An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CIF 301 Activity PlanningUnit 2

  2. Introduction • The unit will cover several methods • Precedence analysis • Gantt Charts • PERT / CPA • Also ….. • Microsoft Project will be covered in labs

  3. Introduction 2 • Activity Planning will help to: • ensure that the appropriate resources will be available precisely when required • avoid different activities competing for the same resource at the same time • produce a detailed schedule showing which staff carry out each activity • Produce a detailed plan against which actual achievement may be measured • produce a timed forecast • re-plan the project during its life to correct drift from a target

  4. Precedence analysis • Must be done before an activity plan can be produced • Reviews the activities that are to be carried out • Decides what activities must be carried out before particular activity can start

  5. Gantt Charts • Developed by Henry Gantt, around 1917 • Gantt charts are easy to use and produce • Very useful for use on less complex projects

  6. Gantt Charts

  7. Gantt Charts • Draw the following Gantt chart Tasks Precedence Time a - 5 days b - 4 days c a 6 days d b 2 days e b 5 days f c,d 8 days

  8. Gantt Charts

  9. Network planning models • PERT • The Program Evaluation and Review Technique • CPM • Critical Path Method • Also know as CPA • Critical Path Analysis

  10. d 2 a g 5 e b End Start 1 7 3 h c f 6 4 Network planning models • A simple on arrow network model

  11. Terminology • Activity • Event • Network • Path • Critical

  12. 2 C=3 A=6 6 3 H=2 4 1 D=4 B=4 E=3 G=3 5 F=10 Terminology • On Arrow Network diagram showing critical path in red

  13. Network syntax • Time moves from left to right • Nodes are numbered sequentially • A network may not contain loops • A network may not contain dangles • Precedents are the immediate preceding activities • Dummy activities can be used to indicate a particular precedence

  14. a b 1 2 3 Network syntax • Time moves from left to right • Nodes are numbered sequentially

  15. 4 d c a 1 2 3 b This is not allowed Network syntax • A network may not contain loops

  16. b a 1 2 3 c 4 This is not allowed Network syntax • A network may not contain dangles

  17. Design Build Commission 1 2 3 4 Network syntax • Precedents are the immediate preceding activities

  18. a c Wrong 1 2 3 b a 2 1 Right c b 3 4 Network syntax • Dummy activities can be used to indicate a particular precedence

  19. On Arrow Networks • Draw the following as an on arrow network Tasks Precedence Time a - 5 days b - 4 days c a 6 days d b 2 days e b 5 days f c,d 8 days

  20. 2 a start 1 b 3 On Arrow Networks • How to start …..

  21. c 2 4 a start 1 b d 5 3 e 6 On Arrow Networks • What not to do

  22. c 2 a start 1 b d 3 e On Arrow Networks • A better way ……

  23. c f 2 4 6 a start 1 d b e 3 5 On Arrow Networks • It is then less confusing that c & d go to the same event … but what about e & f ?

  24. c 2 4 a f start 1 d end 5 b e 3 On Arrow Networks • The completed on arrow network ….

  25. On Arrow Networks • Another on arrow network to draw Tasks Precedence Time a - 6 weeks b - 4 weeks c a 3 weeks d b 4 weeks e b 3 weeks f - 10 weeks g e,f 3 weeks h c,d 2 weeks

  26. 2 C=3 A=6 B=4 D=4 H=2 1 3 4 6 E=3 G=3 F=10 5 On Arrow Networks • The network with activity times added

  27. Event number Earliest date Latest date Slack Event On Arrow Networks • Each event circle can contain the information below

  28. 2 6 3 4 1 5 Event numbers

  29. 2 C=3 A=6 6 3 H=2 4 1 D=4 B=4 E=3 G=3 5 F=10 Timed activities

  30. 2 6 C=3 A=6 6 3 H=2 4 1 D=4 13 B=4 4 9 0 E=3 G=3 5 F=10 10 Forward pass

  31. 2 6 8 C=3 A=6 6 3 H=2 4 1 D=4 13 13 B=4 4 7 9 11 0 0 E=3 G=3 5 F=10 10 10 Backward pass

  32. 2 6 8 C=3 2 A=6 6 3 H=2 4 1 D=4 13 13 B=4 4 7 9 11 0 0 0 3 2 0 E=3 G=3 5 F=10 10 10 0 Event, Slack and Activity Float

  33. 2 6 8 C=3 2 A=6 6 3 H=2 4 1 D=4 13 13 B=4 4 7 9 11 0 0 0 3 2 0 E=3 G=3 5 F=10 10 10 0 The Complete On Arrow Network

  34. Precedence Networks • Precedence network • Becoming more common • Often preferred by project managers

  35. Precedence Networks • Syntax the same as for On Arrow networks • Except there are no dummy activities • Precedence networks must start with a start node and end with a end node

  36. a d g End Start b e c f h Precedence Networks • A simple precedence network

  37. d 2 a g 5 e b End Start 1 5 3 h c f 5 4 • This is the same network drawn as an On Arrow network

  38. Precedence Networks • Draw the following as an Precedence network and an On Arrow Network Tasks Precedence Time a - 5 days b - 4 days c a 6 days d b 2 days e b 5 days f c,d 8 days

  39. a c f End Start d b e Precedence Networks • The completed Precedence Network

  40. c 2 4 a f start 1 d end 5 b e 3 • The same network drawn as an On Arrow Network

  41. Precedence Networks • Draw another precedence and on arrow network Tasks Precedence Time a - 6 weeks b - 4 weeks c a 3 weeks d b 4 weeks e b 3 weeks f - 10 weeks g e,f 3 weeks h c,d 2 weeks

  42. a c End Start d h b e g f Precedence Networks • The completed Precedence Network

  43. 2 C=3 A=6 B=4 D=4 H=2 1 3 4 6 E=3 G=3 F=10 5 • This is the same network drawn as an On Arrow network

  44. Duration Earliest Finish Earliest start ES D EF Description LS F LF Latest Start Latest Finish Float Precedence Networks • Adding more information to the node