An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PMT Bases • PMT bases for DU 1 already available • Tender already finish, PRR done and production on going

  2. Octopus • 50 sets arriving in August • Mass production • Components already ordered • PCB production still to be approved • KVI negotiating to have the first batch of mass production by October. Another possibility under study is to increase to 75 the batch of 50

  3. CLB • Production of 38 CLBs to be launched this/next week • 38 FPGA available • Octopus connectors available • AHRS? • Funding available (INFN/Nikhef) • Clear layout modifications? • To be produced, if possible, by the same company that has won the CLB tender.

  4. CLB • Mass Production: • Tender almost finished: Purchase of components will start in a few weeks. • 400 FPGAs to arrive by beginning September • The real dead line: Final gerbers to be provided by then.

  5. PB • Production of 40 PB to be launched this/next week • PBv2.3 tests OK? • Funding available (INFN/Nikhef) • To be produced, if possible, also by the same company that has won the CLB tender.

  6. PB • Mass Production: • BOM file and gerbers of last PB versionto be providedthis/nextweekto INFN tostartthepurchasingprocess. Purchase of componentswillstartasap. • Note: Monitoringcomponentsshould be removed fromthe BOM file. • Green ligthforproduction can be given as soon as PBv2.3 isfullyvalidated -> End of July?? • To be produced, if possible, also by the same company that has won the CLB tender.

  7. PRR • End of July?: Depending only on the status of the documentation.(Only for PB, CLB, Octopus and Nanobeacon) • Required tests (1/2 DOM, EMC, climate, etc) results to be included on the PRR documentation only if possible. • Real deadline for tests: Start of CLB production (Beginning September)