Landfill Closure and Post-Closure Care Cost Estimates

Landfill Closure and Post-Closure Care Cost Estimates. ADEQ Solid Waste Management Division. Closure and Post-Closure Care Cost Estimation Topics . 1) Cost estimate regulatory requirements 2) Defining closure and post-closure care 3) Planning and phasing closure activities

karik
Download Presentation

Landfill Closure and Post-Closure Care Cost Estimates

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Landfill Closure and Post-Closure Care Cost Estimates ADEQ Solid WasteManagement Division

  2. Closure and Post-Closure Care Cost Estimation Topics 1) Cost estimate regulatory requirements 2) Defining closure and post-closure care 3) Planning and phasing closure activities 4) Cost estimate reference documents and development 5) Review of 1996 SWMD guidance 6) Draft revised cost estimate spreadsheets Emphasis:Planning for closure and post-closure care and thorough cost estimates.

  3. Statutory/Regulatory Requirements - Closure and Post-Closure Care Cost Estimations • A.C.A. 8-6-1603 (Chapter 6 - Disposal of Solid Wastes …, Sub-chapter 16 - Financial Assurance. • Reg. 22, Chapter 14 - Financial Assurance requires closure and post-closure care cost estimates. Topic #1

  4. Regulatory Requirements - Closure and Post-Closure Care Cost Estimations • Must be written estimate in current dollars, and third party (labor, materials, supplies, etc..). • Must include 'largest area requiring closure at any time during life of facility when closure of operation would be most expensive'. • Must be detailed in Closure and Post-Closure Care Plans. Topic #1

  5. Regulatory Requirements - Closure and Post-Closure Care Cost Estimations (con't) • During planning and permitting, Reg. 22.1301 requires closure and post-closure care plans. • The plans include cost estimates for landfill closure and post-closure care. Decisions must be made for phased closures. • Planning and scoping is required in order to determine specific closure and post-closure care items and quantities. Topic #1

  6. What is Closure ? Topic #2 • Landfill closure includes installation of a final cover system, leachate and/or gas collection systems, and groundwater monitoring systems. • Closure includes landfill units. • Landfill unit closure is required when landfill is at capacity or when receipt of waste has stopped. • Reg. 22.1301(f) and (g) describes the timeliness of closure activities (initiating and completing closure). • Closure must be planned during the landfill design.

  7. What is Post-Closure Care? Topic #2 • Post-Closure Care includes operation and maintenance of the final cover system, leachate and/or gas collection system, groundwater monitoring systems, surface water management, site access control, deed restrictions, records maintenance, and reporting. • Post-Closure Care must be plannedduring the landfill design.

  8. Post-Closure Care Maintenance at Closed Landfills Topic #2

  9. Post-Closure Care Maintenance at Closed Landfills Topic #2

  10. Post-Closure Care Maintenance at Closed Landfills Topic #2

  11. Post-Closure Care Maintenance at Closed Landfills Topic #2

  12. What is Post-Closure Care? (con't) Topic #2 • Reg. 22.1302(c) requires post-closure care be conducted for 30 years at Class 1 landfills and 2 years at Class 3 or 4 landfills. • Post-Closure care period may be extended or reduceddepending on site conditions and impacts to the environment.

  13. Phasing Closure and Post-Closure Care Topic #3 • Reg. 221302(g) - Facilities with multiple units may begin post-closure care period if they do not share common liner or cover systems. • Although maybe a limited incentive, closure of completed units can be advantageous because of potential cost savings.

  14. Phasing Closure and Post-Closure Care (con't) Topic #3 • Closing landfill units often reduces operational expenses related to leachate and gas management. • Closing landfill units in phases reduces high capital cost outlays later in the life of the landfill. • Closing landfill units reduced the amount of financial assurance required by Reg. 22, Chapter 14.

  15. Phased Closure Example Topic #3

  16. Phased Closure Example Topic #3 • .

  17. References - Closure and Post-Closure Care Estimates Topic #4 • Federal guidelines exist (1987,1994, 2001). Federal guides include numerous line item details. • SWANA addresses cost estimates and financial assurance in Tech. Policy T-09.1 (1994) • ADEQ has HW guide to closure and cost estimates (2010). ADEQ's Fall 2011 "Solid Waste Quarterly" included article on cost estimations.

  18. References - Closure and Post Closure Care Estimates (con't) Topic #4 • ADEQ - SWMD issued "Guidance for Preparing Closure and Post-Closure Plans and Cost Estimates…" in 1996. • Cost estimation portion (Tables 3 and 4) of the ADEQ 1996 Guide is being reviewed. • More complete list of "line items" is being developed.

  19. ADEQ 1996 Guide - Closure Estimate Table Topic #5

  20. ADEQ 1996 Guide - Closure Estimate Table (con't) Topic #5

  21. ADEQ 1996 Guide Deficiencies Topic #5 • Table 3 (Closure) lack some major cost item details which need to be listed: • closure contract development • procurement and management of closure contract • leachate collection system upgrades or modifications • gas collection system installation • groundwater monitoring well installations

  22. ADEQ 1996 Guide Deficiencies (con't) Topic #5 • Table 4 (Post-Closure Care) cost estimate lacks details: • Leachate collection system upgrades • Leachate analytical costs • Groundwater well replacements • Landfill gas monitoring system upgrades • Gas extraction system operation and maintenance • Procurement and contract management • Post-closure oversight management and reporting

  23. ADEQ 1996 Guide Deficiencies (con't) Topic #5 • Both Table 3 and 4 lack: • Complete analysis of cost associated with closure and post-closure (e.g., final cover soil material cost may be included but loading, transportation and placement may not) • Source documentation of cost estimate (i.e., cost estimation references - cost manuals, actual local estimate)

  24. Draft Revised Closure and Post-Closure Care Cost Item List Closure (THIRD PARTY COSTS!) • Professional services • Final cover • Erosion control • Gas system • Groundwater monitoring system • Leachate collection system Topic #6

  25. Draft Revised Closure and Post-Closure Care Cost Item List (con't) Closure (con't) (THIRD PARTY COSTS!) • Operations and inventory removal • Demolition/removal site improvements • Replace/rebuild site access controls • Borrow area reclamation • Miscellaneous and contingencies Topic #6

  26. Draft Revised Closure and Post-Closure Care Cost Item List (con't) Post-Closure Care (THIRD PARTY COSTS!) • Professional services • Final cover routine maintenance • Final cover repairs • Access road repairs • Leachate collection system operation and maintenance Topic #6

  27. Draft Revised Closure and Post-Closure Care Cost Item List (con't) Post-Closure Care (con't) (THIRD PARTY COSTS!) • Groundwater monitoring system operation and maintenance • Gas monitoring system operation and maintenance • Corrective actions evaluation and implementation • Miscellaneous and contingencies Topic #6

  28. Draft Revised Closure Cost Spreadsheet Topic #6

  29. Draft Revised Closure Cost Spreadsheet (con't) Topic #6

  30. Summary - Closure and Post-Closure Care Cost Estimations • Closure and post-closure care are integral parts of landfill design and operations. • Phased closure can be planned and designed. Decisions must be made early in design. • Numerous guidance exist to outline a thorough cost estimation.

  31. Summary - Closure and Post-Closure Care Cost Estimations • Closure cost estimates must reflect largest area and most expensive situation ever to be addressed. • Post-closure care costs estimates must include repair and replacement of operating systems and must allow for correct action evaluation and implementation.

  32. Comments/Questions? Please hold questions until the afternoon panel discussions? If you have comments, please forward to: • ADEQ Solid Waste Division 501-682-0602