Update of Downtown Rail Improvements DFWI & Chamber Stakeholders February 26, 2014 Alonzo Liñán, PE, PTOE City of Fort Worth
Agenda Tower 55 Live Oak Connector 9th Street Crossing Questions…
Tower 55 TIGER Grant • Goal Increase Economic Productivity • Improve Community Livability • Improve Environmental Sustainability • Impact • Add train capacity • Reduce train and vehicle congestion • Close two (2) crossings (BNSF & East 1st and BNSF & Peach Street) • Reconstruct two (2) crossings (BNSF & Gounah and BNSF & Cold Springs) • Improved pedestrian mobility and safety • Sidewalks, Streetlights, Fencing • Install traffic signals at Hampton and Belknap • Improved Air Quality Conditions
Tower 55 • Two BNSF Rail Bridge Improvements • Cold Springs • Gounah • Two BNSF Rail Crossing Closures • Peach Street • East 1st
Existing Crossing Closures • BNSF & 1st Street • BNSF & Peach Street
Cold Springs Overpass Reconstruction Before Before After
Gounah St. Overpass Reconstruction Before Before After
Sidewalk Network Gounah Peach
3rd St Accessibility • Existing sidewalk at 3rd St underpass • No Improvements proposed
East Lancaster St. Bridges • Built in 1906 (est) • UP led work • Rehabilitate abutment wall • Encapsulate center posts with micro piles • Re-deck entire structure • Local partners coordination for detours and traffic control
Live Oak Connector • Goal • New street construction for reliable neighborhood access • Impact • Construct Live Oak Street from 1st to 4th St • Close (2) UPRR crossings (E 1st and Peach) • Construct fencing on both sides of track • Project still underway
9th Street Crossing • Discussions to Date • Reopen at-grade RR crossing • Leave as is (closed) • Considerations • Businesses are restricted • Quiet Zone/Horns • Staging of trains • Number of trains
Schedule Updates Tower 55 Anticipated substantial completion date – September 2014 Crossing Closures – Late July 2014 1st Street and Peach Street In advance of school year to ensure safe traffic flows Grade separations – Complete Mid-June 2014 Gounah Street – May 1st target completion Cold Springs Road – June 1st target completion Live Oak Plans nearing completion Expect construction to be done by end of 2015 9th Street Pending Land Owner Discussions
Questions? DFWI & Chamber Stakeholders February 26, 2014