1 / 17

Electrical Power Systems (WBS 4)

Electrical Power Systems (WBS 4). S. Ramakrishnan NCSX PROJECT – D TO C Site DC Transmission PROJECT MANAGEMENT MEETING August 05 2004. Electrical Power System DC TRANSMISSION. This work is being performed per WP1118 DC Transmission (Outdoor) PDR was successfully held on 02/17/ 2004.

kawena
Download Presentation

Electrical Power Systems (WBS 4)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX PROJECT – D TO C Site DC Transmission PROJECT MANAGEMENT MEETING August 05 2004 Raki Slide 1

  2. Electrical Power System DC TRANSMISSION • This work is being performed per WP1118 • DC Transmission (Outdoor) PDR was successfully held on 02/17/ 2004. • DC Transmission (Outdoor) FDR was successfully held on May 14 2004. • DC Transmission (Indoor part) FDR was successfully held on July 29 2004. • BURNS ENGINEERING CO. performed the design work of the outdoor portion of the DC transmission (through BOA) and prepared the design package • We completed the design work of the transmission extension to the equipments in each location. • Statement of Work NCSX-SOW-432-02-00 was generated by Henry Carnevale for the installation of the Outdoor part of the transmission including the penetrations into the buildings. • MAUL ELECTRIC Co. has been issued a Sub-contract S005128-F for installing the transmission system. • Project schedule - job to be performed starting August 08 through October 31 2004 Raki Slide 2

  3. PPPL Site Plan FCPC BLDG DC Transmission TEST Cell NCSX Control Room Location NCSX C-Site Location MG BLDG MG BLDG PPPL Site Plan FCPC BLDG DC Transmission TFTR Test Cell NCSX Control Room Location NCSX C-Site Location Raki Slide 3

  4. WORK PERFORMED SO FAR • DC Transmission from D to C Site was proposed in November 2000 • The idea was developed further in several reviews in early 2001. Facilities Department (Carl Potensky was advised of the developments – this was to enable to perform site studies for positioning the towers • When there was a consensus to the approach , under Basic Order Agreement S-04236-F, Job Order # 3 (Title 1) was issued TO Burns through FACILITIES DEPT in December 2001. This was to provide an estimate for the task • Burns provided their input of estimate on January 11 2002 through Henry Carnevale. • Facilities department was studying the route in 2002/2003 • Burns were asked to perform the design work and under BOA issued Title 2 services through Facilities Department on December 12 2003. Facilities Dept gave input to Burns for location of Piers. • Burns submitted their PDR version ( also surveyed) in early Feb.2004; ( PDR held on Feb.14 2004) • FacilitIes Dept. conducted GPR on proposed locations of Piers in March/April 2004 Raki Slide 4

  5. DC TRANSMISSIONORGANIZATION CHART FOR MANAGEMENT Raki Slide 5

  6. DC TRANSMISSIONPreliminary Schedule submitted By Maul July 13: Award Project (by PPPL) - DONE July 14 - Order Cable Tray July 23 - Submit Steel Shop Drawings July 30 - Shop Drawings Approved August 09 - Start Steel Fabrication (Runs through September 17) August 09 - Lay out piers at Site, obtain digging permits Week of August 16 to 20 - Receive Cable Tray August 16 - Start Excavation of Piers August 23 - Iron work in Piers, pour concrete August 30 - Start Steel erection September 07 - Install grd. rods and grounding cabling each new Pier location  September 13 - Start Painting - continue steel erection - make building penetrations September 20 - Start installing cable tray structural support brackets to the steel and follow behind installing cable tray - complete steel erection - continue painting.  September 27 - Complete Painting - continue installation of support brackets and cable tray.  October 18 - Complete cable tray installation - start installation of 500 mcm ground cable. October 25 - Installation of structure and cable tray system complete. Ready for cables October 26 - Start installing cables. Raki Slide 6

