Rural Water Programme 2006 Evaluation of Progress John Fitzgerald Engineering Inspector. Procurement Guidance Documents. Part A: Rural Water Modulw (DBO) Part B: Small Wastewater Projects Part C: Small Water Supply Projects. Part C: Small Water Supply Projects.

karli
Download Presentation

Rural Water Programme 2006 Evaluation of Progress John Fitzgerald Engineering Inspector

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Rural Water Programme 2006 Evaluation of Progress John Fitzgerald Engineering Inspector

  2. Procurement Guidance Documents Part A: Rural Water Modulw (DBO) Part B: Small Wastewater Projects Part C: Small Water Supply Projects

  3. Part C: Small Water Supply Projects Chapter 12: Conventional Procurement for GWSS

  4. Prior to Group employing Consulting Engineer Local Authority will (a) Prepare Brief (b) Determine indicative scale of fee acceptable for grant purposes – if scheme advances to construction.

  5. Scale of fees: (a) Fee per member for preparation of design drawings and calculations still valid. (b) Scale of fees based on Circ. 11/87 Preliminary Report 0 – 20% Design and Tender Drawings. Up to 30% Conditions of Contract / Specifications. 0 – 20% Construction Stage. 0 – 30% (c) PSDS accures separate fee. (ACEI scale of fee dated 9/2/96)

  6. OJEU OJEU National Newspapers National Newspapers Three Prices Three Prices One Price One Price L. Doyle Services The Procurement “Goalposts” Waste Water Directive 04/18/EC Water Directive 04/17/EC € 422,000 € 211,000 € 127,000 € 12,700

  7. L. Doyle The Procurement “Goalposts” Works Waste Water Directive 04/18/EC OJEU € 5,278,000 National Newspapers Water Directive 04/17/EC € 127,000 Three Prices € 12,700 One Price

  8. Water Quality Water Conservation

  9. New & Upgrade (85%) Takeover (100%)

  10. DBO Civil (85%) M&E (100%)

  11. Metering grants for DBO only. Universal Metering Domestic (85% grant subject to max €300) Non-domestic (85%) grant subject to max €250) Additional CLAR funding