1 / 24

Senior Design Friday, April 23, 2010

Senior Design Friday, April 23, 2010. Chris Crock. Aaron Lammers. Brent Long. Aaron Raak. Introduction. Carabuela, Ecuador has a flawed wastewater treatment system O verloaded s eptic t ank Failed leaching f ield Worked with HCJB to remedy the problem. Design Norms/Criteria.

kedem
Download Presentation

Senior Design Friday, April 23, 2010

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Senior Design Friday, April 23, 2010 Chris Crock Aaron Lammers Brent Long Aaron Raak

  2. Introduction • Carabuela, Ecuador has a flawed wastewater treatment system • Overloaded septic tank • Failed leaching field • Worked with HCJB to remedy the problem

  3. Design Norms/Criteria • Effective Treatment • Culturally Appropriate • Sustainability • Site Appropriate • Low Cost • User Friendliness • Life of Design

  4. Performance Requirements • Water Effluent • E. Coli count < 1000/100 mL • Biochemical Oxygen Demand (BOD) under 2.0 mg/L • Helminth eggs < 1 egg/100mL • (WHO standards set E. coli limit for leafy crops at 1,000/100mL; at this level of treatment other pathogens are assumed to be treated as well) • Sludge Effluent • 1000 E. Coli/gram solids • < 1 Helminth egg/ g solids • (With alfalfa, requirements need to only meet Class B sludge treatment. The US EPA determined that sludge which goes through one of six processes of significant reduction of pathogens may be applied to crops)

  5. Functional Requirements • Handle the waste of the entire connected population for 20 yrs (1800 residents) • No electricity • The system must fit in 0.5 hectares • No chemical additives • Shall not need experts outside of the village for construction

  6. General System Description General System Description • Bar Racks • Racks for large solids and objects • Two open channels with inclined bars • Dewatering plate for screenings • Grit Chamber • Settle out large particles (sand, grit, etc.) • Two open channels acting as grit chambers • Velocity control weir • Imhoff Tank • Settle out discrete organic materials and small particles • Store organics for later treatment • Anaerobic digestion of organic solids • Two tanks and settling chambers • Stabilization Lagoons • One facultative pond for Biochemical Oxygen Demand (BOD) reduction • Two maturation ponds for further BOD reduction and pathogen removal • Sludge Drying Beds • Treat sludge from Imhoff Tank and Grit Chamber • Four sludge drying beds for treatment cycling

  7. Q = 192 m3/day BOD = 32 kg/day TSS = 48 kg/day FC = 2x107 /100 mL General System Description Q = 192 m3/day BOD = 32 kg/day TSS = 48 kg/day FC = 2x107 /100 mL Q = 192 m3/day BOD = 32 kg/day TSS = 48 kg/day FC = 2x107 /100 mL Q = 192 m3/day BOD = 16 kg/day TSS = 32.6 kg/day FC 2x107 /100 mL Bar Racks Grit Chamber Imhoff Tank Solids = 16 m3/month Q = 192 m3/day BOD = 0.51 kg/day TSS = 3.2 kg/day FC = 915 /100 mL Sludge Drying Bed Irrigation Stabilization Ponds

  8. Environmental Design - Bar Rack • Important to remove larger solids • Bar Racks • Design depends mostly on clear space between bars • Velocity should be within 0.3—0.6 m/s • Openings between 20—50 mm • Rack for dewatering screenings • Redundant system

  9. Structural Design - Bar Rack • Bar Racks Structural Design • Analysis of moments in the chamber • Designed steel and concrete for worst case loads • ACI 318M-05 Metric Building Code and Commentary • Steel reinforcing requirements • Concrete requirements

  10. Environmental Design – Grit Chamber • Important to remove particulate • Grit Chamber • Design largely depends on the velocity the water (0.3 m/s) • Velocity controlled by Sutro weir • Grit removed is treated in sludge drying beds • Redundant system

  11. Structural Design – Grit Chamber • Structural Design • Ultimate moment design • ACI 318M-05 Metric Building Code and Commentary • Two open channels and sutro weirs for redundancy

  12. How an Imhoff tank works Sedimentation Outflow Inflow Anaerobic Digestion V V0 Stokes Settling Velocity Stokes Rearranged for Particle Removal Sedimentation Anaerobic Digestion

  13. Environmental Design – Imhoff Tank • Environmental Design • Two tanks in one structure for redundancy • Sedimentation • Based off design guides and rules of thumb • Overflow rate of 600 gal/ft2 day • Retention Time of 2 hours • Digestion • Based on case study of Imhoff tank in Honduras • Sludge storage for 0.053 m3 per resident (95.4 m3) • Up to 6 months of sludge storage

  14. Structural Design – Imhoff Tank • Structural Design • Analysis of forces and moments in tank • Finite Element Analysis (FEA) • Structural analysis • Designed steel and concrete to hold for highest loads • ACI 318M-05 Metric Building Code and Commentary • Similar to case study tank in Honduras • Final Design: 9.25m long x 8.6m wide x 7.5 m tall

  15. Concrete Structures Walkthrough

  16. Environmental Design – Lagoons • Loading Rates • BOD: 100mg/L • Helminth Eggs: 1000 Eggs/L • E-Coli: 2x107Coliforms/100mL • Reduced Rates • BOD: 2.7mg/L • Helminth Eggs: 0.10 Eggs/L • E-Coli: 915 Coliforms/100mL

  17. Structural Design – Lagoons • Pond System • 1 Facultative Ponds • 2 Maturation Ponds • Dimensions • 48meters x 24 meters • Depths of 1.5 meters and 0.5 meters • Redundancy

  18. Environmental Design – Sludge Treatment • Must hold sludge for several weeks to dewater • Must hold sludge for longer to make it safe for fertilizer • Designed to hold 1 year’s worth of sludge for Imhoff tank • Area: 960 m2

  19. Structural Design – Sludge Treatment • Beds have layers of sand and gravel • Shear gates to control sludge flow • Low walls of earth or concrete • Under drain system of PVC pipe

  20. Storm Water • Townspeople connect roof drains to sewers • A large rainfall event could flush the system • Model showed 15x increase in flow during 10-year event • Will require an overflow weir to prevent flushing

  21. Storm Water • Storm inflow: 3100 m3/day • Design inflow: 192 m3/day

  22. Project Funding • Estimated cost of construction = $31,000 • Probably too much for residents • We wrote a grant to cover the cost of construction • Maintenance costs to be covered by Carabuela • Estimated $14,000/year

  23. Conclusion • Designed a complete system to treat Carabuela’s wastewater for irrigation reuse • Removal of BOD, TSS, and Pathogens • BOD (98.7%) • TSS (93.4%) • Pathogen Removal • E. Coli (99.995%) • Helminth Eggs (99.99%) • Created construction drawing for the system • Wrote an operations and maintenance manual

  24. Questions??

More Related