1 / 9

Wastewater Treatment Project Update May 15, 2013

Wastewater Treatment Project Update May 15, 2013. Status. Preliminary design complete Detailed design being finalised Public works relocated Site prep to begin late May Construction proper in June Completion for October 2014. PROJECT COSTS & FINANCING - Baseline Position -.

kane-cobb
Download Presentation

Wastewater Treatment Project Update May 15, 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Wastewater Treatment ProjectUpdateMay 15, 2013

  2. Status • Preliminary design complete • Detailed design being finalised • Public works relocated • Site prep to begin late May • Construction proper in June • Completion for October 2014

  3. PROJECT COSTS & FINANCING - Baseline Position - Funding Available Sechelt Funding $ 8.9 Sewer Treatment Reserves $4.9 Sewer Treatment DCCs 1.5 Unrestricted Operating Surplus 2.5 Other governments $11.2 Gas Tax Funding $8.0 Building Canada Funding 3.2 Other sources $2.5 Loan $2.5 Repay over 5 years using sewer reserve surpluses FUNDING AVAILABLE $25.1 Project Costs 2011-2012 Costs $1.0m Contract price $21.3 PST $0.8 2013 -14 costs $1.3 Contingency $0.5 TOTAL COSTS $ 25.0

  4. Why is it “so expensive” • Because we are doing high level (“tertiary”) treatment • This added about $5m to the cost • . . . However . . .

  5. Why are we doing high level treatment? • Enables widest range of options for reuse of water. • 90% reduction in contaminant load to Trail Bay • Avoids $3m outfall expansion • In keeping with Federal and Provincial policies which encourage the use of reclaimed water • Goal was set in Sechelt’s 2011 Sustainability Action Plan

  6. Sustainability Action Plan Liquid Waste : “to treat effluent to the highest levels” • Other goals of the Plan; • Reduce noise and smell to the greatest extent possible • Pursue opportunities to recover resources from treated effluent • Maximise energy efficiency, reduce water consumption • Base infrastructure decisions on full life cycle costs • Ensure that municipal infrastructure is integrated and energy efficient and has the lowest environmental impact possible.

  7. Proposal Evaluation * For comparison, all capital costs assume biosolids composting by Salish Soils Need to add $3.2m of DoS costs to all bid prices to get the “Project Cost” **Base bid, Lot L projects include new, relocated, odour controlled pump station at Ebbtide

  8. Location of Ganges WWTP, Salt Spring Island

  9. Questions?

More Related