FVTX Monthly/Quarterly Report March 2009 Cost Summary Schedule Summary Current technical status of each WBS item. Changes to Management Plan Costs - January. Cost Savings/Increases of previous Quarters not repeated
E N D
FVTX Monthly/Quarterly Report • March 2009 • Cost Summary • Schedule Summary • Current technical status of each WBS item
Changes to Management Plan Costs - January • Cost Savings/Increases of previous Quarters not repeated • Current Expectation is that FNAL will spend ~$90k of $145k on FPHX Round I prototyping • We are transferring $30k to LANL for FPHX testing, covering part of Jon K.’s salary (not used by FNAL) • $30k of sensor testing funds transferred to LANL to cover Jon (covered in baseline) • $40k added to design PCB-version HDI • $40k for Clock and DAQ Interface boards (not explicitly called out from ROC/FEM previously, so currently include this as added cost) • $37k for ROC FPGA programming and testing added • $61k less spent for Electrical Integration than budgeted in MP • Overall contingency remains approximately the same ($940k) as MP ($927k)
New Cost Information • We have our first quote on HDI production: • $185k (with 10% spares and assume small HDIs same cost as large) • $177k in MP (including contingency) • HYTEC Design estimate increased by $30k, may increase more when cable routing tasks are added • Overall contingency $908k compared to MP-$927k
16 channels pulsed FPHX Prototype tests • No significant new information since January report (working on preparations for wedge test) • Gave list of proposed changes to FNAL; they gave preliminary estimate for time to complete work (analog ~1 week, digital may be few weeks) • Working to make contact with Ray Yarema to determine 2nd round schedule • FPHX Review scheduled for Thursday afternoon (PHENIX internal) 64 channels unmasked
FVTX Technical Status - HDI and Sensors • High Density Interconnect, UNM + LANL • Kapton HDI in shipment • HDI PCB expected end of this week • SiDet prepared to bond to both versions of HDI • LANL test stand prepared to read out 13 chips/connector • Preparing for basic tests of HDI before it goes to wedge assembly
FVTX Technical Status - Sensors • UNM completed verification of Hamamatsu tests – all agreed • UNM will ship few to SiDet for assembling onto HDIs
FVTX Technical Status - DAQ • ROC board delivered to LANL • Few board re-works needed, but all handled easily at LANL • Successful readout of chip, good calibration data collected. All looks good so far. • 13-chip readout mocked up by fanning out single chip data to 13 inputs • FVTX ROC design in progress • FEM in progress DATA “13 chips” FPHX ROC ROC board communicating with single FPHX chip, oscilloscope and computer readout.
FVTX Technical Status - Assembly • SiDet will assemble first kapton and PCB HDI wedges • SiDet actively working with components that they have • Assembly preparation work at BNL continues • Rapid-prototype cage purchased Sensor inserted Chips placed on HDI
Summary • FPHX, sensor tests • LANL/Tom Zimmerman analog tests completed and no major issues • Some issues with beam clock output on large events • Sensor testing all good (strip numbering missing only small issue) • HDI • Preparing for tests of HDI before wedge assembly • Wedge tests • Expect wedge assembly to begin soon • SiDet tested assembly process, small mods to chip placement especially • ROC/FEM • Roc prototype testing underway • Prototype ROC will be used for wedge tests • FEM still behind schedule, but not on critical path