Texas Nodal Congestion Revenue Rights (CRR) EDS 3 Release 7 - Overview EDS 3 Phase 2 MP Planning Workshop July 11, 2007. CRR EDS3-R7 Overview. CRR will begin conducting Market Trials in early February of 2008 as part of EDS 3 Release 7 (EDS3-R7) CRR EDS3-R7 will consist of 4 phases

keala
Download Presentation

CRR EDS3-R7 Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Texas NodalCongestion Revenue Rights (CRR)EDS 3 Release 7 - OverviewEDS 3 Phase 2 MP Planning WorkshopJuly 11, 2007 http://nodal.ercot.com 1

  2. CRR EDS3-R7 Overview • CRR will begin conducting Market Trials in early February of 2008 as part of EDS 3 Release 7 (EDS3-R7) • CRR EDS3-R7 will consist of 4 phases • CRR EDS3-R7 will take approximately 4-5 months, ending in May 2008 • Market Participants wishing to participate in CRR EDS3-R7 will have to complete some activities in advance (e.g. Registration) • The CRR EDS3-R7 plans are currently based on Market Participants interacting with the CRR User Interface, NOT an API/Machine to Machine interface • This is per the ERCOT Board of Directors statement that CRR API is currently out of scope http://nodal.ercot.com 2

  3. Pre-Activity Registration and digital certification; NOIE PCRR contract submission • Market Participants will have to register with ERCOT CRR Account Holders and have an appropriate digital certificate (by mid January 2008) • NOIEs must send contracts and desired entitlements (by early December 2007) • NOIEs wishing to identify themselves as Competitive Load Zones shall indicate their intention to do so (by early December 2007) • Wind Generators within the boundaries of the McCamey Area must identify themselves for McFRI eligibility (by early December 2007) • ERCOT to verify receipt to ERCOT of contracts and entitlements information; input into system (prior to Phase 1) http://nodal.ercot.com 3

  4. Phase 1 – beginning early February 2008 UI connectivity, data upload; limited Market Participants (~2 weeks) • Limited number of Market Participants based on MPs prepared by early deadlines • CRR environment for Market Participant EDS Activities made available • Verify CRR Account Holders’ ability to connect to the CRR System using a digital certificate • Verify CRR Account Holders’ ability to utilize Online User Interface to retrieve market information, submit nominations, bids and offers http://nodal.ercot.com 4

  5. Phase 2 Mock Auction (ERCOT provided bids/offers), mock bilateral trades; expanded Market Participants (~3 weeks) • Expanded number of Market Participants; verify expanded CRR Account Holders’ ability submit nominations, bids and offers via UI • Conduct mock monthly allocation with Account Holders self-created nominations • Conduct mock monthly auction with ERCOT provided bids and offers and defined Credit • Verify CRR Account Holders’ ability to download market results via UI • Verify bilateral trade functionality orchestrated by ERCOT http://nodal.ercot.com 5

  6. Phase 3 Mock Monthly Auction (MP created bids/offers) (~3 weeks) • Conduct a mock CRR Monthly Auction with CRR AH created bids and offers • Verify bilateral trade functionality as created by AHs • Credit constraint will self defined within ERCOT identified boundaries http://nodal.ercot.com 6

  7. Phase 4 Mock Multi-Month Auction (MP created bids/offers) (~4 weeks) • Conduct a mock CRR Multi-Month Allocation with CRR AHs created nominations • Conduct a mock CRR Multi-Month Auction with CRR AHs created bids and offers http://nodal.ercot.com 7

  8. Outstanding Items The following items must be included in one of the above phases of the EDS 3 Release 7 or must result in a new phase: • Additional ‘practice’ Auctions – if Market Participants wish, additional rounds of practice bidding may be possible (current phases run though April, EDS3-R7 is scheduled to end June 2007) • Credit – based on design decisions and detailed development timeline, the implementation and testing timeline for Credit data input module TBD • Training – an 8 hour training course is currently planned for Fall 2007 delivery. However, there may be additional hands on UI training that is TBD Note: Settlements and Billing will produce invoices as part of EDS4, auction and allocation results will be available for each CRR phase http://nodal.ercot.com 8

  9. Dec Jan Feb Mar Apr May CRR EDS3-R7 – One-Pager Pre EDS3-R7 Activities Phase 1 Phase 2 Phase 3 Phase 4 • Objectives • Registration of MPs as CRR Account Holders • Assign MP CRR Digital Certificate rights • NOIE contract receipt and entitlement creation in the system • NOIE load zone identification • Objectives • Validate MP CRR Digital Certificate rights • Validate AH system connection – uploads and downloads • Objectives (Incremental) • Conduct mock CRR monthly auction – ERCOT directed bids • Conduct mock CRR monthly allocation – AH created nominations • Verify market result download • Verify bilateral trade functionality • Objectives(Incremental) • Conduct mock CRR monthly auction – AH determined bids • Conduct secondary trading – AH directed • Verify Credit constraint in optimization • Objectives(Incremental) • Conduct mock CRR annual auction – AH determined bids • Conduct mock CRR annual allocation – AH created nominations System Needs CRR • CRR System (Market Operator) NMMS • Network Model w/ NOIE load zones • Network Model output for CRR Registration • CRR AH Registration Data/Stubs • None Infrastructure • CRR FAT System Needs (incremental) CRR/MIS • CRR External UI Data / Stubs • Registration • Network Model Testing Tools • Defect tracking & communication process / tool Infrastructure • EDS 3 Hardware System Needs (incremental) CRR • No Change Data / Stubs • No Change Testing Tools • No Change Infrastructure • No Change System Needs (incremental) CRR • Bug fixes only Data / Stubs • CMM Testing Tools • No Change Infrastructure • No Change System Needs (incremental) CRR • Bug fixes only Data / Stubs • No Change Testing Tools • No Change Infrastructure • No Change • TBD • Interface timing from NMMS, Registration, CMM • Interface timing to S&B, MMS, CMM • EDW Data Extract functionality • Credit data input module SME Support levels: Estimated at 1man day per week SME Support levels: 8 * 5 support for CRR SMEs available to MPs per schedule SME Support levels: 8 * 5 support for CRR SMEs available to MPs per schedule SME Support levels: 8 * 5 support for CRR SMEs available to MPs per schedule SME Support levels: 8 * 5 support for CRR SMEs available to MPs per schedule http://nodal.ercot.com 9