1 / 11

Electrical Power Systems (WBS 4)

Electrical Power Systems (WBS 4). S. Ramakrishnan NCSX PROJECT – D TO C Site DC Transmission PDR February 17 2004. Electrical Power System Tasks. Provide Source of all Electric Power for NCSX * Project CDR successfully held in May 2002; PDR successfully held in Oct. 2003 All AC Power

kaiyo
Download Presentation

Electrical Power Systems (WBS 4)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX PROJECT – D TO C Site DC Transmission PDR February 17 2004 S. Ramakrishnan Slide 1

  2. Electrical Power System Tasks • Provide Source of all Electric Power for NCSX *Project CDR successfully held in May 2002; PDR successfully held in Oct. 2003 • All AC Power • At all Distribution Voltage levels • 13.8kV,4.16kV,480V, 208/120V • Includes Experimental AC Power • Includes AC Power to Future NB • Includes all Auxiliary AC Power up to Power Panels • All DC Experimental Power • Provide DC power for stellarator coil systems • 3 Modular, 1 TF, and 5 PF coils grouped in SIX circuits • PS requirements based on First Plasma Scenario • Clear path for future upgrades (other scenarios, flexibility) • Provide Diagnostics support for Sensor cabling • Grounding S. Ramakrishnan Slide 2

  3. PPPL Site Plan PPPL Site Plan FCPC BLDG FCPC BLDG DC Transmission DC Transmission TEST Cell TFTR Test Cell NCSX Control Room Location NCSX Control Room Location NCSX C-Site Location NCSX C-Site Location MG BLDG MG BLDG S. Ramakrishnan Slide 3

  4. D-Site Power Supplies • D-site power supplies used for Modular, TF, and PF circuits • Ample power and stored energy available (475 MVA and 2.2 GJ per MG) • Ample flexibility for future upgrades (74 PSS Exist) • Only 40 needed in Final Phase • C-site supplies available for Trim coils S. Ramakrishnan Slide 4

  5. Power Supplies Shared with NSTX S. Ramakrishnan Slide 5

  6. TYPICAL CIRCUIT NCSX CT- Current Transducer PT-Voltage Transducer G- Ground fault Relaying S. Ramakrishnan Slide 6

  7. Typical Circuit Arrangement Contd. • DC power transmitted from D-site (FCPC) to C-site (EF/OH Bldg) via overhead transmission (1000 MCM cables) • Disconnect and grounding switches provided at both ends • Existing cables used to connect to MG bus to Test Cell • Current/ Voltage transducers provided • Rapid changeover (4 hrs) possible S. Ramakrishnan Slide 7

  8. DC Transmission Structure • Design of Structure sub-contracted to Burns Group (BG) • BG has submitted preliminary drawings for PPPL Review and Comments • This review is to provide comments to BG on the proposed Structure S. Ramakrishnan Slide 8

  9. Schedule for Installing DC Transmission • BG to Complete Design by 03/31/04 • Present the final BG design in an FDR at PPPL before end of April 2004. • PPPL to provide comments on the preliminary design by BG by 02/27/04 S. Ramakrishnan Slide 9

  10. Conclusions • Sharing D-site power supplies with NSTX is cost-effective for powering NCSX coils • Technical risks are minimal • Since this is standard electrical work • Cost risks are modest • Schedule risks are addressed • Enough Float in Schedule • Is performed by experienced personnel. • Careful planning with NSTX operating schedule • Completion in time to support PTP/ISTP • Highest priority to Personnel Safety with Disconnect & Ground switches and Mechanical & Electrical Interlocks S. Ramakrishnan Slide 10

  11. NCSX Power System One line S. Ramakrishnan Slide 11

More Related