), Hucheng Chen ( LAr )
E N D
eFEX PDR Scope Actions Schedule
Introduction • eFEX PDR was held 12 Feb • Reviewers • Stefano (chair), Sam (Tile Cal), Wade (Hub module), Uli (L1Topo + jFEX), Richard (Test module), Jim+DavidS (physics), Maurice (ROD), Stefan Hass (CTP + CERN electronics group), Hucheng Chen (LAr) • Bruce, Rainer, David & David as ex-officio members • Many thanks to all involved • Outcome: • project was approved, • a few minor design changes were suggested and agreed • actions were identified, to be pursued by eFEX design team & wider L1Calo group
Scope • Update the conceptual design • Verify design meets physics requirements • Check whether any open issues appear from the viewpoint of the design, on the overall ATLAS Trigger architecture, that should be brought to the attention of a wider community • Check specifications is sufficiently defined to proceed to prototype • Check whether the specifications of the interfaces are sufficiently defined to proceed to the preliminary neighbouring components • Review cost, schedule and organisation • Not reviewed: production-related issues, e.g., final engineered design, detailed cost estimates, production schedule.
Requirements External to L1Calo • Identified 1 requirement that proposed L1Calo system imposes on external systems: • L1Calo expects upstream systems (LDPS, L1Calo PPr and eventually TileDPS) to record the incoming data to DAQ. • Needs to be formalised with those groups (eFEX doesn’t have capacity to transmit a copy of all received data)
Actions for L1Calo (1)(beyond eFEX Engineering Team) • Simulation studies are needed to establish • baseline algorithms for the eFEX for seeding candidates, measuring their ET and applying hadronic vetos. • No. TOBs that eFEX must handle • TOB-merging functionality required of the eFEX, e.g.: • disambiguation of EM and Tau candidates; • prioritisation of TOBs (including sorting, although suspect precluded by latency); • prescaling • overflow handling & flagging • any need for the eFEX to compute multiplicities. • The physics groups should be questioned to establish the lowest required thresholds for EM & Tau candidates
Actions for L1Calo (2)(beyond eFEX Engineering Team) • A Review of L1topo is required, to establish the constraints it places on the design of the FEXs and the Optical Plant: • How many L1topo boards are needed to accept one copy of all the inputs from the FEXs plus Muon system? • How does each L1Topo Processor FPGA on a L1Topo board get the inputs it needs? • If more than one L1Topo board is needed, how will the topo algorithms be divided? • How will multiplicity triggers be implemented in L1Topo? • What is the maximum number of TOBs that can actually be accessed in a topoalgorithm? • How many copies of inputs does all this imply?
Actions for L1Calo (3)(beyond eFEX Engineering Team) • Plan for the transition from the CP/JEP-based trigger to the new system should be documented • Handling of environment data to DCS and ATCA Shelf Controller – coherent scheme needed • Mapping of ECAL and HCAL fibres into MTP sockets: is segregation required? • (Optical plant issue) • Feasibility of common RTM design for the eFEX and jFEX should be investigated • Consider renaming L1Calo ROD (which also carries near real-time signals in Run 4)
Actions for eFEX Engineering Team • Check all proposed data formats with interfacing systems • Change design to allow handling of over-lapping readout time frames • Established need (or not) for playback memories on all inputs • Amend buffering requirement on Readout path to 6s & assess impact • Document plan B for FPGA configuration, should System ACE IP prove unobtainable • Inform ATLAS electronics group of power (cooling) requirements • And many other helpful recommendations of more local impact….
Schedule • First draft of report imminent, for circulation amongst reviewers • Most pressing issues raised are the physics questions • Aim for first answers in summer – allows hardware changes to be incorporated in prototype