An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project UpdateMARC Maintenance &Layover Facility September 18, 2012

  2. Project History • MARC Maintenance & Layover Facility • Support existing and expanded Penn Line operations @ MTA controlled facility • Provide storage for rolling stock • Transfer maintenance & layover from Amtrak facilities • Site Selection Report – February 2012 • Evaluated five sites • Narrowed options down to two • APG • Prologis • Site Selected - 2012 • Prologis site (Edgewood – Harford Co.)

  3. Project Overview • Why Prologis? • Property acquisition & low risk of hazardous materials • Traditional risks & challenges developing this site w/more predictable resolutions & schedules • Environmental Condition Report (ECP) for APG – Superfund site • Prologis is hydrogeologically upstream from APG site. • Have entered Preliminary Engineering (PE) Phase • Determine project Phasing • Develop Preliminary plans • PE concurrent with Environmental document

  4. Prologis Site • Location: • North side of Amtrak (across from APG Site) • Part of a mixed commercial/ industrial facility • Zoned: • General Industrial District 64 acres • Urban Residential – 4 acres • Road Access: The Gap Drive

  5. Preliminary Engineering Phase Creation of a site master plan Break project down into Phases Develop storage layout for first Phase No new interlocking on NEC Located between Magnolia & Wood interlocking Coordinate with Amtrak Determine new location for existing stormwater management facility May be possible to reforest some in this location 5

  6. Project Schedule • September 2012 - Begin Preliminary Engineering & Environmental Document • Fall 2013 - Complete Preliminary Engineering & Environmental Document • Winter 2013/2014 – Begin Final Design

  7. Contact Ms. Deirdre Smith, P.E. Project Manager (Jacobs) Maryland Transit Administration Project Development 410.767.3869 dsmith31@mta.maryland.gov