Elementary School #33. Elementary School #33. Board approval in 2006 Funding 2002 Bond 2005 Bond Location Camino A Lago Meadows. Opening Date – 2014 versus 2015. 2014 Opening Considerations Construction costs Committee support Enrollment stabilization Challenges Alternate location
E N D
Elementary School #33 • Board approval in 2006 • Funding • 2002 Bond • 2005 Bond • Location • Camino A Lago • Meadows
Opening Date – 2014 versus 2015 • 2014 Opening Considerations • Construction costs • Committee support • Enrollment stabilization • Challenges • Alternate location • Budgeting considerations • New Request For Proposal (RFP) requirements for Construction Manager (CM) at Risk • Compressed timeline
Opening Date – 2014 versus 2015 • 2015 Opening Considerations • More time for review and development of school design • More time to ready fixtures and furnishings upon completion • Challenges • More than one move for some students
Design Options • Proceed with 2008 design • Review prototypes from approved architects • Design committee to work with architect to develop site plans and make recommendations to Board