An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Conditional Firm Service Business Practice February 4, 2011

  2. Agenda • Introduction – Al Woodruff 9:00 AM • Conditional Firm Service (CFS) – Stephen Tran 9:15 AM • Lunch 12:00 PM • NERC TTC/ATC Methodologies – Stephen Tran 1:00 PM • Refreshment 2:15 PM • TTC Calculator Project – Ebrahim Vaahedi 2:30 PM • Wrap Up 3:30 PM

  3. Introduction Al Woodruff Manager, Market Policy and Operations • Updates on consultation regarding Re-integration

  4. Conditional Firm Service Presenting By Stephen Tran

  5. Conditional Firm Service • Background (FERC CFS) • BC Hydro Conditional Firm Service • Monthly Posted Firm ATC & CFS ATC Methodology • CFS Service Offer Process • Common Practices • Option 1 • Option 2 • Q & A • Next Steps

  6. Conditional Firm Service • FERC Conditional Firm Service (CFS) • A long-term service • Intended for bridge service or substitute service • Conditional period and unconditional period • During conditional Period: Service priority = 6NN • Higher priority than non-firm • Same priority as Network Secondary Service • During unconditional Period: Service priority = 7F • Same service priority as other firm services

  7. Conditional Firm Service • FERC Conditional Firm Service (CFS) • CFS can be based on either: • System conditions: may be curtailed for • Pre-defined system contingencies • System load levels • Number of hours: may be curtailed for • Pre-specified number of hours per year • Biennial Assessment

  8. Conditional Firm Service • BC Hydro Conditional Firm Service • Has same terms and conditions • Based on posted monthly Firm ATC • Consists of firm service and conditional service • Firm service has priority 7F • Conditional service has priority 6NN • Higher priority than non-firm • Same priority as Type 1 Network Economy • Service Agreement specifies: • 24 monthly ATC profile (firm service amount and conditional service amount)

  9. Conditional Firm Service • Short-Term Firm ATC (i.e. hourly, daily, weekly or monthly) will be awarded to CFS Transmission Customers prior to being offered to the market. • When short Term Firm ATC is posted for a given period: • The condition service of the CFS for that period: • Becomes firm service • Will be curtailed pro-rata with other firm transmission services.

  10. Conditional Firm Service • CFS will be charged the same price as LTFPTP transmission service as defined in Rate Schedule 01.

  11. Definitions: • Forecasted Period: means a 24-month period. • Current Forecasted Period: means a Forecasted Period starting from the month following. • Initial Forecasted Period: means the first Forecasted Period from the Start-date of a CFS Service Agreement Conditional Firm Service

  12. CFS ATC Methodology • Use Posted monthly Firm ATC as first year’s monthly Firm ATC. • Use the values obtained in #1 above as estimates for the second year’s monthly Firm ATC. • Using the calculated monthly Firm ATC, offer CFS as follows: • Monthly firm service amount equal to monthly Firm ATC • If the monthly Firm ATC is less than the capacity requested, offer monthly conditional service for the balance of requested capacity. Conditional Firm Service

  13. Conditional Firm Service • Total Firm Service and CFS commitments cannot exceed (TTC – TRM) • TTC ≥ TRM + Firm Commitments + CFS

  14. Conditional Firm Service • Example: • A 5-year request for 200 MW • TTC = 560 MW; TRM = 50 MW; F Commitment = 300 MW • Assumed posted monthly Firm ATC is 150 MW • Then offer a CFS with: • Monthly firm service amount = 150 MW; and • Monthly conditional service amount = 50 MW • TTC ≥ 50 + 300 + 150 + 50 = 550 • If TTC = 520 MW • Then offer a CFS with: • Monthly firm service amount = 150 MW; and • Monthly conditional service amount = 20 MW • TTC = 50 + 300 + 150 + 20 = 520

  15. Conditional Firm Service • Short-term Firm ATC • For US-BC, US-AB, BC-AB, AB-BC & paths • ST Firm ATC is mostly unaffected by system load • For examples: • AB-BC Path • Posted monthly Firm ATC is a constant 136 MW (except for months with scheduled maintenance) • BC-AB Path • Posted monthly Firm ATC is a constant 0 MW

  16. For BC-US Path • The monthly Firm ATC for Current Forecasted Period is determined as follows: • Using BC Hydro’s: • Forecast monthly loads • Forecast monthly generation dispatching pattern, and • Transmission system configuration. • Determining monthly firm transfer capabilities after allowing for the requirement of BC Hydro’s domestic customers • Determining month Firm ATC by subtracting existing firm commitments for the next 12 months. Conditional Firm Service

