Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope Instrument Flight Software LAT Monthly Sept 1, 2005 Terry Schalk U. C. Santa Cruz. FSW Status. FSW Short term goals Run calibration on the LAT with a FSW build OCT 1
E N D
Gamma-ray Large Area Space Telescope GLAST Large Area Telescope Instrument Flight Software LAT Monthly Sept 1, 2005 Terry Schalk U. C. Santa Cruz
FSW Status • FSW Short term goals • Run calibration on the LAT with a FSW build OCT 1 • Build will have all FSW functionality with a small number of well identified liens (eg GRB identification) • Engineering FQT during Sept with Formal FQT in Dec • Added configuration functionality last month and FSW packages have moved from imbedded data to this system • We now have the pieces for new build (V0-5-0) • Provide event output to SSR • Basic science data output format • Most remaining FSW packages under CCB control with this build
FSW Development and TestMilestones for FQT FSW Development Candidate Release 0-4-0 (includes CFG system) Science Data Output(Release 0-5-0) Releasefor Testing(Release 0-6-0) GRB and Compression(Release 0-7-0) ΔTRR TRR 7/20 8/15 9/8 9/15, 9/20 9/30 10/1 11/18 {I&T SystemTest} Procedure ReviewComplete Scripts Complete FQT Complete FSW Test FSW Status Review
FSW TRR Preparation • Documentation • Specification: Baselined, final updates to CCB 9/6 • Test Plan: Baselined, final updates to CCB 9/6 • Test Procedures: 48 for System Checkout phase baselined. 7 more (GRB-related) to be baselined prior to System Test. • Design Document: Draft complete • FSW-ISOC ICD: In work • Telecommand and Telemetry Formats: Autogenerated after each integrated build. Will rebaseline prior to FSW testing supporting System Checkout phase • RFAs • 1 of 6 Flight Unit Peer Review RFAs closed • Responses to remaining 5 provided and awaiting closure
TRR Preparation - SQA Documentation • Action plan resulting from various internal & external reviews • Update and approve MD-00091 Quality Manual • Incorporate relevant parts of MD-00474 Internal Quality Audits • MD-00216 Controlled Document Release Procedure superseded by CM Plan. Remove reference from Quality Manual. • Update MD-00472 Corrective & Preventive Action to clarify that JIRA is FSW database and approve • Update Software Mgmt. Plan to reflect current management structure • Corrective action status • All items in progress • ECD 9/2 for changes • ECD 9/9 for approval
July Activities • Incorporated configuration parameters into all relevant pkgs • Built filter's infrastructure for calorimeter pedestal, gains and geometry files • Finished the preliminary event output format definitions • high energy Gamma are about 500-600 compressed bytes. • Delivered code to write data to the SSR • "Finished" the LATC design document • Finished testing LIM’s modes. • Started discussions on operational usage issues
July Activities • Worked on a number of bug fixes • Identified flaw in LCI compaction routines (& reduced footprint to ~7MB. ) • Worked on FES firm/soft ware bugs wrt testing of the calibration code • Debugged an issue in the RING buffers • Debugged an issue with the Thermal code running at lockheed
FSW Outstanding Issues • CR 0-5-0 needs to be made with pkgs exercising the SSR path • Completion of high priority Lien list items • GRB identification • Finish any missing event formats • Finish event compression if needed • Discovered bugs need to be addressed and CR 0-6-0 made to run system checkout TTR and FQT against. • Gain operational experience and address any high priority issues