An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FAALC Distribution SystemOperational Improvements • FAA Logistics Center Joe McClure, Darryl Thompson • University of Oklahoma Principal Investigators: Tom Landers Shivakumar Raman Research Assistants: Stephanie Cox Aylin Civan, Kelli Robinson • Global Concepts Randy Kirk

  2. FAALC Distribution Center forField Service Parts Profile: • National Distribution Center supporting field locations and local circuit card repair shops • High mix of low volume service parts • Extremely high field system up-time requirements

  3. Reasons for Improvement • Roof Refurbishment & Stock Room Moves An opportunity to review the layout Make improvements where needed • Mini-Load ASRS Hard to Support Parts hard/impossible to find More frequent hardware failures Extremely costly to operate

  4. Analysis and Design • High Level Material Flow Planning • Performance Assessment of the Mini-Load ASRS • Review data and profile activity(inbound, stocking, outbound) • Detailed Design of Stocking and Layout

  5. Previous LSF Layout A & B MINI-load AS/RS Bulk Storage Secure Storage & Other Storage Serviceable Items Repairable Items Bulk & Over-sized Storage Packing Packing Packing Packing Shipping Repack & Crating Receiving Inspection C D E F G

  6. Mini-Load ASRS Assessment • Utilization: 75% • Up-time: 75% • Storage/retrieval cycle time: 1-2 min • Space Utilization: 30% of 12” bins empty < 50% of 24” bin cubic space empty • Costs: Pending Upgrade:$1M O&M:$500K/year

  7. Mini-Load ASRS Assessment • Low Rise System – poor floor-space utilization • Reliability Problems • Outdated Technology • Lots of Unused Bin Space • Costly De-commission the MINI!!!

  8. Overall Material Flow Assessment • 10% of stock(4,100 items) cause 90% of activity • 19,000 items have not moved in 2 years • Travel distances long • Large conveyor little used, blocking flow Need Streamlined Flow!!! Popularity-Based Buffering!!!

  9. Operational Improvements • Considering “80-20 rule”, best practices, & growth: • Centralize operations in south end of LSF (Area G): • Shipping/Receiving docks, Crating, Inspection, & Repack • Centralize Packing in Area G, also • Remove the MINI & the conveyor system • Put high activity items closest to Area G (Area F); put slowmovers further back (Areas E - C)

  10. Additional Improvements • In key areas use carton-flow rack & static shelving to store more in less space • Use wheeled lift-truck or cart traffic in place of conveyor system (more flexible) • Continue with study of Warehouse Management System (WMS) software

  11. Planned Straight-line Flow 90% of Activity A & B TSF Crate Very Low Activity Items Low Activity Items High Activity Items Pack Receive & Ship Growth Secure Storage Inspect & Repack C D E F G

  12. Impact of Improvements • Investment -- $1M • Savings • One Time -- $2M(cost avoidance) • Mini Upgrade:$1M • Roof Refurbishment in D:$1M • Annual -- $500K Fast Payback!!