Northstar Commuter Rail Project Update. Mark Fuhrmann, Project Director Rich Rovang, Deputy Project Director, Design and Construction Chris Weyer, Assistant Director of Design and Construction Metropolitan Council June 25, 2008. Northstar Budget Status. Northstar Funding Status. ($X,000).
E N D
Northstar Commuter Rail Project Update Mark Fuhrmann, Project Director Rich Rovang, Deputy Project Director, Design and Construction Chris Weyer, Assistant Director of Design and Construction Metropolitan Council June 25, 2008
Northstar Funding Status ($X,000)
Northstar Contingency Status Through May 30, 2008 – All figures in year of expenditure dollars Hold Points: 20%: $21.8MM 50%: $15.2MM 75%: $6.8MM 90% $4.5MM
Vertical Circulation BuildingConstructed by the Ballpark Authority