Objective FCM05. ESSIP Plan 2014. Octavian CIOARA DPS/PEPR 19.09.2014. Objective FCM05. Comprehensive Explanation What is new or has changed since LSSIP 2013 Link to European ATM Master Plan Finalisation Criteria and Closed Questions ESSIP Report 2013
E N D
Objective FCM05 ESSIP Plan 2014 Octavian CIOARA DPS/PEPR 19.09.2014
Objective FCM05 • Comprehensive Explanation • What is new or has changed since LSSIP 2013 • Link to European ATM Master Plan • Finalisation Criteria and Closed Questions • ESSIP Report 2013 • Objective Coordinator’s Analysis, recommendations, tips & tricks • Links and contacts ESSIP Plan 2014 / Objective FCM05
Comprehensive Explanation • Area of applicability: All ECAC • Initial Operational Capability (IOC): 09/2013Full Operational Capability (FOC): 12/2016 • The objective will ensure the improvement of B2B exchanges between local ASM tools and NM • Implementation will provide enhanced NOP capabilities (ADR, DDR2, Flight Plan filling...) • Most of the activities are part of the Interim Deployment Programme – IDP ESSIP Plan 2014 / Overview LSSIP 2013
What is new or has changed since LSSIP 2013 • Nothing. ESSIP Plan 2014 / Overview LSSIP 2013
Link to European ATM Master Plan Objective FCM05 covers the following SESAR OI steps: • OI Step – [AOM-0205] – Modular Temporary Airspace Structures and Reserved Areas • OI step - [DCB-0102] – Interactive Rolling NOP ESSIP Plan 2014 / Overview LSSIP 2013
Most important SLoA(s) • FCM05-ASP01 – Upgrade the automated ASM support system with the capability of AIXM 5.1 B2B data exchange with NM • FCM05-ASP02 – Perform an integration of the automated ASM support systems with the Network • Each SLoA should be fulfilled in accordance with the relevant provisions of the NM B2B Reference Manuals ESSIP Plan 2014 / Overview LSSIP 2013
Finalisation Criteria and Closed Questions Finalisation criteria: • Contact your subject matter expert to determine the deployment Status for each SloA Closed questions: • Closed Questions have been introduced for this Objective • Statements on Deployment Status should provide answersto Closed Questions ESSIP Plan 2014 / Overview LSSIP 2013
ESSIP Report 2013 • The submitted reports indicate that the objective will be implemented in time by the relevant stakeholders. However, as this is a new objective, there is still a high proportion of States having reported -No Plan-, therefore it is still premature to identify clear trends with regard the implementation progress. ESSIP Plan 2014 / Overview LSSIP 2013
Objective Coordinator’s Analysis, recommendations, tips & tricks • Ensure that your subject matter expert is involvement once you make your statement. • Information provided per SLoA can be easily verified by checking the provisions laid down in the supporting material. • Attention to the applicability to the Military stakeholders as airspace users. • Objective also related to AOM19 ESSIP Plan 2014 / Overview LSSIP 2013
Links and contacts Objective Coordinator: Octavian CIOARA +32 2 729 3282 octavian.cioara@eurocontrol.int NMD Objective Expert: Nil AGACDIKEN +32 2 729 3073 nil.agacdiken@eurocontrol.int ESSIP Plan 2014 / Overview LSSIP 2013