100 likes | 216 Views
An overview of the status and schedule for the project. Modulator and klystrons startup in July, 2002 High power checkout in January, 2003 DLDS operation in July 2004. The 8-Pack Project at NLCTA. Phase 1 SLED layout. Demonstrate full NLC RF power & stored energy, 1 st with SLED,
E N D
An overview of the status and schedule for the project. Modulator and klystrons startup in July, 2002 High power checkout in January, 2003 DLDS operation in July 2004 The 8-Pack Project at NLCTA Phase 1 SLED layout
Demonstrate full NLC RF power & stored energy, 1st with SLED, Test DLDS components at full power prior to DLDS assembly Then with DLDS Deliver full NLC RF power to NLCTA accelerating structures Phase-1: 4-Pack Assemble system with: 2 XP3 klystrons to power the SLED, additional XP3 klystron(s) as available A solid state modulator (from the ‘4-dog’) SLED system A simplified LLRF control system allowing SLED operation Produce NLC spec. power: 600 MW 400 ns Benchmark as a power source for the NLC Test DLDS components at full power before installing Phase-2: 8-pack Assemble 8 (total) XP3 klystrons with a (new) solid state modulator and an NLC spec. LLRF control system Attach DLDS system with two half arms reaching to two girders of high gradient accelerating structures in NLCTA (from FNAL). The 8-Pack Project
Goals – Phase 1 Use multimoded SLED II pulse compression on 2 tubes to attain >600 MW, 400 ns (@ cross potent) – meeting the NLC spec. Set up a station for high power tests of DLDS components & begin testing components Gain experience with 75 MW klystron operation Not to interfere with the High Gradient Structure Tests
Goals – Phase 2 Demonstrate DLDS pulse compression to attain NLC power specs. 500 MW, 396 ns (@ girder) Power NLCTA girders • Test DLDS system and high gradient structures to full energy (200J – 400J) • Investigate operational, stability, maintenance issues associated with DLDS
Modulator Solid State Modulator in the 4-dog Test Stand Stand and tank being designed and built by LLNL Move to NLCTA 5/28
Klystrons Unit #2 under test by the SLAC klystron group. Schedule: Install #2: 7/19-7/25 Install #3: 8/21-8/27 XP3 PPM #2 75MW
Phase 1 schedule overview • Held system design review 2/22 • 75% of individual systems completed design reviews • Civil and infrastructure complete 6/5 • Commission modulator at NLCTA 7/18 • Klystron #2 power to loads 8/2 • SLEDII system installation begins 10/1 • Pump down SLEDII 1/22/03
Phase 2 schedule overview Begin DLDS design during FY’02 High-power test DLDS components April-October 2003 Remaining klystron parts fabricated in FY’03 Install remainder of klystrons January-February 2004 DLDS system with controls installed June 2004 DLDS testing begins July 2004
8-pack project spending needsin direct, FY’02 dollars In FY’02, $2.4M spent by NLC for R&D in klystrons, modulators, and SLEDII/DLDS component development - hardware used in 8-Pack Phase 1. In Phase 2 the 8-Pack project must pick this up and purchase remaining hardware, including 5 klystrons and DLDS system
Issues and Concerns for the 8-Pack Project (Remember, this is an R&D project) • No contingency in plan, either cost or schedule • In Phase 2, Project must purchase all remaining hardware • Klystrons fabrication pushed out of ’02 by budget • DLDS fabrication and testing • Must compete for SLAC services with PEP-II, SPEAR 3, LCLS, & NLC structures development • If we had more dollars, we could • Outsource more fabrication work to secure schedule • Accelerate parts for remaining klystron in FY’02 • Enhance the diagnostics in the control system in FY’02 • Currently in the process of resource loading the schedule • Costs and tasks may shift when complete