  7. DC TRANSMISSIONJob Break up • SALIENT PARTS OF JOB • PPPL SAFETY TRAINIG (GET) • DAILY JHA REVIEW • LOCKOUT & TAGOUT • DAILY LOG • DIGGING • CONCRETE POURING • STEEL ERECTION (INCLUDES WELDING) • PAINTING • CABLE TRAY INSTALL • INSTALL GROUNDS • INSTALL CABLES • PENETRATIONS & SEALING (PERMITS ETC.) • ENGINEERING OVERVIEW Raki Slide 7

  8. DC TRANSMISSIONJob Break up Contd. • SAFETY TRAINING (GET)- (TRAINING DEPT). • MAUL SAFETY MANUALS & JHA REVIEWED BY JERRY LEVINE & BILL SLAVIN • WELDING QUALIFICATIONS REVIEWED BY BOB PARSELLS • GET TRAINING FOR 13 CREW ARRANGED TO BE HELD 08/10/04 - REGINA • DAILY JHA REVIEW WITH CREW – DON McBRIDE & BILL SLAVIN & OTHERS AS REQD. • LOCKOUT & TAGOUT; ROPING OFF AREAS • FCPC TF1 TRFMR. BREAKERS – JIM CORL/DMCBRIDE • SQT10 - ART WISE/DMCBRIDE • SQT11 - AS NEEDED BY ART WISE/DMCBRIDE • STREET LIGHTING – AS NEEDED BY FACILITIES • TELEPHONE LINE – AS NEEDED BY FACILITIES • ROAD BLOCKS – AS NEEDED BY FACILITIES • ROPING OFF AREAS AS NEEDED – FACILITIES/DMCBRIDE Raki Slide 8

  9. DC TRANSMISSIONJob Break up Contd. • DIGGING • (OVERSIGHT BY FACILITIES DEPT & SAFETY). • FACILITIES DEPT. WILL AGAIN CONDUCT GPR • SURVEY BY MAUL • PERMITS – BASED ON GPR AND ENGINEERING REVIEW • CONCRETE POURING (OVERSIGHT BY DEPT & SAFETY). Raki Slide 9

  10. DC TRANSMISSIONJob Break up Contd. • STEEL ERECTION • (LIFT MANAGER &, SAFETY) . • PPPL LIFT MANAGER WILL OVERSEE LIFTS • PPPL WILL VERIFY QUALIFIACATIONS • PAINTING (OVERSIGHT BY DMCBRIDE/SAFETY) • CABLE TRAY INSTALLATION (OVERSIGHT – DON McBRIDE /SAFETY & R.Van KIRK) • GROUNDING (OVERSIGHT – DON McBRIDE /SAFETY& R.Van KIRK) • CABLING (OVERSIGHT – DON McBRIDE /SAFETY& R.Van KIRK) • OVERALL QC (OVERSIGHT – HINMAN; SPECIAL ATTENTION TO HIGH STRNGTH BOLTS) • ENGINEERING REVIEW (OVERSIGHT – BURNS –TITLE 3 ISSUED) Raki Slide 10

  11. Cost & Schedule for Installing DC Transmission • 600K$ COST • Complete installation by 12/15/2004 SCHEDULE Raki Slide 11

  12. PROJECT GOAL SUMMARY • SAFETY TRAINING TO SUB-CONTRACTORS • PROPOSE WEEKLY PROGRESS MEETING • CONSTRUCTION MANAGER/SAFETY OFFICER IS THE SINGLE CONTACT PERSON • SUB-CONTRACTOR’S CONSTR. SUPERINTENDENT IS THE SINGLE CONTACT PERSON FOR ALL THE TOWER WORK. • DC TRANSMISSION PERMITS NCSX TO Share D-Site power supplies with NSTX • IMPORTANT INFRASTRUCTURE ENHANCEMENT IN PPPL • AIM IS TO PERFORM WORK SAFELY, SAFELY, SAFELY Raki Slide 12

  13. Raki Slide 13

  14. Raki Slide 14

  15. Raki Slide 15

  16. D:\04.jpg Raki Slide 16

  17. Raki Slide 17

More Related