1 / 5

FACILITIES MANAGEMENT ENVIRONMENTAL & ENERGY IMPROVEMENTS

FACILITIES MANAGEMENT ENVIRONMENTAL & ENERGY IMPROVEMENTS. Carbon Saving Initiatives Update 2009 / 2010. FACILITIES MANAGEMENT ENVIRONMENTAL & ENERGY IMPROVEMENTS. ConCom (Continuous Commissioning) Flowers building, ‘Night Set-Back’ – delivered 239 tCO 2 savings / year.

Download Presentation

FACILITIES MANAGEMENT ENVIRONMENTAL & ENERGY IMPROVEMENTS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FACILITIES MANAGEMENT ENVIRONMENTAL & ENERGY IMPROVEMENTS Carbon Saving Initiatives Update 2009 / 2010

  2. FACILITIES MANAGEMENT ENVIRONMENTAL & ENERGY IMPROVEMENTS ConCom (Continuous Commissioning) • Flowers building, ‘Night Set-Back’ – delivered 239 tCO2 savings / year. • Faculty building, ‘Weekend Set-Back’ – delivered60 tCO2 savings / year • SAF building, AHU ‘Set-Backs’ - initial air readings underway. • SAF, transformer voltage reduction – savings being assessed • Commonwealth building, AHU ‘Set-Backs’ – desk-top report of operational times & fan ratings completed, ConCom to review with FM team & academic community, identify and initiate opportunities. • Obtained Carbon Trust matched funding to support ConCom -£38,765

  3. FACILITIES MANAGEMENT ENVIRONMENTAL & ENERGY IMPROVEMENTS Lighting • Faculty building, LED lights installed on ramp and in secure bike store – delivered 26.3 tCO2 savings / year. • Sherfield building, LED lights installed in level 2 main concourse – delivered 6.3 tCO2 savings / year. • Sherfield building, LED lights extension to ground floor concourse – programmed for 26th / 27th June expected to deliver 11.5 tCO2 savings / year. • All lighting works, are now being challenged to demonstrate carbon savings, projects in development include: Skempton stairwells, RSM mezzanine corridors, Elec Eng workshops. • ConCom survey of existing lighting on SK Campus, to commence 1st July, will establish strategy for installing more efficient lighting and introducing controls.

  4. FACILITIES MANAGEMENT ENVIRONMENTAL & ENERGY IMPROVEMENTS Other inititatives • Silwood transformers, ‘Power Perfector ’ installation, controlling operational voltage – delivered 32 tCO2 savings / year. • RSM & Bessemer, office ‘Hot Water Boilers’, programmed to occupied office hours only – delivered10 tCO2 savings / year • Food recycling composter – delivered166 tCO2 savings / year • Lagging & insulation works – delivered55 tCO2 savings / year • Silwood buildings ‘Cavity Wall Insulation’ – works due to start 2nd July, expected to deliver, 75 tCO2 savings / year. • Steam trap remedial works, survey identified improvements – expected to deliver, 491 tCO2 savings / year.

  5. FACILITIES MANAGEMENT ENVIRONMENTAL & ENERGY IMPROVEMENTS Opportuities under review • ETHOS ‘waste to heat’ , convert, 550 tonnes of waste to heat / steam on site – expected to realise 450 tCO2 savings / year. • Plant Replacement : installation of new chillers, efficient lifts & air conditioning units – potential savings under assessment. • Photovoltaic's (PV): Discussions with Inside2Outside regarding OPV Membrane, potential applications and Solar Century identifying potential roof locations for systems on site for PV panels – potential savings and viability to be assessed. • CHP operation - initial discussions regarding more efficient operation & exploring with Kiwi Power potential income from the ‘Grid’. • Bike & Electric car provision on SK campus – initial operational desk-top report completed, ConCom Team commencing review with FM team / academic community, identify & initiate opportunities.

More Related