  17. For BC-US Path • To mitigate uncertainty risk in forecasting BC Hydro’s requirements for domestic customers, BC Hydro will adjust the monthly Firm ATC for CFS for the BC to US path as follows: • Set the monthly Firm ATC for CFS for the months of November, December, January and February to zero to account for the uncertain timing of the weather dependent system peak. • Reduce the monthly Firm ATC for CFS in the second year based on BC Hydro’s projected growth rate for integrated system demand. • Applicable to AB-US Path as well Conditional Firm Service

  18. Sample of Current Forecasted Period Monthly Firm ATC and CFS Conditional Firm Service Set to 0 3% below previous year level

  19. Sample of Monthly Firm ATC and CFS beyond Current Forecasted Period Conditional Firm Service

  20. CFS Service Offer Process • The approaches for option 1 and option 2 are the same for most part • The differences are related to BC-US and AB-US paths • Both paths include Interior to Lower Mainland system • ATC for these paths are dependent on load forecast Conditional Firm Service

  21. In response to a Completed Application, BC Hydro will tender to the Transmission Customer: • A Service Agreement for Partial Service and/or CFS as applicable; and • An applicable study agreement • Customer’s choices are: • Partial Service; or • CFS ( substitute service); or • Partial Service and study; or • CFS and study (*bridge service) • CFS serves as bridge service until: • NU are completed - if Customer commits to NU; or • All applicable studies are completed – if Customer doesn’t commit to NU Conditional Firm Service (Common Practices)

  22. BC-AB Path • Service queue and LT process are suspended • Service requests are in queue for LT firm service • Service requests stay in queue until End-date • If and when LT firm sale limit increases: • Firm ATC will be offered first-come first-served • CFS will be available only to the first 305 MW requests • For example: Conditional Firm Service (Common Practices)

  23. Biennial Assessment: • Provide assessment every 2 years • Provide results 90 days before effective date • If curtailment conditions are more stringent, Customer may terminate service • If curtailment conditions are less stringent or same, service is contractually bound • Additional assessment will be provided 30 days before roll-over deadline Conditional Firm Service (Common Practices)

  24. BC-US Path and AB-US Path (Example 2) • A Completed Application submitted on 2 April 2011 for Transmission Service on BC to US Path for 200 MW with service Start-date of 1 June 2011. In accordance with OATT timelines, BC Hydro must tender a study agreement or Service Agreement by 2 May 2011. At this time: • The Current Forecasted Period is from 1 June 2011 to 1 June 2013 • The Initial Forecasted Period for this request is from 1 June 2011 to 1 June 2013 • There is sufficient information for determining monthly firm service amount and monthly conditional service amount for all months within the Initial Forecasted Period • Assuming the projected growth for integrated system demand is 3% Conditional Firm Service (Option 1)

  25. Conditional Firm Service (Option 1) Example 2

  26. BC-US Path and AB-US Path (Example 3) • A Completed Application submitted on 2 April 2011 for Transmission Service on BC to US Path for 200 MW with service Start-date of 1 August 2011. In accordance with OATT timelines, BC Hydro must tender a study agreement or Service Agreement by 2 May 2011. At this time: • The Current Forecasted Period is from 1 June 2011 to 1 June 2013 • The Initial Forecasted Period for this request is from 1 August 2011 to 1 August 2013 • There is insufficient information for determining monthly firm service amount and monthly conditional service amount for all months within the Initial Forecasted Period • Assuming the projected growth for integrated system demand is 3% Conditional Firm Service (Option 1)

  27. Conditional Firm Service (Option 1) Example 3

  28. BC-US Path and AB-US Path • To provide certainty for firm service for months in the Initial Forecasted Period • Customers must specify in the Completed Application if they wish to have CFS as substitute service only • If not specify, follow LTPTP process and tender CFS as bridge service as required • Tender the CFS Service Agreement when the Current Forecasted Period coincides with the Initial Forecasted Period • Tender the CFS Service Agreement no earlier than one month prior to service Start-date except the Start-date is: • December, January, February or March Conditional Firm Service (Option 2)

