1 / 15

LCLS-II Project Overview

LCLS-II Project Overview. David Schultz LCLS-II Deputy Project Director March 19, 2012. Outline. Project priorities and status Key features Project o verview & layout Project schedule and path forward. LCLS-II Project Priorities. Build a highly productive scientific user facility

kassia
Download Presentation

LCLS-II Project Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS-II Project Overview David Schultz LCLS-II Deputy Project Director March 19, 2012

  2. Outline • Project priorities and status • Key features • Project overview & layout • Project schedule and path forward LCLS-II New Instruments Workshops, March 19-22, 2012

  3. LCLS-II Project Priorities • Build a highly productive scientific user facility • Maximize technical capabilities for the longer-range future • Simultaneous SXR and HXR operation • Experiment hall capacity • Undulator hall length • Control the Project Cost/Schedule • DOE Guidance is $405M Total Project Cost • Formal Project completion (CD-4) in 2019 LCLS-II New Instruments Workshops, March 19-22, 2012

  4. LCLS-II Project Status • Conceptual Design (CD-1) approval 10/14/11 • Long-lead procurements approval 3/14/12 • Injector system and support facility • Fully funded for FY12 • DOE Preliminary Design (CD-2) Review as early as August, 2012 • Establish Project baseline schedule and budget LCLS-II New Instruments Workshops, March 19-22, 2012

  5. Key Features of LCLS-II • Second 120 Hz injector and 1km LINAC section • LCLS-1 and LCLS-II operate independently • Two New Undulator sources with variable gap • In a new undulator tunnel • Electrons to two undulators in parallel, 60 Hz each • Soft (250- 2,000 eV) • Hard (2,000 - 13,000eV) • New underground experiment hall, two floors LCLS-II New Instruments Workshops, March 19-22, 2012

  6. Linac Coherent Light Source II CD-0 10 April 2010, CD-1 14 October 2011 Injector @ 1-km point Sectors 10-20 of Linac (1 km) Bypass LCLS Linac in PEP Xport Line New Beam Transport Hall SXR, HXR Undulators X-ray Transport Optics/Diagnostics New Underground Experiment Hall DOE CD-3a Review of the LCLS-II Project, Dec 6-7, 2011

  7. Electron Systems Schematic Layout 0 • Electron Systems largely copied from LCLS-1 • Gun, BC’s, diagnostics, e- dumps LCLS-II New Instruments Workshops, March 19-22, 2012

  8. LCLS-II New Construction Layout LCLS-1 Beam Transport Hall 2 Undulator Hall 2 Experimental Hall 2 LCLS-II New Instruments Workshops, March 19-22, 2012

  9. LCLS-II Undulator Hall • Undulator tunnel is 286 meters in length • Space for baseline 114 m HXR and 66 m SXR undulators • Room allocated for seeding and tapering extensions e- Beam Dump Space for HXR Seeding and Tapering Front End Baseline HXR Baseline SXR Space for SXR Seeding and Tapering LCLS-II New Instruments Workshops, March 19-22, 2012

  10. Undulator Magnets • LCLS-II Undulators are based on undulators designed at LBNL for the ALS. Servo Motor Linear Slide Strongbacks Linear Encoder Undulator Hall Cross Section • Undulator tunnel is similar in cross section to the LCLS tunnel. Magnetic Structure Compensating Springs LCLS-II New Instruments Workshops, March 19-22, 2012

  11. Experimental Hall 2 Layout • Space for 4 experimental stations in an 80m long cavern. • Full size second floor for HVAC, racks, control rooms Front End Systems Area for Soft X-rays Area for Hard X-rays 14m 80m LCLS-II New Instruments Workshops, March 19-22, 2012

  12. LCLS-II Project Schedule EH2 complete  First Light  Install Instruments LCLS-II New Instruments Workshops, March 19-22, 2012

  13. 2012 plans • Start Injector facilities construction in July • Start Injector technical system fabrication • Complete Construction designs by the end of the year. • Develop the Project baseline schedule and budget for presentation to DOE in August. LCLS-II New Instruments Workshops, March 19-22, 2012

  14. Summary • LCLS-II will add capacity and capability to the LCLS scientific program, and will provide space for expansion. • To minimize cost and risk, electron systems rely heavily on LCLS-1 designs. • LCLS-II will dovetail with the LUSI-II project. First light in 2018. LCLS-II New Instruments Workshops, March 19-22, 2012

  15. End of Presentation

More Related