1 / 11

The Hydrogen Delivery System – An Introduction

The Hydrogen Delivery System – An Introduction. M Hills. In Block Diagram. Each Hydrogen Delivery System in MICE is designed to fill an Absorber with 22L of liquid hydrogen (~18000L (or 18m 3 ) of gas) in a controllable and safe manner.

Download Presentation

The Hydrogen Delivery System – An Introduction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Hydrogen Delivery System – An Introduction M Hills

  2. In Block Diagram • Each Hydrogen Delivery System in MICE is designed to fill an Absorber with 22L of liquid hydrogen (~18000L (or 18m3) of gas) in a controllable and safe manner. • Prior to use with the final MICE absorbers, the system will be tested with a Test Cryostat which represents the final absorber (this is the “R&D system”)

  3. System Components

  4. In CAD Vacuum Pump Enclosure Relief lines Gas Panel Enclosure Fans Test Cryostat Ventilation ducts 4

  5. In photos • Gas Panel Enclosure is situated on the south mezzanine • Hydride Bed heater/chillers located along the mezzanine • Ventilation and vacuum pipework is routed above the magnetic shield wall • Test Cryostat sits at floor level, approximately in the eventual location of the third AFC module

  6. H2 Charging Station Hydrogen “Charging Station” (right) installed below south mezzanine Will provide a ventilated area for hydrogen bottles during the periods when the hydride beds are being filled Hydrogen bottles will only be brought into the hall during charging. This means for 1-2 days max. and (hopefully) once per bed.

  7. Hydrogen Local Control Room (HLCR) • Located adjacent to the main hall, opposite the MICE Local Control Room • Home to the Hydrogen System control racks: • one for control functions specific to the first system • one for general control functions (H2 detection and ventilation system) • Houses the UPS and battery rack to keep safety critical systems running during a power outage

  8. On the roof • Vacuum Pump Enclosure (left) houses the vacuum pumps and is ventilated by the two smaller fans in the fan stack (right) • Ventilation stack contains the fans and flow monitoring • The relief lines vent above the stack platform

  9. External Helium and Nitrogen Store 9 • Storage area for the nitrogen and helium bottle packs that serve the system • Final stage of construction still in progress • Gas panels for connection of the bottle packs have been manufactured and are ready to be fitted • Gas panels include regulators that allow for automatic switching between packs • Current estimate is that continuous purging of the relief lines with nitrogen will use ~1pack/week (with 3 systems) • With two packs of nitrogen in position and automatic changeover, there will be a week to replace a used pack during continuous running

  10. In reality... • Hall Tour: • Will visit all the areas described above • Hall is a CDM (Construction Design and Management) area and also a (very low) radiation area • PPE and radiation monitoring will be provided • Please stay with the guides and watch your step

  11. Latest news.......... • Matt Hills is taking a two-year career break – very best wishes from MICE • Stephen Watson of STFC assumes responsibility for LH2 system w.e.f October 17th • Successful pre-operation safety review held at RAL, expect formal report next few days • Minor pipework on bottle rack and vac system to do, but all major installations are complete • Very likely we can repeat LHe test and do LH2 test early in 2012 • Director-level safety responsibility (David Wark) has been established at RAL

More Related