  29. BC-US Path and AB-US Path (substitute service) • Example 5 • A Completed Application submitted on 2 April 2011 for Transmission Service on BC to US Path for 200 MW with service Start-date of 1 August 2011. The Transmission Customer has indicated in its Completed Application that it doesn’t want to commit to Network Upgrades In accordance with OATT timelines, BC Hydro must tender a study agreement or Service Agreement by 2 May 2011. At this time: • The Current Forecasted Period is from 1 June 2011 to 1 June 2013 • The Initial Forecasted Period for this request is from 1 August 2011 to 1 August 2013 • There is insufficient information for determining monthly firm service amount and monthly conditional service amount for all months within the Initial Forecasted Period Conditional Firm Service (Option 2)

  30. BC-US Path and AB-US Path (substitute service) • Example 5 • On May 2, 2011: • Tender a System Impact Study agreement • Projected study completion date is July 1, 2011 • On July 1, 2011: • Tender a Service Agreement for CFS as substitute • LTPTP process completed by July 16, 2011 Conditional Firm Service (Option 2)

  31. BC-US Path and AB-US Path • Example 6 • A Completed Application submitted on 2 April 2011 for Transmission Service on BC to US Path for 200 MW with service Start-date of 1 June 2011. The Transmission Customer does not indicate in its Completed Application that it doesn’t want to commit to Network Upgrades. In accordance with OATT timelines, BC Hydro must tender a Service Agreement by 2 May 2011. At this time: • The Current Forecasted Period is from 1 June 2011 to 1 June 2013 • The Initial Forecasted Period for this request is from 1 June 2011 to 1 June 2013 • There is sufficient information for determining monthly firm service amount and monthly conditional service amount for all months within the Initial Forecasted Period Conditional Firm Service (Option 2)

  32. BC-US Path and AB-US Path • Example 6 • On May 2, 2011: • Tender a System Impact Study agreement • Tender a Service Agreement for CFS • If only Service Agreement is executed, CFS is substitute service • If both agreements are executed: • CFS serves as bridge service • Studies will be performed Conditional Firm Service (Option 2)

  33. BC-US Path and AB-US Path • Example 6 • Tender a SA at the completion of all applicable studies • If SA is executed: • CFS continues as bridge service until NU are completed • Full service replaces CFS if NU are not required • If SA is not executed, CFS continues as substitute service Conditional Firm Service (Option 2)

  34. BC-US Path and AB-US Path • Example 7 • A Completed Application submitted on 2 April 2011 for Transmission Service on BC to US Path for 200 MW with service Start-date of 1 August 2012. The Transmission Customer does not indicate in its Completed Application that it doesn’t want to commit to Network Upgrades. In accordance with OATT timelines, BC Hydro must tender a Service Agreement by 2 May 2011. At this time: • The Current Forecasted Period is from 1 June 2011 to 1 June 2013 • The Initial Forecasted Period for this request is from 1 August 2012 to 1 August 2014 • There is insufficient information for determining monthly firm service amount and monthly conditional service amount for all months within the Initial Forecasted Period Conditional Firm Service (Option 2)

  35. BC-US Path and AB-US Path • Example 7 • On May 2, 2011: • Tender a System Impact Study agreement • No CFS is not offered at this time • If SIS is executed, studies will be performed • Tender a SA at the completion of all applicable studies • If SA is executed and NU completion is after Start-date: • Tender CFS as bridge service 30 days prior to Start-date Conditional Firm Service (Option 2)

  36. BC-US Path and AB-US Path • Biennial Assessment will be the same as option 1 • Completed 90 days before effective date • Will have zero firm service amount for month 23rd and 24th Conditional Firm Service (Option 2)

  37. BC-US Path and AB-US Path Conditional Firm Service (Option 1 vs. Option 2)

  38. BC-US Path and AB-US Path Conditional Firm Service (Option 1 vs. Option 2)

  39. Conditional Firm Service (Option 1 vs. Option 2)

  40. BC-US Path and AB-US Path • Competition with short-term service • Monthly ST service request can be for up to 11 months • 60 days prior to Start-date • Conditionally confirmed up to 30 days • 30 days prior to Start-date, ST request • Unconditionally confirmed • Cannot be displaced by Long-term • Less Firm ATC will be available for Long-term Conditional Firm Service (Option 2)

  41. Conditional Firm Service (Option 2)

  42. Conditional Firm Service Q & A

  43. Conditional Firm Service • Next Steps • Customers to provide comments to Brenda.Ambrosi@bchydro.com by February 18, 2011 • BC Hydro will post responses along with Customer comments on February 25, 2011 • BC Hydro will post the final CFS BP by March 11, 2011 • CFS BP becomes effective on April 1, 2011