1 / 10

ISO-NE Offer Review: Generation Costs and Cost of Capital Update

This presentation provides an update on the ISO-NE offer review, focusing on generation costs, cost of capital, and revenue offsets. The update includes information on energy efficiency and demand response, as well as a response to stakeholder comments.

kempk
Download Presentation

ISO-NE Offer Review: Generation Costs and Cost of Capital Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ISO-NE Offer Review Trigger Price 2013 Update: Project Update Presented to: NEPOOL Markets Committee Presented by: Sam Newell July 10, 2013

  2. Agenda Approach Update and Response to Stakeholder Comments • Energy Efficiency and Demand Response • Generation Costs • Cost of Capital • CONE Calculations • Revenue Offsets and Net CONE • Next Steps

  3. Energy Efficiency and Demand Response • For EE, follow similar approach to previous ORTP by reviewing state programs’ cost effectiveness studies • Rely on the studies’ cost data and MWh savings • We will estimate the value of energy savings • For DR, estimate costs for “large C&I” and “mass market” • Large C&I: interviewed merchant DR providers • Assume 1 to 4 MW peak load • The primary cost is sharing 60-80% of capacity revenues with retail customers • For ORTP, assume this cost stays constant in dollar terms, at about $2/kW-mo • Mass Market: rely on a variety of sources

  4. Generation Costs • Developing capital and fixed O&M costs for reference plants of these technologies • Simple Cycle Combustion Turbine (GE LMS100) • Combined Cycle Gas Turbine (Siemens SGT6-5000F) • Biomass (Bubbling Fluidized Bed) • On-Shore Wind • Assume a competitive entrant at an unencumbered site • Assume interconnection costs similar to actual entrants, based on system impact studies • For annual updates, ISO-NE would index individual cost components to widely available indices

  5. Response to Stakeholder Comments on Generation Costs • Response to Comments • Researched Solar and Off-Shore Wind but found to still have high capital costs with potential ORTP values well above FCA starting price • Existing CC technologies should be competitively priced and have performance characteristics that would be compatible with ISO-NE’s “Performance Incentives” proposal • Dual fuel storage capacity varies, but enough for 3 days of operation is somewhat typical and a reasonable assumption • Wind interconnection costs from system impact studies show substation upgrades but limited network upgrades, at least for past and current projects

  6. Cost of Capital • We are estimating the cost of capital based on market data for merchant generators • Assume a PPA on energy revenues only (not capacity), as implied by the tariff • PPA assumption partially reduces ATWACC relative to mostly-unhedged merchant generators but won’t reduce the ATWACC as low as those of regulated utilities • We will present a range but will focus on the low end of merchant companies’ ATWACCs, reflecting the energy-PPA assumption • We will include a 75 bp upward adjustment on the risk-free rate used in the CAPM determination of the cost of equity, due to temporary depression from Fed “quantitative easing” policy

  7. CONE Calculations • The Cost of New Entry (“CONE”) is the net revenue a new resource would need in Year 1 to be willing to enter the market, such that the NPV of all cash flows (over 20 years) is zero • A key driver of CONE is whether total net revenues are likely to increase over time (such that lower first year revenues are acceptable) or decrease (such that higher first-year revenues are necessary) • Long-term revenues will be determined by future prices (energy + capacity + other) which, all-in, must equal CONE of future entrants to support investment • Hence, projected cost trends determine revenue trajectories for current entrants • Also need to consider performance differences between current and future units • Revenue trajectories may vary by technology • We assume total revenues for gas entrants will be approximately constant in real terms over time • We are still considering the possibility that total revenues for renewables might decline over time as technology develops, which would increase the amount of revenue a new entrant would need in year 1

  8. Revenue Offsets and Net CONE • First year revenues must equal CONE, with revenues coming from several sources, including capacity, energy and ancillary services margins (EAS), and RECs if applicable • “Net CONE” is the 1st year revenue a new resource would need specifically from capacity to be willing to enter the market • Net CONE = CONE – 1st Year Non-Capacity Revenue Offsets • ORTP is Net CONE of a competitive entrant for each technology • Calculating 1st year non-capacity revenue offsets: • 1st year EAS margins will be calculated based on historical average net revenues for like units, adjusted to a 2018/19 forward value based on futures prices • 1st year REC prices will be estimated using the most forward-looking prices available in New England markets, currently 2016

  9. Response to Comments on Revenue Offsets • The tariff does not specify a methodology for calculating EAS offsets • How does the EAS offset relate to the PPA assumption? • Our EAS estimate will approximate a “forward” value that should be less than expected spot value, consistent with the PPA assumption • The lower forward EAS offset combined with an ATWACC that accounts for an energy-only PPA should produce the same Net CONE as without a PPA • We are assuming continuation of PTC; this assumption can be modified easily in future annual updates • We are still reviewing whether and how to estimate “Performance Incentive” payments/penalties for the various resource types

  10. Next Steps • Calculate bottom up Net CONE estimates for identified technologies • Develop draft report describing ORTP calculations to be reviewed with MC at August meeting • ISO-NE to develop revised Tariff language incorporating recommended ORTPs and indexing methodology to be reviewed with the MC at August meeting

More Related