1 / 32

IMPACTS OF LARGE DISTRIBUTED GENERATORS ON CENTERPOINT ENERGY’S DISTRIBUTION SYSTEM

Presented by Ed Briggs, P.E. Manager of Electric Distribution Planning SWEDE Presentation May 9, 2014. CenterPoint Energy Proprietary and Confidential Information. IMPACTS OF LARGE DISTRIBUTED GENERATORS ON CENTERPOINT ENERGY’S DISTRIBUTION SYSTEM. SAFETY MOMENT.

kaiya
Download Presentation

IMPACTS OF LARGE DISTRIBUTED GENERATORS ON CENTERPOINT ENERGY’S DISTRIBUTION SYSTEM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presented by Ed Briggs, P.E. Manager of Electric Distribution Planning SWEDE Presentation May 9, 2014 CenterPoint Energy Proprietary and Confidential Information IMPACTS OF LARGE DISTRIBUTED GENERATORS ON CENTERPOINT ENERGY’S DISTRIBUTION SYSTEM

  2. SAFETY MOMENT PUBLIC AND EMPLOYEE SAFETY IS THE MOST IMPORTANT CONSIDERATION OF DG DESIGN, CONSTRUCTION AND UTILITY INTERCONNECTION !

  3. WHAT IS DISTRIBUTED GENERATION (DG) ? Texas PUC Substantive Rule 25.211 An electric generating facility located at a customer’s point of delivery (point of common couple) of ten megawatts (MW) or less and connected at a voltage less than 60 kilovolts (kV) which may be connected in parallel operation to the utility system.

  4. DISTRIBUTED GENERATION BY FUEL TYPE

  5. Total Pending and Connected DGs Through 4/16/14

  6. Large DG (7500+ KW) Statistics

  7. WHATS DRIVING THE LARGE DISTRIBUTED GENERATION INTERCONNECTIONS? Emergency Response Service (ERS) or Demand Response Close transition-parallel with the utility grid for less than 1 second (closed transition switching) Parallel operation with power export option Parallel operation with no power export

  8. IMPACTS OF LARGE DISTRIBUTED GENERATION LOAD VOLTAGE POWER FACTOR FAULT CURRENT CIRCUIT PROTECTION LATERAL FUSE COORDINATION EFFECTIVE GROUNDING RELIABILITY SAFETY

  9. DG SIZE RATING A GENERATOR NAME PLATE RATING SHOWS 2500 kVA @ 80% POWER FACTOR • WHAT IS THE DG kW CAPACITY ? • 2000 kW or 2500 kW ? SAME QUESTION AS ABOVE EXCEPT THE PRIME MOVER OF THE GENERATOR IS A DIESEL ENGINE RATED AT 1800kW • WHAT IS THE DG kW CAPACITY ? • 1800 kW or 2000 kW or 2500 kW ?

  10. 12.47 kV DISTRIBUTION FEEDER DG STUDY • 7 GENERATORS RATED AT 2500 kW EACH (7 X 2500 = 17,500 kW) • PRIME MOVER DIESEL ENGINE RATED AT 1800kW • ACTIVE GENERATION = 7 X 1800 = 12,600 kW • 12.47 kV FEEDER RATED AT 12,960 kW • DG VOLTAGE CONTROL @ 100%PF

  11. 12.47kV FEEDER PEAK LOAD 10,260 kW 540 kVAR 99.9 PF SUB DG

  12. DISTRIBUTIVE GENERATION SETUP (PCC IS POINT OF COMMON COUPLING) TO SUBSTATION Utility Source Utility source PCC 2 PCC 1 12.47 kV BUS 2500 kVA TRANSFORMER 2500 kW GENERATOR 480Y277V

  13. DG VOLTAGE TRIP SETTING DG TRIPS IF: VOLTAGE = 126V FOR 30 SECONDS VOLTAGE = 132V FOR 10 CYCLES CUSTOMER WANTS TO OPERATE DG AT 100% PF

  14. DG ANALYSIS CNP SUBSTATION VOLTAGE REGULATION IS SET AT 122V TO 125V FOUR CIRCUIT MODELING SENARIOS ARE: • SUMMER PEAK LOADING • SUB AT 125V • SUB AT 122V • OFF-PEAK LOADING • SUB AT 125V • SUB AT 122V

  15. LOCATION AT PCC WITH SUB AT 125 V WITH SUMMER PEAK LOAD

  16. LOCATION AT PCC WITH SUB AT 122 V WITH SUMMER PEAK LOAD

  17. LOCATION AT PCC WITH SUB AT 125 V WITH OFF-PEAK LOAD

  18. LOCATION AT PCC WITH SUB AT 122 V WITH OFF-PEAK LOAD

  19. LOCATION AT PCC WITH SUB AT 125 V WITH SUMMER PEAK LOAD & EFFECTS OF CAPACITOR BANKS

  20. DG CAN REDUCE THE VOLTAGE AT PCC BUT RESULTS IN INCREASED kVAR WHICH RESULTS IN A 394 kVA DEMAND THUS A $$$$$ MONTHLY BILL

  21. DURING OFF PEAK SEASON 4 DGs BACKFEEDS SUBSTATION TRANSFORMER WITH 2279 kW Substation Transformer 2279 kW Circuits #1 #3 #2

  22. 12.47kV FEEDER PEAK LOAD 10,260 kW 540 kVAR 99.9 PF DG SUB DG DG

  23. At PCC with Sub at 125 V with Summer peak load & DG located near Sub

  24. At PCC with Sub at 125 V with Summer peak load & DG located at end of circuit

  25. DG INCREASES CIRCUIT FAULT CURRENT • AND CAUSES 100T FUSE NOT TO COORDINATE WITH 65T, MUST CHANGE LATERAL TO A FEEDER AT CUSTOMER EXPENSE Without DGs, I LG max = 2578 A With 7 DGs, I LG max =3976 A 65T fuse 100 T fuse

  26. DG ELEVATES FAULT CURRENT ON SUBSTATION BUS AND ADJACENT CIRCUITS • A FAULT ON ADJACENT CIRCUIT WILL BE FED BY DG CIRCUIT AND MAY RESULT IN TWO CIRCUITS OPERATING THUS IMPACTING RELIABILITY • LATERAL FUSE COORDINATION WILL NEED TO BE ASSESSED ON ADJACENT CIRCUITS DUE TO HIGHER FAULT CURRENT

  27. Line to Ground Fault Currents

  28. EFFECTIVELY GROUNDED SYSTEM PER IEEE STANDARD 142

  29. EFFECTIVELY GROUNDED SYSTEM CHECK ?CUSTOMER’S HIGHSIDE RESISTIVE GROUNDING 24 OHM ON 12.47kV SIDE OF THE TRANSFORMER

  30. CNP REQUIRES TRANSFER TRIP FOR DGs OVER 2000 kW. HOWEVER CIRCUIT SWITCHING CAN SCUTTLE THIS N.C. N.O. (TIE) Sub 1 Sub 2 N.C. Utility crew closes the tie switch Utility crew opens the N.C. switch DG will be transferred from a feeder from sub 1 to another feeder from sub 2 Lateral DG

  31. SWEDE 2015 NEXT YEAR’S PRESENTATION DG ACTUAL DATA VERSUS MODELED THANK YOU !

  32. NEXT YEARDG ACTUAL VERSUS MODELED THANK YOU ! Any Questions ?

More Related