1 / 11

Project Management

Project Management. Unit 6. Project Schedule (contd). Three types of floats (slacks): Total Float (also called Float) : The total time an activity can be delayed without delaying project completion.

julie
Download Presentation

Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management Unit 6

  2. Project Schedule (contd) • Three types of floats (slacks): • Total Float (also called Float) : The total time an activity can be delayed without delaying project completion. • Free Float : The total time an activity can be delayed without delaying the early start of any successor activity. • Project Float : The total time a project can be delayed without passing the customer-expected completion date.

  3. Duration Compression Techniques • Working on ways to shorten the project duration • Two techniques • Crashing • Fast Tracking • One or both techniques can be applied to reach a completion date earlier than the preliminary schedule shows.

  4. Crashing • Add more resources to the activities on the critical path. • Usually adds cost. • Can do a cost-benefit analysis. • Fast Tracking • Activities that can are in sequence can be done in parallel. • May increase risk.

  5. Performance Measurement You are working on a project that consists of 5 activities one after another in sequence. The relationships among these activities are all Finish-to-start from start till end. Each activity requires 20 hours of work, and costs $2,000. The duration of each activity is one week. Four weeks after start, you found that only 3 activities have been completed. The amount spent so far is $7,000. What can you say about the project’s performance ?

  6. Earned Value (EV) Analysis • BAC (Budget At Completion) • The amount budgeted for the entire job. • EV (Earned Value) or BCWP (Budgeted Cost of Work Performed) • Estimated value of work actually performed till date. • Equals to percentage of completion multiplied by BAC

  7. PV (Planned Value) or BCWS (Budgeted Cost of Work Scheduled) • Estimated value of work planned to be completed • AC (Actual Cost) or ACWP (Actual Cost of Work Performed) • Actual cost incurred till date.

  8. CV (Cost Variance) • BCWP – ACWP • Schedule Variance • BCWP - BCWS • Cost Performance Index • CPI = BCWP/ACWP • Schedule Performance Index • SPI = BCWP/BCWS

  9. How to use these values ?

  10. How to use these values ?

  11. Quiz: How is the project doing?

More Related